FIRE-Final Inspection | 3/15/2004 | 3/15/2004 | 3/15/2004 | P | CANC |
Troy Cobbley
|
|
|
fire life safety final already given 3/15/2004 2:49:57 PM
|
BLD-Final | 3/15/2004 | 3/15/2004 | 3/15/2004 | P | PASS |
Jim Sly
|
|
|
karl evans; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 3/15/2004 2:07:15 PM OK for Perm Occ. :) 3/15/2004 2:07:41 PM
|
Letter of compliance | | | 3/15/2004 | | DONE |
|
|
|
lETTER OF cOMPLIANCE ISSUED 3-15-04.
|
FIRE-Final Inspection | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 2/25/2004 9:10:02 AM
|
BLD-Final | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | FAIL |
Jim Sly
|
|
|
carl; Phone #: ###-#### Internet Inspection Request from: Annette Moore Need Temp glass at window by ADA shower....Per Bob A. 2/25/2004 8:51:01 AM
|
FIRE-Final Inspection | 2/18/2004 | 2/19/2004 | 2/19/2004 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the the southeast exit door gets approved door hardware installed 2/19/2004 11:20:26 AM
|
BLD-Final | 2/18/2004 | 2/19/2004 | 2/19/2004 | A | PART |
Jim Sly
|
|
|
Karl --- FIR final is in the a.m. as well.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes \ OK for Temp. C/N (3) rated doors need smoke seals and rating tags cleaned. Waiting for interpretation for glazing at ADA shower. Remove key lock at S. E. door and install panic. Obtain Perm Occ status within 90 days of this notice. 2/19/2004 12:21:10 PM
|
FIRE-Final Inspection | 2/17/2004 | 2/18/2004 | 2/18/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide approved door hardware on the southeast exterior door. Final fire alarm system 2/18/2004 4:00:49 PM
|
BLD-Final | 2/17/2004 | 2/18/2004 | 2/18/2004 | P | CANC |
Jim Sly
|
|
|
###-#### Karl
|
BLD-Final | 2/4/2004 | 2/5/2004 | 2/5/2004 | A | PART |
Jim Sly
|
|
|
Carl; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Grid OK. 2/5/2004 9:35:47 AM
|
BLD-Framing/Rough-in | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PASS |
Jim Sly
|
|
|
CARL ( FIRE WALL ); Phone #: ###-#### Internet Inspection Request from: Darla Downs Framing OK. Contractor to call me to talk about Energy code Req.
12/17/2003 4:01:43 PM 12/17/2003 4:02:41 PM
|
BLD-Framing/Rough-in | 12/8/2003 | 12/9/2003 | 12/9/2003 | A | PART |
Jim Sly
|
|
|
carl; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OKd to 1 side.......Need to complete gyp membrane around electrical panels at 1hr walls (storage) and brace X ray machine tracks. 12/9/2003 10:24:26 AM
|
Issue PAID IN FULL permit | | | 10/28/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/21/2003 | | DONE |
|
|
|
Left message for Dave to remind that permit is ready & fees
|
Telephone call | | | 9/24/2003 | | DONE |
|
|
|
Left message for Steve Trout that permit is ready & fees
|
Inspection Record Card- Bld | | | 9/9/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/9/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/9/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/9/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plan assigned to (R_H) | 7/29/2003 | | 9/8/2003 | | PASS |
|
|
|
9/8/2003 10:25:32 RMH - activity updated through activity BLDA022 from case BLD03-01798.
|
Routing - PLAN CHECK | 9/5/2003 | | 9/8/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2003 | | DONE |
|
|
|
|
Routing - FIRE | 8/28/2003 | | 9/5/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/3/2003 | | DONE |
|
|
|
Resubmittal Sheets A2.1, A5.2, A5.3 (3 copies) and cover letter received and forwarded to Ron.
|
Routing - PLAN CHECK | 8/8/2003 | | 8/28/2003 | | FAIL |
|
|
|
Faxed requirements to the architect on 8/28/03, Routed plans to the fire department same day.
|
Plan resubmittals received | | | 8/18/2003 | | DONE |
|
|
|
Received two copies of calculations for Primary Health. Routed to Ron Hill. kmm
|
Routing - PLANNING | 8/5/2003 | | 8/8/2003 | | PASS |
|
|
|
Approved per CZC03-109.
|
Routing - PLUMBING | 7/31/2003 | | 8/5/2003 | | PASS |
|
|
|
1. water heater needs pan with a drain to an approved location 2. thermal expansion protection will be required
|
Routing - PUBLIC WORKS | 7/29/2003 | | 7/31/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/30/2003 | | DONE |
|
|
|
Received one copy of letter from Dave Bliss. Routed to Ron H. kmm
|
Received Certificate of Value | | | 7/29/2003 | | DONE |
|
|
|
Received cert. of value for demo and revised cert for project minus demo. Put with file and routed copy to Ron H. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 7/25/2003 | | DONE |
|
|
|
1. No building code data.
2. Certificate of Value not signed by applicant. Faxed to Steve Trout for signature.
|
Application received | | | 7/24/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/24/2003 | | |
|
|
|
|
Fee Review-notes | 7/24/2003 | 7/24/2003 | | | |
|
|
|
|