Case Summary (BLD) | | | 12/16/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/22/2008 | | DONE |
|
|
|
|
Third Notice BLD | 1/20/2006 | 1/20/2006 | 4/6/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 3/31/2006 | | DONE |
|
|
|
tlk t jim cox said that Rick Cummins in charge of the final - I talked to rick ###-#### and fax him the notice for final values 3/31 1:57 pm
|
Second Notice BLD | 1/3/2006 | 1/3/2006 | 1/20/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/21/2005 | 1/3/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 12/21/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10849 issued 12-21-05 to the West Boise Wastewater Treatment Plant.
|
BLD-Final | 12/14/2005 | 12/15/2005 | 12/15/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/14/2005 at 2:15:40 PM. Contact: ###-####. OK for perm occ ():
|
Permanent Occupancy | | 12/15/2005 | 12/15/2005 | | DONE |
|
|
|
|
BLD-Final | 12/7/2005 | 12/8/2005 | 12/8/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/7/2005 at 1:40:32 PM. Contact: ###-####. Need Final affidavit from MTI
|
Second Notice BLD | 9/20/2005 | 9/20/2005 | 9/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/5/2005 | 9/20/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/11/2005 | 8/12/2005 | 8/12/2005 | A | PASS |
Troy Cobbley
|
|
|
rick ; Phone #: ###-#### Permit finaled. Per Rick the materials passed through the building and contained inside do not meet the definitions of hazardous materials per the msds sheets.
|
CHANGE STATUS TO (ISS) | | | 8/11/2005 | | DONE |
|
|
|
not fn yet for fire fn or bld fn
|
FIRE-Final Inspection | 8/4/2005 | 8/5/2005 | 8/5/2005 | A | FAIL |
Troy Cobbley
|
|
|
rick; Phone #: ###-#### No approved plans or notes on site. I talked to Rick about fire extinguisher requirements.
|
Code Occupancy Approval | | | 8/5/2005 | | PASS |
|
|
|
|
Print Occupancy Form | | | 8/2/2005 | | DONE |
|
|
|
|
BLD-Conference | 1/19/2005 | 1/20/2005 | 1/20/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/19/2005 at 9:59:02 AM. Contact: ###-####. Discusses stairways handrails etc with Rick. 1/20/2005 11:29:08 AM
|
BLD-Conference | 12/3/2004 | 12/6/2004 | 12/6/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/3/2004 at 1:45:25 PM. Contact: ###-####.
|
BLD-Conference | 10/21/2004 | 10/25/2004 | 10/25/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/21/2004 at 9:44:54 AM. Contact: ###-####. Met with Rick C. Talked about Special insp and tests from MTI. Rick and Engineer of record have been reviewing Special insp reports.....so far there have been no descrepancies.....Looked at Control Bldg....OK to insulate and Side (steel) Need to have plumbing and HVAC inspection on control Bldg. 10/25/2004 11:15:56 AM
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PART |
Jim Sly
|
|
|
WIP 8/4/2004 6:22:54 PM
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PART |
Jim Sly
|
|
|
WIP 8/4/2004 6:22:38 PM
|
BLD-Wall cover | 4/13/2004 | 4/13/2004 | 4/13/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/13/2004 at 7:46:09 AM. Starting CMU walls... MTI on site for special insp. 4/13/2004 4:07:23 PM 4/13/2004 4:16:56 PM
|
BLD-Concrete | 3/10/2004 | 3/10/2004 | 3/10/2004 | P | PART |
Jim Sly
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Darla Downs PLEASE CALL FIRST 3/10/2004 4:09:21 PM E. wall of main Bldg. OK Pend tests and approvals for compression. 3/10/2004 4:36:45 PM
|
BLD-Concrete | 2/18/2004 | 2/19/2004 | 2/19/2004 | A | PART |
Jim Sly
|
|
|
###-#### Rick Wall insp. 2/19/2004 12:21:44 PM
|
Override - Parcel Holds | | | 2/18/2004 | | |
|
|
|
|
BLD-Concrete | 12/18/2003 | 12/19/2003 | 12/19/2003 | A | PART |
Tom Arcoraci
|
|
|
wip spec insp 12/19/2003 8:27:46 AM
|
Override - Parcel Holds | | | 12/18/2003 | | |
|
|
|
|
BLD-Concrete | 11/28/2003 | 12/1/2003 | 12/1/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/28/2003 at 3:40:02 PM. 1st approx 4' of walls OK pending special insp. reports and approvals. 12/1/2003 11:11:23 AM
