First Notice | | 8/12/2003 | 8/12/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/8/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9759 issued 8-8-03 to Policy Studies.
|
BLD-Final | 8/4/2003 | 8/5/2003 | 8/5/2003 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/4/2003 at 11:08:00 AM. Contact: ###-####. Ok for a perm oc. 8/5/2003 10:04:07 AM
|
Permanent Occupancy | | 8/5/2003 | 8/5/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/5/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4981 issued 8-5-03 to Policy Studies.
|
FIRE-Final Inspection | 8/4/2003 | 8/4/2003 | 8/4/2003 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 8/4/2003 3:43:57 PM
|
FIRE-Final Inspection | 7/31/2003 | 8/1/2003 | 8/1/2003 | A | FAIL |
Troy Cobbley
|
|
|
fire alarm system failed. Provide map at the facp and signage on the riser room door. When the fire alarm is ready to go all life safety items are ok 8/1/2003 11:33:21 AM 8/1/2003 11:35:24 AM
|
FIRE-Alarm Testing | 7/31/2003 | 8/1/2003 | 8/1/2003 | A | FAIL |
Troy Cobbley
|
|
|
fire alarm system failed. Provide map at the facp and signage on the riser room door. When the fire alarm is ready to go all life safety items are ok 8/1/2003 11:33:21 AM 8/1/2003 11:35:33 AM
|
BLD-Other | 7/22/2003 | 7/22/2003 | 7/22/2003 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 7/22/2003 at 7:06:55 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/7/2003 | 7/8/2003 | 7/8/2003 | A | PASS |
Russ Owen
|
|
|
Mike ###-####
|
Plan assigned to (R_H) | 6/23/2003 | | 7/7/2003 | | PASS |
|
|
|
7/7/2003 09:07:51 RMH - activity updated through activity BLDA022 from case BLD03-01513.
|
Routing - PLAN CHECK | 6/25/2003 | | 7/7/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/7/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/7/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/7/2003 | | DONE |
|
|
|
|
Issue & PRINT permit | | | 7/7/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/24/2003 | | 6/25/2003 | | FAIL |
|
|
|
Faxed and mailed requirements to Wes Steele on 6/25/03, Routed plans to the fire department on the same day.
|
Routing - FIRE | 6/25/2003 | | 6/25/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 6/24/2003 | | 6/24/2003 | | PASS |
|
|
|
Approve per CUP01-00001 and DRH00-00105.
|
Routing - PUBLIC WORKS | 6/23/2003 | | 6/24/2003 | | PASS |
|
|
|
|
Application received | | | 6/23/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/23/2003 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/23/2003 | | DONE |
|
|
|
PARTIAL PERMIT issued this date at the request of R.S. Hosac.
|
Fee Review-notes | 8/20/2003 | 8/20/2003 | | | |
|
|
|
Waiting on final certs.
|
Fee Review-notes | 6/23/2003 | 6/23/2003 | | | |
|
|
|
|