First Notice | | 11/24/2003 | 11/24/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/24/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9882 issued 11-24-03 to Snake River Pool & Spa.
|
Permanent Occupancy | | 11/18/2003 | 11/18/2003 | | DONE |
|
|
|
|
BLD-Final | 11/17/2003 | 11/18/2003 | 11/18/2003 | P | PASS |
Tom Arcoraci
|
|
|
Mark --- later afternoon please. thanks.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok for perm 11/18/2003 2:09:54 PM
|
FIRE-Final Inspection | 11/17/2003 | 11/17/2003 | 11/17/2003 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
FIRE-Final Inspection | 11/13/2003 | 11/14/2003 | 11/14/2003 | P | FAIL |
Troy Cobbley
|
|
|
Mark; Phone #: ###-#### Fire alarm failed. Fire life safety will be ok to sign off when fire alarm is complete 11/14/2003 3:41:36 PM
|
BLD-Final | 11/13/2003 | 11/14/2003 | 11/14/2003 | P | FAIL |
Russ Owen
|
|
|
Mark; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Went to job 2 times once at 11:00 and as requested 3:00 still needs fire life safety. 11/13/2003 11:46:40 PM
|
Code Occupancy Approval | 11/6/2003 | 11/6/2003 | 11/6/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 11/6/2003 2:44:14 PM
|
BLD-Wall cover | 11/4/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/4/2003 at 2:46:40 PM. Contact: ###-####.
|
Inspection Record Card- Bld | | | 10/31/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/31/2003 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 7/22/2003 | 7/22/2003 | 10/13/2003 | | PASS |
Dan Stuart
|
|
|
10/13/2003 10:28:40 DRS - activity updated through activity BLDA022 from case BLD03-01739.
|
Routing - FIRE | 10/8/2003 | | 10/13/2003 | | PASS |
|
|
|
Approved per resubmitted Haz Mat report.
|
Routing - PLAN CHECK | 10/13/2003 | | 10/13/2003 | | PASS |
|
|
|
Plans approved based on notes on plans and the attached plan review conditions & comments of all reviewing agencies.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2003 | | PASS |
|
|
|
To permit desk to issue.
|
Print Occupancy Form | | | 10/13/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/13/2003 | | DONE |
|
|
|
permit ready and fee due
|
Plan resubmittals received | | | 10/7/2003 | | DONE |
|
|
|
Received transmittal sheet with two sets of A1.0,A1.1, A1.2, A1.3,A1.4,A2.1, A3.1,A3.2, M-1, E1.1, M0.0, M1.0,M2.0,E1.2,EN1.2, two hazardous material books. Letter addressing exit hardware, Orchard Cernter mall ,Auto showroom door sheet, Civil and Structural Engineering, Facsimile transmittal form regarding Orchard Center Mall, information regarding the DRH 03-00119 all taken to Dan S.
|
Routing - PLAN CHECK | 9/19/2003 | | 9/25/2003 | | FAIL |
|
|
|
LETTER FROM OWNER JIM PAXTON REQUESTING THAT I SEPARATE THIS PERMIT BLD03-01739 (1340 ORCHARD)FROM PERMITS BLD03-01554 (1346 OCHARD), BLD03-01738 (1342 ORCHARD) & BLD03-01880 (1338 ORCHARD), SO THE OTHER PERMITS CAN BE ISSUED WHILE WAITING FOR THE HAZARDOUS MATERIALS REPORT FOR SNAKE RIVER POOL AND SPA. A SEPARATE PLAN SUBMITTAL WILL BE MADE FOR THIS TENANT SPACE ONCE THE HAZ MAT REPORT IS RECEIVED BY ARCHITECT. THIS WAS DONE AND THE OTHER PERMITS ISSUED.
|
Telephone call | | | 9/24/2003 | | DONE |
|
|
|
Received telcon from Mark Bolland who requested that we approve the three vanilla finish tenant spaces on a promise that they will comply with the haz mat issues in Snake River tenant space. Told him I can't approve it on that basis, as the occupancy determined for Snake River will affect the tenants as this is an unseparated building. I agreed to talk to Dan Stuart about splitting this into separate permits. However, I also pointed out that the sprinkler system failed its inspection and plans for the sprinkler monitoring alarm system were just submitted and won't be reviewed until next week. The FI, Troy Cobbley indicates they were looking to occupy by this weekend. I told Mark of these concerns and indicated even if separate permits were issued to the separate tenants, they will not be allowed to occupy without the sprinkler system and alarm system being approved.
