Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/13/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/13/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10326 issued 10-13-04 to Hastings in the Country Square Shopping Center.
|
Agreement of Future work | 2/21/2001 | 1/31/2005 | 10/1/2004 | | PASS |
Jason Blais
|
|
|
Upgrade Agreement work throughout entire shopping center completed.
|
FIRE-Final Inspection | 9/28/2004 | 10/1/2004 | 10/1/2004 | A | CANC |
Troy Cobbley
|
|
|
duplicate inspection 10/1/2004 11:15:44 AM
|
BLD-Final | 9/30/2004 | 10/1/2004 | 10/1/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/30/2004 at 1:15:21 PM. Contact: ###-####. final ok no card. 10/1/2004 2:53:26 PM
|
FIRE-Final Inspection | 10/1/2004 | 10/1/2004 | 10/1/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
Permanent Occupancy | | 10/1/2004 | 10/1/2004 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/24/2004 | 9/27/2004 | 9/27/2004 | P | FAIL |
Troy Cobbley
|
|
|
Various locations still have insulation laying on sprinkler uprights and some heads have been painted. Pete has locations on his list. 9/27/2004 3:02:26 PM
|
FIRE-Final Inspection | 4/19/2004 | 4/20/2004 | 4/20/2004 | P | PART |
Troy Cobbley
|
|
|
insulation modifications in Rocky Mountain Fitness have been completed except for one up right sprinkler head over the cycling area 4/20/2004 2:33:34 PM
|
FIRE-Conference | 3/31/2004 | 4/5/2004 | 4/5/2004 | P | DONE |
Troy Cobbley
|
|
|
Inspection was for the east one third of the Rocky Mountain Fitness tenant. Insulation is ok 4/6/2004 8:15:38 AM
|
FIRE-Conference | 3/31/2004 | 4/5/2004 | 4/5/2004 | P | DONE |
Troy Cobbley
|
|
|
Inspection was for the east one third of the Rocky Mountain Fitness tenant. Insulation is ok 4/6/2004 8:15:38 AM
|
FIRE-Final Inspection | 3/29/2004 | 3/30/2004 | 3/30/2004 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the insulation modifications that are taking place throughout the entire strip mall. Inspected today was the old paint store at the east end and the west third of Rocky Mountain Fitness. Insulation looks ok in these areas. 3/30/2004 4:05:20 PM
|
BLD-Conference | 1/20/2004 | 1/20/2004 | 1/20/2004 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for approval of the insulation attachment. The insulation still needs attached in certain areas. Needs to be re-inspected
|
FIRE-Final Inspection | 10/6/2003 | 10/6/2003 | 10/6/2003 | P | FAIL |
Rick Jackson
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Annette Moore the only items left are the two "troubles" on the fire alarm panel - one in Hastings and the other in Bangkok duct detectors 10/6/2003 1:29:11 PM
|
BLD-Final | 10/6/2003 | 10/6/2003 | 10/6/2003 | P | CANC |
Tom Arcoraci
|
|
|
JIM; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
FIRE-Final Inspection | 9/30/2003 | 9/30/2003 | 9/30/2003 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 9/30/2003 2:22:26 PM
|
BLD-Final | 9/30/2003 | 9/30/2003 | 9/30/2003 | P | NH |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/30/2003 at 9:49:11 AM. Contact: ###-####. needs fire sign off 9/30/2003 4:07:24 PM
|
FIRE-Final Inspection | 9/30/2003 | 9/30/2003 | 9/30/2003 | P | FAIL |
Troy Cobbley
|
|
|
Correct exit sign near rear stock room(it should point to the east exit), Post occupancy load signs, verify annual sprinkler inspection, final sprinklers
|
FIRE-Final Inspection | 9/18/2003 | 9/18/2003 | 9/18/2003 | P | FAIL |
Troy Cobbley
|
|
|
jim; Phone #: ###-#### I stopped at the job site after not being able to contact the general contractor but was unable to due the inspection. 9/18/2003 3:35:49 PM
|
BLD-Final | 9/18/2003 | 9/18/2003 | 9/18/2003 | P | CANC |
Jim Storey
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marc Lileks fire not complet for temp occ waiting for previous fir c/n no insp performed. 9/18/2003 3:54:09 PM
|
FIRE-Conference | 8/29/2003 | 8/29/2003 | 8/29/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 8/29/2003 at 12:46:40 AM. Contact: ###-####. Troy did the inspection and it is okay to cover areas per conversation with GC 8/29/2003 3:48:52 PM
|
FIRE-Conference | 8/28/2003 | 8/28/2003 | 8/28/2003 | A | DONE |
Troy Cobbley
|
|
|
I inspected more of the insulation attachments so ceiling tile could be put in and went over door hardware issues with Jim with Steed Construction 8/28/2003 2:52:55 PM
|
BLD-Framing/Rough-in | 8/25/2003 | 8/26/2003 | 8/26/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/25/2003 at 4:43:26 PM. Contact: ###-####.
