DOC - Permit Finaled | | | 12/9/2003 | | DONE |
|
|
|
|
First Notice | | 12/8/2003 | 12/8/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/8/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9895 issued 12-8-03 to Asin Homes Office.
|
Permanent Occupancy | | 12/4/2003 | 12/4/2003 | | DONE |
|
|
|
|
BLD-Final | 12/4/2003 | 12/4/2003 | 12/4/2003 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/4/2003 at 9:50:16 AM. Contact: ###-####.
ok for perm. c of occupancy 12/4/2003 3:33:01 PM
|
FIRE-Final Inspection | 11/20/2003 | 11/20/2003 | 11/20/2003 | P | PASS |
Troy Cobbley
|
|
|
Structural inspector to verify the removal of the thumbturn from the main exit, provide approved door hardware on the east exit door 11/20/2003 1:07:35 PM
|
BLD-Final | 11/20/2003 | 11/20/2003 | 11/20/2003 | P | PART |
Tony Young
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
ok for temp. occ. pending trades, door hardware, energy code,etc 11/20/2003 4:19:05 PM
|
FIRE-Final Inspection | 11/18/2003 | 11/18/2003 | 11/18/2003 | P | FAIL |
Troy Cobbley
|
|
|
remove thumbturn from the main exit, provide approved door hardware on the east exit door and test the duct smoke detectors 11/18/2003 2:30:48 PM
|
Print Occupancy Form | | | 11/14/2003 | | DONE |
|
|
|
|
BLD-Wall cover | 9/25/2003 | 9/25/2003 | 9/25/2003 | P | PASS |
Tony Young
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs
also see bld 03-00493 9/25/2003 3:55:49 PM
|
BLD-Framing/Rough-in | 9/23/2003 | 9/23/2003 | 9/23/2003 | P | PART |
Steven Webb
|
|
|
C/N issued 9/23/2003 3:59:06 PM
|
Issue PAID IN FULL permit | | | 9/11/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/10/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/10/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2003 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (R_H) | 8/1/2003 | | 9/10/2003 | | PASS |
|
|
|
9/10/2003 13:37:18 RMH - activity updated through activity BLDA022 from case BLD03-01836.
|
Routing - PLAN CHECK | 9/5/2003 | | 9/10/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/9/2003 | | DONE |
|
|
|
received three sets of 3-TI, P0.0, P1.1 taken to Ron H.
|
Routing - FIRE | 8/29/2003 | | 9/5/2003 | | PASS |
|
|
|
Approved subject to satisfactory field inspeciton to verify IFC compliance. (No written comments).
|
Routing - PLAN CHECK | 8/4/2003 | | 8/29/2003 | | FAIL |
|
|
|
Faxed and mailed requirements to Mike Fairchild on 8/29/03, Routed plans to the fire department same day.
|
Routing - PUBLIC WORKS | 8/1/2003 | | 8/4/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2003 | | DONE |
|
|
|
|
Application received | | | 7/30/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/30/2003 | | DONE |
|
|
|
|
Fee Review-notes | 7/30/2003 | 7/30/2003 | | | |
|
|
|
|