|
Plan resubmittals received | | | 9/24/2003 | | DONE |
|
|
|
Received two copies of revised sheets E1.1 and EN1.2 and envelope compliance certificate. Routed to Dan S. kmm
|
BLD - Request for Extension | 9/17/2003 | 9/18/2003 | 9/18/2003 | A | PASS |
Tom Arcoraci
|
|
|
ok to extend 9/18/2003 8:44:32 AM
|
Routing - FIRE | 9/16/2003 | | 9/18/2003 | | FAIL |
|
|
|
Haz Mat info not acceptable for Snake River Pool. Since four permits are on one set of plans, plans for the other approved permits cannot be issued until the Snake River Pool issues are resolved. Faxed revised review to archtect.
|
Plans ACCEPTED BY PLAN TECH | | | 9/17/2003 | | |
Dave Hannah
|
|
|
467-137
|
Plan resubmittals received | | | 9/9/2003 | | DONE |
|
|
|
Received two copies of revised sheets, A1.0, A1.1, A1.2, A1.3, A1.4, A2.1, A3.1, A3.2, E1.1, M0.0, M1.0, M2.0, one copy of response letter, four copies of envelope compliance cert., two copies of struct. claculations for orcard center mall openings, four copies of United Water letter, one copy of chemicals for pools and spa and response letter regarding the external storage area. Routed to Dan S. kmm
|
Plan resubmittals requested | | | 8/5/2003 | | FAIL |
|
|
|
Plan re-submittals of 7/31/03 are incomplete. 4th tenant space created in resubmittals and items were only partially addressed or not addressed at all. Copy of plan review #2 faxed, e-mailed and mailed to architect.
|
Telephone call | | | 8/5/2003 | | DONE |
|
|
|
Talked with architec to let him know the plans submitted were incomplete and that I was sending him copy of plan review comments and items needing to be addressed.
|
Routing - PLAN CHECK | 7/28/2003 | | 8/5/2003 | | FAIL |
|
|
|
Plan resubmittals inserted into plans. Re-submittals are incomplete or do not addres some items of plan review at all. Copy of 2nd review comments faxed e-mailed and mailed to architect.
|
Telephone call | | | 8/5/2003 | | DONE |
|
|
|
Phone call from Mark Bowen contractor and Pat Dalgleish architect stating they had the hazardous materials list of item to be store & sold on site by this tenant space. I tld them to submitt the list with the resubmittals that are required by the second plan review comments I will fax to them. Plans submitted were incomplete; did not address some items of the 1st review at all and new fourth space created in resubmittals added additional items needing clarified.
|
Plan resubmittals received | | | 7/31/2003 | | DONE |
|
|
|
Received new plan sheets 'A2.1' & 'A3.2".
|
Routing - FIRE | 7/22/2003 | | 7/28/2003 | | FAIL |
|
|
|
Comments faxed to architect. FD access, water suppy and Haz Mat issues.
|
Application received | | | 7/25/2003 | | DONE |
|
|
|
New application recieved for this tenant space.
|
Received Certificate of Value | | | 7/25/2003 | | DONE |
|
|
|
Received new C.V. for this tenant space T.I.
|
Plan resubmittals requested | | | 7/22/2003 | | FAIL |
|
|
|
Copy of plan review comments needing a response were faxed and mailed to architect of record.
|
Routing - PLAN CHECK | 7/9/2003 | | 7/22/2003 | | FAIL |
|
|
|
Plans incomplete and incorrect for code compliance. Notified architect by faxing copy of review & mailing copy.Routing to fire code analyst for his review.
|
Application received | | | 7/18/2003 | | |
|
|
|
ONE VALUE WAS TURNED IN ON THIS PERMIT, PERMITS WERE SPLIT INTO A TOTAL OF 4 PERMITS. I TRASFERED THE FEES TO OTHER PERMIT.BLD03-01554 AND BLD03-01739..LH
|
Telephone call | | | 7/18/2003 | | DONE |
|
|
|
Phone call to Mark Bowen concerning submitted plans. Plans indicate the three tenant spaces but application is for one permit and one address. The addressing division have assigned thre address's, one for each space. Three application will be need for this project. One will be for snake river pool and spac to finihs out the space and obtain a certificate of occupancy; the other two spaces will recieve letter of compliance for the scope of work covered under thier permit but no certificate of occupancy. These two tenant will be required to provide their own applications & plans for finishing out thier propose space for code compliance and to obtain their own individual certificate of occupancies. Mark will follow up with additional applications.
|
Routing - PLANNING | 7/2/2003 | | 7/9/2003 | | PASS |
|
|
|
Approved as part of BLD03-01554 and as noted in DRH03-00119.
|
Routing - PLANNING Land Div | 7/1/2003 | | 7/1/2003 | | PASS |
|
|
|
Approved as part of BLD03-01554.
|
Routing - PUBLIC WORKS | 6/27/2003 | | 7/1/2003 | | PASS |
|
|
|
Approved as part of BLD03-01554. This space is one of three being created for new tenant spaces, each requiring a permit.
|