|
BLD-Foundation | 11/13/2003 | 11/14/2003 | 11/14/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/13/2003 at 11:44:47 AM. Contact: ###-####. Talked with George about approval of Rick Cummings, a Public Works employee, as a reinforced concrete (special) inspector for this project. George OK'd. We have Boise City structural inspections and third party inspections from MTI for test samples and all req (other) special inspections for project. I verified Rick's certification for reinforced concrete.... ICC # XX4141006233. Footing OK pending special insp reports and approvals. 11/14/2003 10:29:46 AM 11/14/2003 10:33:57 AM
|
BLD-Conference | 11/5/2003 | 11/12/2003 | 11/12/2003 | P | PASS |
Jim Sly
|
|
|
###-#### Craig; Phone #: ###-#### x3684 Internet Inspection Request from: Aimee Hughes Met with Craig and Rick Cummings......discussion of special insp req. and proceedures. 11/12/2003 4:06:29 PM
|
Issue PAID IN FULL permit | | | 9/30/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/29/2003 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 9/25/2003 | | DONE |
|
|
|
Removed parcel hold. Property has been anexed into the city. Ok to issue permit per Scott Spjute.
|
Inspection Record Card- Bld | | | 9/25/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/25/2003 | | |
|
|
|
|
Telephone call | | | 9/25/2003 | | DONE |
|
|
|
left mess for rob that permit is ready
|
Routing - PLAN CHECK | 8/29/2003 | | 9/24/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 9/24/2003 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/24/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/24/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/24/2003 | | DONE |
|
|
|
received certificate of value, taken to Mike P.
|
Plan assigned to (M_P) | 6/18/2003 | | 9/24/2003 | | PASS |
Mike Phillips
|
|
|
9/24/2003 10:52:12 M_P - activity updated through activity BLDA022 from case BLD03-01484.
|
Routing Off Site - STRUCTURAL | 8/29/2003 | | 9/16/2003 | | PASS |
|
|
|
Contacted PDQ to take resubmittals of 8/15/03, clacls, comment 24 response, addendum #1, addendum#2, and addendum #3 to outside engineering. kmm
|
Routing - PLAN CHECK | 7/24/2003 | | 8/29/2003 | | PEND |
|
|
|
Waiting for outside engineering firms approval prior to issuing permit.
Waiting for annexation to be approved prior to issuning permit.
|
Plan resubmittals received | | | 8/18/2003 | | DONE |
|
|
|
Received one copy of response letter and comment 24 response, three copies of supplemental structural claculations and three copies of Addendum no. 1. Routed to Mike P. kmm
|
Routing - FIRE | 7/17/2003 | | 7/23/2003 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 7/17/2003 | | |
|
|
|
|
Print permit w/o conditions | | | 7/17/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 7/2/2003 | | 7/17/2003 | | FAIL |
|
|
|
Plan review completed, sent copy of correction report to engineer requesting additional information be submitted for further review prior to issuing permit.
|
Routing Off Site - STRUCTURAL | 6/19/2003 | | 7/10/2003 | | FAIL |
|
|
|
contacted PDQ to take plans to outside engineering.
Additional information requireed to be submitted for further review. MJP
|
Routing - PLUMBING | 7/1/2003 | | 7/1/2003 | | PASS |
|
|
|
per plans and 2000 upc
|
Routing - PLANNING | 6/30/2003 | | 7/1/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 6/26/2003 | | 6/30/2003 | | PASS |
|
|
|
ESC Waiver approved with attached conditions.
|
Routing - PUBLIC WORKS | 6/19/2003 | | 6/26/2003 | | PASS |
Brandi Dominguez
|
|
|
|
Routing - PLANNING Land Div | 6/19/2003 | | 6/19/2003 | | PASS |
|
|
|
Approved, parcel is over 5 acres in size.
|
Plan routing begun/TENANTS | | | 6/19/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/19/2003 | | DONE |
|
|
|
|
Application received | | | 6/18/2003 | | |
|
|
|
|
Fee Review-notes | 6/18/2003 | 6/18/2003 | | | |
|
|
|
|