First Notice | | 4/8/2004 | 4/8/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/8/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10091 issued 4-8-04 to Highlands Elementary School portable classroom bldg.
|
Permanent Occupancy | | 3/29/2004 | 3/29/2004 | | DONE |
|
|
|
|
BLD-Final | 3/29/2004 | 3/29/2004 | 3/29/2004 | P | DONE |
Tony Young
|
|
|
I have the card, please let me know when you final it. Thanks, Cathy
|
PubWorks Occupancy Approval | 1/21/2004 | 1/21/2004 | 1/21/2004 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 1/21/04. M.Strasser
|
BLD-Final | 1/21/2004 | 1/21/2004 | 1/21/2004 | P | PART |
Tony Young
|
|
|
Dale, ###-#### or Doug, ###-#### - call 1st so they can meet you there. I have the occ. card, so please call me & let me know if you approved it - plmbg. is still outstanding. Thanks, Tony!
temp. occ ok 1/21/2004 2:51:37 PM
|
Temporary occupancy | | | 1/21/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5069 issued 1-21-04 to Highlands Elementary School for a portable classroom bldg.
|
FIRE-Final Inspection | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/17/2003 at 10:24:54 AM. Contact: ###-####. double entry; passed earlier this afternoon 12/17/2003 2:51:38 PM
|
FIRE-Final Inspection | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PASS |
Rick Jackson
|
|
|
1:00
|
FIRE-Final Inspection | 12/10/2003 | 12/10/2003 | 12/10/2003 | P | FAIL |
Rick Jackson
|
|
|
need to repair exit and emergency lights 12/10/2003 4:21:23 PM
|
BLD-Foundation | 9/11/2003 | 9/12/2003 | 9/12/2003 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/11/2003 at 3:15:20 PM. Contact: ###-####.
|
Routing - FIRE | 8/26/2003 | | 8/26/2003 | | PASS |
|
|
|
Resubmitted water info received 8/25/03 and revised plans acceptable.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/26/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/26/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/26/2003 | | DONE |
|
|
|
|
Telephone call | | | 8/26/2003 | | DONE |
|
|
|
permit ready and fees due
|
Issue PAID IN FULL permit | | | 8/26/2003 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 6/27/2003 | | 8/26/2003 | | PASS |
Mike Otto
|
|
|
8/26/2003 13:55:18 MLO - activity updated through activity BLDA022 from case BLD03-01549.
|
Routing - FIRE | 8/19/2003 | | 8/25/2003 | | FAIL |
|
|
|
Hydrant waterflow not resubmitted; Called architect and left message to send it.
|
Routing - PLAN CHECK | 8/25/2003 | | 8/25/2003 | | NR |
|
|
|
|
Routing - Erosion and Sediment | 8/15/2003 | | 8/19/2003 | | PASS |
|
|
|
ESC waiver approved with conditons attached to plans.
|
Routing - PLANNING | 8/13/2003 | | 8/15/2003 | | PASS |
|
|
|
Pending approval by public works and fire. Approved per CUP03-00057
|
Routing - PUBLIC WORKS | 8/7/2003 | | 8/13/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/4/2003 | | 8/7/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/4/2003 | | DONE |
|
|
|
Transmittal sheet from HSA, Waiver letter for Erosion, four sets of A0,DP1,A1,A2,A3,A4,E1,M1, with three extra sheets of A1 and taken to Mike O.
|
Routing - PUBLIC WORKS | 7/14/2003 | | 7/18/2003 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/18/2003 | | 7/18/2003 | | NH |
|
|
|
|
Routing - FIRE | 7/8/2003 | | 7/11/2003 | | FAIL |
|
|
|
Indequate FD accessibility & lack of hydrant flow information. Comments faxed to architect.
|
Routing - PLAN CHECK | 7/2/2003 | | 7/7/2003 | | FAIL |
|
|
|
correction sent to architect
|
Routing - PLUMBING | 7/2/2003 | | 7/2/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 6/30/2003 | | 7/1/2003 | | FAIL |
|
|
|
NO ESC Waiver letter.
|
Routing - PUBLIC WORKS | 6/27/2003 | | 6/30/2003 | | FAIL |
|
|
|
Failed for drainage per Brian Murphy.
|
Application received | | | 6/26/2003 | | |
|
|
|
|
Fee Review-notes | 6/26/2003 | 6/26/2003 | | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|