First Notice | | 1/22/2004 | 1/22/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/22/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 9943 issued 1-22-04 to Dr. Mike Davis.
|
Permanent Occupancy | | 1/14/2004 | 1/14/2004 | | DONE |
|
|
|
|
BLD-Final | 1/14/2004 | 1/14/2004 | 1/14/2004 | P | PASS |
Jim Sly
|
|
|
for perm occ- jim ###-#### OK for Perm Occ. :) 1/14/2004 2:02:36 PM
|
BLD-Energy code compliance | 12/3/2003 | 12/4/2003 | 12/4/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/3/2003 at 6:57:35 PM. Contact: ###-####.
|
BLD-Final | 12/3/2003 | 12/4/2003 | 12/4/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/3/2003 at 6:58:16 PM. Contact: ###-####. C/N Need Electr sign off for Perm Occ... Once verified.........OK to final structural for Perm Occ. :) 12/4/2003 9:10:47 AM 12/4/2003 9:11:43 AM
|
Temporary occupancy | | | 12/4/2003 | | DONE |
|
|
|
Temp. Occ. Cert. # 5034 issued 12-4-03 to Dr. Mike Davis.
|
FIRE-Final Inspection | 12/2/2003 | 12/3/2003 | 12/3/2003 | A | PASS |
Rick Jackson
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Final | 12/2/2003 | 12/3/2003 | 12/3/2003 | P | NR |
Jim Sly
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Need plumb final 12/3/2003 4:28:38 PM
|
FIRE-Supply Line Cover | 12/1/2003 | 12/2/2003 | 12/2/2003 | A | FAIL |
Rick Jackson
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes needs extinguisher hung 12/2/2003 10:40:39 AM
|
BLD-Energy code compliance | 11/14/2003 | 11/17/2003 | 11/17/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 5:37:05 PM. Contact: ###-####.
|
BLD-Other | 11/14/2003 | 11/17/2003 | 11/17/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 5:39:02 PM. Contact: ###-####. Ceiling grid and removal of kraft facing from insul....OK. 11/17/2003 11:37:51 AM
|
BLD-Framing/Rough-in | 11/13/2003 | 11/14/2003 | 11/14/2003 | P | PART |
Jim Sly
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Ceiling appears OK....Need to remove exposed kraft paper from ceiling insulation. 11/14/2003 11:34:56 AM
|
BLD-Framing/Rough-in | 10/22/2003 | 10/23/2003 | 10/23/2003 | A | PASS |
Jim Sly
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Framing/Rough-in | 10/21/2003 | 10/22/2003 | 10/22/2003 | A | PASS |
Jim Sly
|
|
|
JIM; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
Issue PAID IN FULL permit | | | 10/9/2003 | | |
|
|
|
|
Plan assigned to (JCB) | 7/24/2003 | | 9/30/2003 | | PASS |
Jason Blais
|
|
|
9/30/2003 13:28:44 JCB - activity updated through activity BLDA022 from case BLD03-01742.
|
Routing - PLAN CHECK | 9/30/2003 | | 9/30/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2003 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/30/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/30/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/30/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - FIRE | 9/23/2003 | | 9/29/2003 | | PASS |
|
|
|
resubmittal approved subject to field verification of quantities of oxidizing gases. Review faxed to architect.
|
Routing - PLUMBING | 9/18/2003 | | 9/23/2003 | | PASS |
|
|
|
provide a valve to control all outlets in this space, n2o and o2 systems have been deleted from this project.
|
Routing - PLAN CHECK | 8/19/2003 | | 9/18/2003 | | PEND |
|
|
|
Permit can be issued when there is approval by Public Works, Plumbing, and the Fire Department. Plans to route to these divisions.
|
Routing - PUBLIC WORKS | 9/18/2003 | | 9/18/2003 | | PASS |
|
|
|
Additional restroom and service sink added.
|
Plan resubmittals received | | | 9/15/2003 | | DONE |
|
|
|
Response letter to Jason with two sets of A2.1, A7.1,EN-1, M.1, M.2 taken to Jason.
|
Routing - FIRE | 8/13/2003 | | 8/19/2003 | | FAIL |
|
|
|
Inadequate Med gas information on plans. Review faxed to architect.
|
Plan resubmittals requested | | | 8/13/2003 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 8/6/2003 | | 8/13/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans routed to Fire Dept.
|
Routing - PLUMBING | 7/25/2003 | | 8/6/2003 | | FAIL |
|
|
|
provide a floor sink at vacuum pump, show intake and exhaust for equipment, water lines to equipment under cabinets will need r.p.s, provide an alarm system for compressed medical gas system, service piping to each tenant shall be separate, a mop sink will be required, show piping.
|
Routing - PUBLIC WORKS | 7/24/2003 | | 7/25/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/23/2003 | | DONE |
|
|
|
Received three copies of EN-1 sheets for Com-Check, put with plans
|
Plans ACCEPTED BY PLAN TECH | | | 7/22/2003 | | PEND |
|
|
|
Waiting for mechanical com check.
|
Application received | | | 7/18/2003 | | |
|
|
|
|