|
FIRE-Conference | 8/25/2003 | 8/26/2003 | 8/26/2003 | A | PART |
Troy Cobbley
|
|
|
Conference was to discuss the attachments that are being used to keep the insulation above the existing sprinkler piping . Most of what I was shown will work but there were some problem areas that Jim with Steed was going to fix. Per Dave Miller once Hastings is complete it will be OK to sign a temp occupancy until the rest of the strip mall has the insulation issue taken care of 8/27/2003 9:02:25 AM
|
BLD-Framing/Rough-in | 8/21/2003 | 8/21/2003 | 8/21/2003 | P | PART |
Russ Owen
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marc Lileks. ok 8/21/2003 3:24:21 PM
|
BLD-Framing/Rough-in | 8/19/2003 | 8/20/2003 | 8/20/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/19/2003 at 12:38:58 PM. Contact: ###-####.brace the soffit . walls ok. contractor on site will recall. 8/20/2003 4:34:08 PM
|
BLD-Framing/Rough-in | 8/15/2003 | 8/18/2003 | 8/18/2003 | A | FAIL |
Russ Owen
|
|
|
curtis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylieposted c/n. 8/19/2003 9:50:58 AM
|
Plan assigned to (JCB) | 6/10/2003 | | 8/11/2003 | | PASS |
Jason Blais
|
|
|
8/11/2003 09:38:46 JCB - activity updated through activity BLDA022 from case BLD03-01324.
|
Routing - PLAN CHECK | 8/8/2003 | | 8/11/2003 | | PASS |
|
|
|
Plans and permit approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/11/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/11/2003 | | DONE |
|
|
|
|
Telephone call | | | 8/11/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 8/11/2003 | | DONE |
|
|
|
|
Telephone call | | | 8/7/2003 | | DONE |
|
|
|
telcon with Dennis Potter
|
Routing - PLAN CHECK | 7/14/2003 | | 8/6/2003 | | FAIL |
|
|
|
Two items to be addressed. Architect rep. will be contacted. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 8/6/2003 | | 8/6/2003 | | PASS |
|
|
|
Restroom added on resubmittal sheets.
|
Plan resubmittals received | | | 7/29/2003 | | DONE |
|
|
|
Received two copies of revised sheets A-1, A2.1, A2.2, A-2.3, A-3, A-5, D-1, F-1, M-1, DE-1, E-1, E-2, P-1,P-2 and two copies of response to plan review. Routed to Jason B. kmm
|
Routing - FIRE | 7/8/2003 | | 7/11/2003 | | FAIL |
|
|
|
Conditions of an existing upgrade agreement on file relative to this tenant space have not been met. Plans shall show the corrections required per that agreement.
|
Routing - PLAN CHECK | 6/16/2003 | | 7/8/2003 | | FAIL |
|
|
|
Plan review sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept.
|
Plan resubmittals requested | | | 7/8/2003 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PUBLIC WORKS | 6/10/2003 | | 6/13/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/10/2003 | | DONE |
|
|
|
three copies of E-3 and taken to jason
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2003 | | DONE |
|
|
|
Per Ron H. kmm Three energy sheets should be coming.
|
Application received | | | 6/6/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/6/2003 | | DONE |
|
|
|
|
Routing - PLUMBING | 6/13/2003 | | 3/16/2003 | | PASS |
|
|
|
additional cross connection protection may be required, water heaters located 8' or more above finish floor must be provided with a perminently fastened ladder, if an automatic soap dispensor is installed at the mop sink, provide a water supply for it, **BFP-dual check backflow preventors are not an approved cross connection device in the city of Boise.
|
Routing - FIRE | 8/6/2003 | | 8/8/2002 | | PASS |
|
|
|
Approved with conditions related to the overdue shopping center fire sprinkler upgrade agreement. See permit scope of work and IFC plan review comment # 2.
|
Fee Review-notes | 6/6/2003 | 6/6/2003 | | | |
|
|
|
|