Permit Information
Permit NumberBLD03-01552
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMICRON BLDG 24
Customer NumberPCS5657
ePlanReviewNo
Description
Micron Building #24 - FC Buildout & Install an IPA/MSE Dist. System (24-20035657) * To remove an exterior door and infill opening at north exterior wall and to relocate a shower/eyewash from the north side to the south side of Chemical Dispensing Room #103A. This work is at the first floor of Building #24A between grid lines 1&1.5 and F&G. To demo and remodel Water Reactive Bulk Chemical Distribution Room #103C to create a new H-2 Occupancy, IPA Distribution Room. This work includes creating a two-hour fire-resistive occupancy separation and spill control and containment, as well as, other H-2 Occupancy requirements. This work is being done at the first floor of Building #24C at grid line 21 betwenn grid lines B.2&B.4. All construction per the approved plans and attached comment list. #03-370/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  6/28/2004 DONE
Letter of Compliance issued 6-28-04.
BLD-Final6/24/20046/25/20046/25/2004APASS
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
DOC - Permit Finaled6/25/20046/25/20046/25/2004APASS
DetailsJim Storey
Finaled by inspector at 6/25/2004 11:01:24 AM
BLD-Final6/23/20046/24/20046/24/2004PCANC
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
BLD-Final5/13/20045/14/20045/14/2004AFAIL
DetailsJim Storey
need listing for 6 inch rain leader. 5/14/2004 10:52:25 AM
FIRE-Final Inspection5/14/20045/14/20045/14/2004APASS
DetailsRick Jackson
BLD-Final5/12/20045/13/20045/13/2004ACANC
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
BLD-Final5/13/20045/13/20045/13/2004PPASS
DetailsRick Jackson
Fire final okay 5/14/2004 7:37:50 AM
BLD-Aging Inspection3/17/20043/17/20043/17/2004 PASS
DetailsJim Storey
pending fire. 3/17/2004 8:08:20 AM
Inspection Record Card- Bld  1/20/2004 DONE
BLD-Final1/9/20041/15/20041/15/2004ANR
DetailsJim Storey
Jim my man, you can call me on my cell if you need to. ###-####; Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
BLD-Final1/9/20041/13/20041/9/2004ACANC
DetailsJim Storey
Jim buddy, you can call me on my cell if you please, ###-####. Thx. Holmes; Phone #: ###-#### Internet Inspection Request from: Dennis Holmes Inspection cancelled from web by: Dennis Holmes
Issue & PRINT to be Invoiced  1/8/2004 DONE
Plan assigned to (JCM)6/27/2003 1/5/2004 PASS
DetailsJohn Menard
1/5/2004 09:44:08 JCM - activity updated through activity BLDA022 from case BLD03-01552.
Routing - PLAN CHECK12/26/2003 1/5/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/5/2004 PASS
Permit Ready to Issue  1/5/2004 DONE
email to paul and darla permit ready
Inspection Record Card- Bld  1/5/2004 DONE
Routing - FIRE12/22/2003 12/26/2003 PASS
Resubmittal acceptable.
Plan Reviewer's activity  12/22/2003 PASS
Final resubmittals reviewed and approved as submitted. JCM
Routing - PLAN CHECK8/1/2003 12/22/2003  
Plan resubmittals received  12/19/2003 DONE
Received response letter to Micron PCS 5657 and calculations. Routed to John M. kmm
Plan resubmittals received  10/24/2003 DONE
Received two copies of revised sheets M2.1 and A2.1.2 one copy of plan review, one copy of plan review response, one copy of section view detail, one copy of project conditions, one copy of letter to Sam Rogers and one copy of Fier Code Review. Routed to John M. kmm
Routing - FIRE7/21/2003 8/1/2003 FAIL
7/24/03 - Insufficient info to verify compliance with IFC 27 and 34. Called Paul Marcolina to discuss; not avail.; left voice message to call back to discuss. Hold for additional information.
8/1/03 - No additional information received to date. Plan review comments issued on plans as submitted.
Plan resubmittals received  7/30/2003 DONE
Received cover letter and 2 copies of resubmittal sheet A2.1.2 and forwarded to John.
Plan resubmittals requested  7/21/2003  
E-mailed the architect a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK6/30/2003 7/21/2003 FAIL
Plan resubmittals received  7/10/2003 DONE
response letter, letter to Paul, Horizontal membrane details, basic interfaces, two copies of G.0. A2.12, and taken to Paul.



























Plan resubmittals requested  7/3/2003  
E-mailed the architect asking for additional information and detailing. JCM
Routing - PUBLIC WORKS6/27/2003 6/30/2003 PASS
Fee Review-notes6/26/20036/26/2003