Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/28/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 9/28/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10309 issued 9-28-04 to the Richard Davis Office Building.
|
Permanent Occupancy | | 9/27/2004 | 9/27/2004 | | DONE |
|
|
|
|
BLD-Final | 9/24/2004 | 9/27/2004 | 9/27/2004 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/24/2004 at 3:47:28 PM. Contact: ###-####. OK for Perm. :) 9/27/2004 10:38:36 AM
|
BLD-Final | 9/24/2004 | 9/27/2004 | 9/27/2004 | A | PASS |
Jim Sly
|
|
|
raylene; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Perm. :) 9/27/2004 10:38:54 AM
|
Code Occupancy Approval | | | 9/24/2004 | | DONE |
|
|
|
Meets compliance with CUP and DR - Final - OK
|
BLD-Final | 9/23/2004 | 9/23/2004 | 9/23/2004 | P | NR |
Jim Sly
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 9/23/2004 2:59:55 PM Need Code Enforce final. 9/23/2004 3:17:26 PM
|
Temporary occupancy | | | 7/30/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5128 issued 7-30-04 to the Richard Davis Ofc. Bldg.
|
BLD-Final | 7/29/2004 | 7/29/2004 | 7/29/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/29/2004 at 7:32:43 AM. Contact: ###-####. OK for Temp Occ. Owner has bonded for landscaping. C/N....Need Perm Occ. status within 90 days of this notice. 7/29/2004 2:24:35 PM
|
BLD-Final | 7/27/2004 | 7/28/2004 | 7/28/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/27/2004 at 8:47:26 AM. Contact: ###-####. Need plumb final. 7/28/2004 8:18:57 AM
|
FIRE-Final Inspection | 7/28/2004 | 7/28/2004 | 7/28/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 7/28/2004 3:51:43 PM
|
BLD-Final | 7/26/2004 | 7/27/2004 | 7/27/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/26/2004 at 10:37:23 AM. Contact: ###-####. Need all req. signatures. 7/27/2004 8:19:29 AM
|
FIRE-Final Inspection | 7/27/2004 | 7/27/2004 | 7/27/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide "Door to remain unlocked while building is occupied" sticker at main entry/exits. Remove the dead bolt locks on all doors except the main entry/exit doors. Provide building address and suite numbers. Relocate fire hydrant so large outlet is accessible from the driveway. Paint curbing for fire dept. access per review note #11 and sheet A1.0. Install fire extinguishers per review note #13. Provide duct smoke detectors on units 2 and 3 per review note #27. 7/27/2004 1:54:48 PM
|
PubWorks Occupancy Approval | 7/26/2004 | 7/26/2004 | 7/26/2004 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 7/26/04. G.Fitts
|
BLD-Energy code compliance | 6/8/2004 | 6/9/2004 | 6/9/2004 | P | PASS |
Jim Sly
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 6/4/2004 | 6/7/2004 | 6/7/2004 | A | FAIL |
Jim Sly
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Annette Moore C/N posted 6/7/2004 12:59:50 PM
|
BLD-Framing/Rough-in | 6/7/2004 | 6/7/2004 | 6/7/2004 | P | DONE |
Tom Arcoraci
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Foundation | 4/19/2004 | 4/20/2004 | 4/20/2004 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/19/2004 at 2:40:16 PM. Contact: ###-####. wip subject to s-i. 4/19/2004 9:57:36 PM
|
BLD-Footing | 4/16/2004 | 4/19/2004 | 4/19/2004 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/16/2004 at 2:35:58 PM. Contact: ###-####. Strata doing special insp.... Footing OK pend special insp reports and approval. 4/19/2004 4:10:13 PM
|
(F) Reprint permit | | | 4/15/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/14/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2004 | | DONE |
|
|
|
talked to todd with vertical that permit is ready
|
Telephone call | | | 4/8/2004 | | DONE |
|
|
|
Left message for Todd per Bob Arcxhibald that this permit must be picked up tomorrow in the am as they are doing site work with out permit///4/8/04 BAM
|
Plan assigned to (JCM) | 8/4/2003 | | 3/10/2004 | | PASS |
John Menard
|
|
|
3/10/2004 13:36:38 JCM - activity updated through activity BLDA022 from case BLD03-01840.
|
Routing - PUBLIC WORKS | 3/3/2004 | | 3/10/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/10/2004 | | 3/10/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/10/2004 | | DONE |
|
|
|
Received one copy of revised sheet M2.0. Routed to John M. kmm
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2004 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/10/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 3/5/2004 | | DONE |
|
|
|
Received two sets of EL-1,EL-2 taken to John M.
