DOC - Permit Finaled | 8/9/2004 | 8/9/2004 | 8/9/2004 | A | PASS |
Jim Sly
|
|
|
Finaled by inspector at 8/9/2004 9:13:26 AM
|
DOC - Permit Finaled | 8/9/2004 | 8/9/2004 | 8/9/2004 | A | PASS |
Jim Sly
|
|
|
Finaled by inspector at 8/9/2004 9:13:19 AM
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Jim Sly
|
|
|
|
Case Summary (BLD) | | | 9/9/2003 | | |
|
|
|
|
BLD-Final | 9/5/2003 | 9/8/2003 | 9/8/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/5/2003 at 11:54:16 AM. Contact: ###-####. OK for Perm Occ. :) 9/8/2003 12:29:43 PM
|
FIRE-Final Inspection | 9/5/2003 | 9/8/2003 | 9/8/2003 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/5/2003 at 1:47:56 PM. Contact: ###-####.
|
Letter of compliance | | | 9/8/2003 | | DONE |
|
|
|
Letter of Compliance #24111 issued 9-7-03.
|
FIRE-Final Inspection | 9/4/2003 | 9/5/2003 | 9/5/2003 | A | FAIL |
Troy Cobbley
|
|
|
test duct smoke detectors 9/5/2003 1:44:42 PM
|
BLD-Final | 9/4/2003 | 9/5/2003 | 9/5/2003 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/4/2003 at 2:52:17 PM. Contact: ###-####. Need all req signatures. 9/5/2003 12:05:03 PM
|
FIRE-Final Inspection | 8/26/2003 | 8/27/2003 | 8/27/2003 | A | FAIL |
Troy Cobbley
|
|
|
Sprinkler pendant is overspaced near east exit, repair exit light out side the exit in egress corridor, test duct smoke detectors, remover thumb turn on west doors 8/27/2003 12:50:53 PM
|
BLD-Final | 8/26/2003 | 8/27/2003 | 8/27/2003 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/26/2003 at 1:01:13 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/8/2003 | 8/11/2003 | 8/11/2003 | A | PASS |
Jim Sly
|
|
|
###-####
|
Issue & PRINT permit | | | 8/8/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/8/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/7/2003 | | DONE |
|
|
|
|
Telephone call | | | 8/7/2003 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2003 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 7/11/2003 | | 8/6/2003 | | PASS |
|
|
|
8/6/2003 10:05:44 RMH - activity updated through activity BLDA022 from case BLD03-01634.
|
Routing - PLAN CHECK | 7/28/2003 | | 8/6/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/5/2003 | | DONE |
|
|
|
3 copies of Sheet EN1 received and fowarded to Ron Hill.
|
Plan resubmittals received | | | 8/4/2003 | | DONE |
|
|
|
one transmittal, one copy of Mechanical compliance certificate taken to Ron H.
|
Routing - FIRE | 7/24/2003 | | 7/28/2003 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 7/24/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 7/11/2003 | | 7/24/2003 | | FAIL |
|
|
|
Emailed and mailed requirements to Wes Steele on 7-24-03, Routed plans to fire for review same day.
|
Plans ACCEPTED BY PLAN TECH | | | 7/9/2003 | | DONE |
|
|
|
|
Application received | | | 7/8/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/8/2003 | | PEND |
|
|
|
No compcheck submitted. I contacted Wes Steele with a message that plan reviewer may be in touch with him; however, if not adding new lights and switches are called out plans may be ok as is. kmm
|
Fee Review-notes | 7/8/2003 | 7/8/2003 | | | |
|
|
|
|