BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 8/2/2004 | 8/2/2004 | 8/2/2004 | P | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 8/2/2004 11:34:47 AM
|
PubWorks Occupancy Approval | 3/19/2004 | 3/19/2004 | 3/19/2004 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 3/19/04. D.Erskine
|
BLD-Aging Inspection | 1/15/2004 | 1/15/2004 | 1/15/2004 | | DONE |
Dave Hannah
|
|
|
wip 1/15/2004 8:32:13 AM
|
Issue PAID IN FULL permit | | | 10/16/2003 | | |
|
|
|
|
(F) Reprint permit | | | 10/16/2003 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/14/2003 | | 10/15/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/15/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2003 | | |
|
|
|
|
Permit Ready to Issue | | | 10/15/2003 | | |
|
|
|
|
Telephone call | | | 10/15/2003 | | DONE |
|
|
|
left mess that permit is ready--
|
Routing - PLAN CHECK | 10/7/2003 | | 10/14/2003 | | PEND |
|
|
|
Plans in hold box waiting for PW to approve plans. kmm\\pw requested plans back.rad
|
Routing - PUBLIC WORKS | 10/3/2003 | | 10/7/2003 | | FAIL |
|
|
|
Requires three copies of street lighting plan. Per Bill Colson. kmm
|
Plan assigned to (KMM) | 7/15/2003 | | 10/7/2003 | | PASS |
Kathy Miller
|
|
|
10/7/2003 10:48:20 CJW - activity updated through activity BLDA022 from case BLD03-01696.
|
Routing - PLAN CHECK | 9/30/2003 | | 10/3/2003 | | |
|
|
|
Waiting PW approval. Plans in hold box. kmm \\plans routed to PW
|
Routing - Erosion and Sediment | 9/26/2003 | | 9/29/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/26/2003 | | DONE |
|
|
|
Received two copies of revised ESC1 sheet, letter and two copies of plan narrative. Put with plans. kmm
|
Routing - PLAN CHECK | 9/22/2003 | | 9/26/2003 | | |
|
|
|
Plans in hold box. kmm
|
Plan resubmittals received | | | 9/23/2003 | | DONE |
|
|
|
Recieved two copies of revised ESC application and Storm Water Pollution Prevention Plan. Put with plans. kmm
|
Routing - PLAN CHECK | 8/15/2003 | | 9/22/2003 | | |
|
|
|
Plans in hold box pending further documentation required for public works.
|
Routing - PUBLIC WORKS | 9/22/2003 | | 9/22/2003 | | FAIL |
|
|
|
Requires drainage plan revision. per Brian M. kmm
|
Routing - Erosion and Sediment | 8/14/2003 | | 8/14/2003 | | FAIL |
|
|
|
No ESC narrative included with plans which meet standards of BCC8-17 or appendix A&C of plan designer manual. Individual listed as RP is not certified by Boise City. Contacted Plan Designer.
|
Routing - PUBLIC WORKS | 8/12/2003 | | 8/14/2003 | | FAIL |
|
|
|
Requires drainage plan revision per Brian M. kmm
|
Routing - PLAN CHECK | 7/25/2003 | | 8/12/2003 | | |
|
|
|
Plans in hold box. kmm
|
Routing - FIRE | 7/22/2003 | | 7/25/2003 | | PASS |
|
|
|
Approved with no written comments required.
|
Routing - PLANNING | 7/18/2003 | | 7/22/2003 | | PASS |
|
|
|
Approved per DRH03-91.
|
Routing - PUBLIC WORKS | 7/16/2003 | | 7/18/2003 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian M. kmm
|
Routing - Erosion and Sediment | 7/18/2003 | | 7/18/2003 | | FAIL |
|
|
|
ESC does not meet requirements of BCC 8-17 and Appendix C of plan designer manual. No written narrative provided. Contacted Plan Designer on 7/18/03.
Individual listed as RP is not certified by Boise City.
|
Plans ACCEPTED BY PLAN TECH | | | 7/16/2003 | | DONE |
|
|
|
Received 2 copies of civil and ESC app. kmm
|
Routing - PLANNING Land Div | 7/15/2003 | | 7/15/2003 | | PASS |
|
|
|
Approved. Lot 1-3 of Block of Central Subdivision.
|
Plan routing begun/TENANTS | | | 7/15/2003 | | DONE |
|
|
|
|
Application received | | | 7/15/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/15/2003 | | PEND |
|
|
|
Requires two additional copies of civil drawings and completed ESC application. Contacted Larry Knopp of this need. kmm
|