|
Plan Reviewer's activity | | | 3/2/2004 | | PASS |
|
|
|
Reviewed and approved resubmittals. JCM
|
Plan resubmittals requested | | | 3/2/2004 | | |
|
|
|
Called the architect and requested a second copy of plans sheet M2.0. JCM
|
Routing - FIRE | 2/24/2004 | | 2/27/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Plan resubmittals received | | | 2/27/2004 | | DONE |
|
|
|
Received five copies of revised sheets C1.0, C1.1, C1.2, C1.3, two copies of O and M manual and two copies of Storm Water Management Plan. Two copies of revised sheetsA8.0 and A3.0. One copy of sheet M2.1. One copy of plan review conditions. Routed to John M. kmm
|
Routing - PLUMBING | 2/20/2004 | | 2/23/2004 | | PASS |
|
|
|
1. need four inch vent through roof to meet cross sectional area venting 2. need expansion tank
|
Routing - PUBLIC WORKS | 2/18/2004 | | 2/20/2004 | | FAIL |
|
|
|
Needs 3 copies of revised drainage plan.
|
Routing - PLAN CHECK | 9/11/2003 | | 2/18/2004 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 2/18/2004 | | |
|
|
|
Faxed the architect a comment list requesting additional revisions. JCM
|
Routing Off Site -Energy | 8/5/2003 | | 2/18/2004 | | PASS |
|
|
|
Contacted Eric Makela for outside energy review. kmm Reviewed and approved resubmitted energy information. JCM
|
Plan resubmittals received | | | 2/6/2004 | | DONE |
|
|
|
Received one copy of response letter to John M. One copy of response letter to Dave Miller. Two copies of plan review report. One copy of fire flow. One copy of struc. calculations. One copy of Envelope compliance cert. 81/2 x 11. One copy of involved Parties sheet and one copy of design prof. in responsible charge. Three copies of P1, M2.0, M4.0, M5.0, S1.1, S1.2, A8.0, A6.0, A3.0, A2.0, A1.0. Routed to John M. kmm
|
Plan Reviewer's activity | | | 1/13/2004 | | |
|
|
|
Resent, by fax, copies of the plan review comment list and energy review list. JCM
|
Routing - FIRE | 9/3/2003 | | 9/11/2003 | | FAIL |
|
|
|
FD access and fire hydrant issues. Copy of comments faxed to architect.
|
Plan resubmittals requested | | | 9/2/2003 | | |
|
|
|
Mailed the architect a copy of the plan review and energy review comment lists requesting revisions. JCM
|
Routing - PLAN CHECK | 8/25/2003 | | 9/2/2003 | | FAIL |
|
|
|
|
Routing - PLUMBING | 8/22/2003 | | 8/25/2003 | | FAIL |
|
|
|
1. water and dwv need sizes 2. need premise backflow protection 3. need fixture schedule showing sizes 4. water heater needs pan with a drain to approved location
|
Routing - PLANNING | 8/19/2003 | | 8/22/2003 | | PASS |
|
|
|
Approved.
|
Routing - Erosion and Sediment | 8/15/2003 | | 8/19/2003 | | PASS |
|
|
|
ESC approved with conditons attached to plans.
|
Plan resubmittals received | | | 8/15/2003 | | DONE |
|
|
|
received four copies of revised sheet C1.2 and Geotech. report. Routed to John M. kmm
|
Routing - PUBLIC WORKS | 8/5/2003 | | 8/15/2003 | | FAIL |
|
|
|
Requires (3) more copies of drainage plan revision. Per Brian Murphy.
|
Plan resubmittals received | | | 8/12/2003 | | DONE |
|
|
|
Revcievd four copies of revised sheet C1.0 and one copy of Capitol Water letter.
Routed to John M. kmm
|
Routing - PLANNING Land Div | 8/1/2003 | | 8/5/2003 | | PASS |
|
|
|
Approved, exisiting building approved with building permit issued on same parcel.
|
Pending Assignment by JCM | 8/1/2003 | | 8/4/2003 | | DONE |
John Menard
|
|
|
8/4/2003 09:24:05 JCM - activity updated through activity BLDA166 from case BLD03-01840.
|
Plan resubmittals received | | | 8/4/2003 | | DONE |
|
|
|
one fire flow sheet with a fax transmittal sheet taken to John M.
|
Plans ACCEPTED BY PLAN TECH | | | 8/1/2003 | | DONE |
|
|
|
|
Application received | | | 7/30/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 2/27/2004 | | | | |
|
|
|
|