Micron Building 36-Relocate Netcom and Flash Lab Areas (PCS #36-20035846) * To demo and remodel an approximate 1900 square foot area of the existing IS Machine Room 110B to create a new Netcom and Flash Lab/Office. This will include new interior partions, doors, electrical lighting and mechanical equipment. This work is being done on the first floor of Building #36 between grid lines 9&11 and C&D. All work per approved plans as drawn with redlined notes. PC#409-03/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/30/20042/2/20042/2/2004APASS
DetailsJim Storey
john; Phone #: ###-#### Internet Inspection Request from: Annette Moore
DOC - Permit Finaled2/2/20042/2/20042/2/2004APASS
DetailsJim Storey
Finaled by inspector at 2/2/2004 8:44:49 AM
FIRE-Final Inspection1/29/20041/29/20041/29/2004APASS
DetailsRick Jackson
no occupancy card to sign; fire/life safety okay 1/29/2004 8:34:56 AM
BLD-Aging Inspection1/27/20041/27/20041/27/2004 NR
DetailsJim Storey
wip phase c changes in progess. 1/27/2004 10:02:09 AM
BLD-Aging Inspection11/25/200311/25/200311/25/2003 PART
DetailsJim Storey
BLD-Conference9/23/20039/24/20039/24/2003PPASS
DetailsJim Storey
ermie; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Plan resubmittals received  8/7/2003 DONE
Energy sheet EN01 and EN02 received and forwarded to John Menard.
Inspection Record Card- Bld  8/6/2003 DONE
Issue & PRINT to be Invoiced  8/6/2003 DONE
Plan assigned to (JCM)7/16/20037/16/20038/4/2003 PASS
DetailsJohn Menard
8/4/2003 09:41:31 JCM - activity updated through activity BLDA022 from case BLD03-01707.
Routing - PLAN CHECK8/4/2003 8/4/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/4/2003 PASS
Routing - FIRE7/28/2003 8/1/2003 PASS
Routing - PLAN CHECK7/21/2003 7/28/2003 PASS
Plan Reviewer's activity  7/28/2003 PASS
Plans approved as submitted with plan review redlined notes on plans. JCM
Routing - PLUMBING7/18/2003 7/21/2003 PASS
no plumbing on these plans, if plumbing is added, resubmittals will be required.
Plan resubmittals received  7/18/2003 DONE
Received three copies of revised sheet M2.3.1 Routed to John M. kmm
Plans ACCEPTED BY PLAN TECH  7/16/2003 DONE
1. No applicant's signature on Involved Parties and Certificate of Value sheet. Owner's signature required on Registered Design Professional sheet. Faxed all three sheets to Paul Marcolina and requested that he fax back signed forms.
2. No energy compliance plans or documents. Left message for Paul Marcolina that energy compliance is required.
Application received  7/15/2003  
Fee Review-notes7/15/20037/15/2003   
Routing - PUBLIC WORKS7/18/2003   PASS