Permit Information
Permit NumberBLD03-01605
StatusFinaled
Name BIG D CONSTRUCTION
Site Address 1301 W BANNOCK ST
Project NameMeadow Gold Dairies(Phase 1)
Customer Number 
ePlanReviewNo
Description
Meadow Gold Dairies Milk Receiving Bay Addition * To construct a 2250 square foot, one story structural steel building addition and a 30'x17'x2' reinforced concrete pad for support of two future 40,000 gallon silos on the north side of the existing Meadow Gold Building #C. This addition will be separated from the existing building by a three-hour fire wall. The silos are not approved under this permit. All construction per the approved plans and attached comment list. DRH03-00088/CUP03-00026/PC#384-03/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval1/14/20051/14/20051/14/2005 DONE
Finaled without PW approval, no final inspection, drive-by shows complete. 1/14/05 R.Rokovitz
First Notice 2/25/20042/25/2004 DONE
Permanent occupancy UNPAID FEE  2/25/2004 DONE
Perm. Occ. Cert. # 10004 issued 2-23-04 to Meadow Gold Dairies (Phase 1).
Permanent Occupancy 2/18/20042/18/2004 DONE
Details
BLD-Final2/9/20042/9/20042/9/2004PPASS
DetailsDave Hannah
dan ; Phone #: ###-#### Internet Inspection Request from: Annette Moore ok for prem occ 2/9/2004 1:29:59 PM
Temporary occupancy  12/18/2003 DONE
Temp. Occ. cert. #5043 issued 12-18-03 to Meadow Gold Dairies.
FIRE-Final Inspection12/9/200312/9/200312/9/2003PPASS
DetailsRick Jackson
dan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Final12/9/200312/9/200312/9/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/9/2003 at 11:19:01 AM. Contact: ###-####. ok for temp occ ok for perm occ after other trades go perm 12/9/2003 2:42:53 PM
FIRE-Final Inspection12/1/200312/1/200312/1/2003PFAIL
DetailsRick Jackson
dan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie installed emergency lights per plans and needs one fire extinguisher 12/1/2003 1:32:44 PM
BLD-Framing/Rough-in11/12/200311/12/200311/12/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/12/2003 at 11:20:40 AM. Contact: ###-####. roof joist cliping to cmu wall ok to cover 11/12/2003 4:56:48 PM
BLD-Other11/5/200311/6/200311/6/2003PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/5/2003 at 1:26:30 PM. Contact: ###-####. will have mti inspect cmu 11/7/2003 7:51:18 AM
BLD-Other11/4/200311/5/200311/5/2003PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/4/2003 at 1:43:52 PM. Contact: ###-####.
BLD-Other11/4/200311/4/200311/4/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/4/2003 at 7:42:06 AM. Contact: ###-####.ok to cover roof 11/4/2003 3:30:26 PM
BLD-Other9/29/20039/30/20039/30/2003PCANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/29/2003 at 3:39:41 PM.
BLD-Foundation9/23/20039/25/20039/25/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/23/2003 at 11:34:47 AM. done under specal inspection 9/25/2003 1:39:56 PM
BLD-Foundation9/19/20039/22/20039/22/2003PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/19/2003 at 10:37:52 AM. mti will also inspect and test concrete 9/22/2003 1:06:48 PM
BLD-Foundation9/12/20039/15/20039/15/2003ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/12/2003 at 8:51:06 AM.
BLD-Footing9/15/20039/15/20039/15/2003PPASS
DetailsDave Hannah
mti on site to inspect and test
Issue PAID IN FULL permit  9/10/2003 DONE
Routing - PLAN CHECK8/28/2003 9/3/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/3/2003 PASS
Inspection Record Card- Bld  9/3/2003 DONE
Print Occupancy Form  9/3/2003 DONE
Telephone call  9/3/2003 DONE
PERMIT READY AND FEES DUE
Permit Ready to Issue  9/3/2003 DONE
Plan assigned to (JCM)7/8/2003 9/3/2003 PASS
DetailsJohn Menard
9/3/2003 09:40:21 JCM - activity updated through activity BLDA022 from case BLD03-01605.
Routing - FIRE8/20/2003 8/28/2003 PASS
Plan resubmittals received  8/28/2003 DONE
Received United Water information
Routing - PUBLIC WORKS8/20/2003 8/20/2003 PASS
Plan resubmittals received  8/20/2003 DONE
Received two copies of revised sheet A-1.1 Put with plans. kmm
Routing - PLANNING8/7/2003 8/20/2003 PASS
Routing - PLANNING7/11/2003 8/20/2003 PASS
Passed by Sev Jones per CU conditions. Approved by Tempra Wilson for Design Review sign-off per DRH03-88.
Routing Off Site - STRUCTURAL8/13/2003 8/14/2003 PASS
contacted PDQ to take resubmitted plans of 7-8-03 to outside engineering. Received letter e-mailed from consulting structural engineer approving the resubmitted items. JCM
Plan resubmittals received  8/12/2003 DONE
received two copies of a response letter with general comments, letter of transmittal, three copies of calculations from Power Engineers, three sets of SO-1, S1.1, S2-1, S2-2 Taken to John M
Routing - PLAN CHECK7/24/2003 8/7/2003  
Routing - PUBLIC WORKS7/18/2003 7/18/2003 FAIL
Plan resubmittals requested  7/18/2003  
Faxed the applicant a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL7/8/2003 7/18/2003 FAIL
Contacted PDQ to take to outside engineering. kmm Received an e-mailed comment list from the consulting structural engineer requesting revisions, JCM
Routing - PLAN CHECK7/16/2003 7/17/2003 FAIL
Plan resubmittals requested  7/17/2003  
Mailed the applicant a copy of the plan review comment list requesting revisions. JCM
Routing - PLUMBING7/16/2003 7/16/2003 PASS
1. hot water hose bibbs must have backflow protection 2. have engineer specify type of floor drains in receiving bay 3. sand trap needs a vent and a cleanout on the outlet side.
Routing - Erosion and Sediment7/10/2003 7/10/2003 PASS
ESC approved with conditions attached to plans.
Routing - PUBLIC WORKS7/8/2003 7/9/2003 FAIL
Requires drainage plan revisions per Brian M. kmm
Routing - PLANNING Land Div7/8/2003 7/8/2003 PASS
Approved by ROS 3571.
Plans ACCEPTED BY PLAN TECH  7/8/2003 DONE
Site plan needs to be signed. Faxed involved parties sheet to Bruce Cunnington to sign. kmm
Plan routing begun/NEW & ADDTN  7/8/2003 DONE
Routing Off Site -Energy7/8/2003 7/8/2003  
John will do energy review
Application received  7/2/2003