BLD-Final | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | DONE |
Jim Sly
|
|
|
EXP.
|
DOC - Permit Expired | 4/12/2006 | 4/12/2006 | 4/12/2006 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 8/6/2003 | 8/7/2003 | 8/7/2003 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
(F) Reprint permit | | | 7/22/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/21/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/21/2003 | | DONE |
|
|
|
permit ready and fees due
|
Issue PAID IN FULL permit | | | 7/21/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/18/2003 | | 7/18/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/18/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/18/2003 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 6/30/2003 | | 7/18/2003 | | PASS |
Mike Phillips
|
|
|
7/18/2003 14:17:32 M_P - activity updated through activity BLDA022 from case BLD03-01418.
|
Routing - FIRE | 7/15/2003 | | 7/17/2003 | | PASS |
|
|
|
Approved with no written comments
|
Print permit w/o conditions | | | 7/15/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 6/30/2003 | | 7/15/2003 | | FAIL |
|
|
|
Plan review completed, need structural calculations for design of footing and information about existing exiting into and through new canopy. Called contractor and left message for him to call me.
|
Routing - Erosion and Sediment | 6/27/2003 | | 6/30/2003 | | DONE |
|
|
|
No ESC required.
|
Routing - PUBLIC WORKS | 6/26/2003 | | 6/27/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/16/2003 | | FAIL |
|
|
|
Called Joe and told him we needed two site plans stamped and signed, Erosion permit application filled out, he stated that he may want to file a waiver letter instruction where given on how to do so. No Civil required per Jim W. Plans placed in hold box.
|
Application received | | | 6/12/2003 | | |
|
|
|
|
Routing - PLANNING | 6/30/2003 | | 6/30/2002 | | PASS |
|
|
|
Approved per CZC03-00057.
|