Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD03-01849
StatusFinaled
Name BRATNEY COMPANIES
Site Address 565 W MYRTLE ST Unit: 250
Project NamePARK PLAZA-2ND FLR
Customer Number 
ePlanReviewNo
Description
(BRATNEY COMPANCIES - SUITE 250 - SOUTH SIDE) Fire sprinklers substitute for 1-hr fire-resistant rated construction. To remodel a 4,604 square foot office tenant space located on the 2nd floor (South side) of a 4 story building. Most work is being performed within a 2,787 square foot area. An egress door for the remaining 1,817 square feet is being relocated. A demolition permit (BLD03-02070) was issued earlier. Work is to include interior nonbearing walls, millwork, suspended ceilings, and finishes all per the approved drawings and the plan review report on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/200310/31/200310/31/2003APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/30/2003 at 1:49:37 PM. Contact: ###-####. ok for perm occ. 10/31/2003 9:17:17 AM
Letter of compliance  10/31/2003 DONE
Letter of Compliance #24317 issued 10-31-03.
FIRE-Final Inspection10/29/200310/30/200310/30/2003APASS
DetailsTroy Cobbley
fire alarm, fire sprinkler and fire life safety finaled 10/30/2003 2:31:43 PM
BLD-Framing/Rough-in10/7/200310/7/200310/7/2003PPASS
DetailsDave Hannah
BRANDON CEILING GRID; Phone #: ###-#### Internet Inspection Request from: Annette Moore ok to drop in pannals c/n items completed 10/7/2003 3:30:24 PM
BLD-Framing/Rough-in10/3/200310/6/200310/6/2003ACANC
DetailsRuss Owen
brandon celing grid; Phone #: ###-#### Internet Inspection Request from: Darla Downsout of time rolled over for pm. 10/5/2003 7:07:24 PM
BLD-Framing/Rough-in10/5/200310/6/200310/6/2003PFAIL
DetailsRuss Owen
ceiling grid 10/5/2003 7:05:02 PM left over from am. 10/5/2003 7:08:34 PM light cans in room 110 need support wires. called and talked to contractor will recall. 10/5/2003 10:13:36 PM
BLD-Framing/Rough-in9/16/20039/16/20039/16/2003PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/16/2003 at 8:08:34 AM. Contact: ###-####.c/n items completed 9/16/2003 3:36:28 PM
FIRE-Conference9/12/20039/15/20039/15/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 9/12/2003 at 3:30:54 PM. Contact: ###-####. met with GC and a fire sprinkler permit is required due to overspacing of sprinklers; extinguishers; exit signs 9/15/2003 10:36:06 AM
BLD-Framing/Rough-in9/12/20039/12/20039/12/2003PPART
DetailsDave Hannah
brandon; Phone #: ###-#### Internet Inspection Request from: Darla Downsok to cover after elec also need to check elec hole on back side of elev shaft and remover screws that fasten ceil track to walls 9/12/2003 4:47:36 PM
Issue PAID IN FULL permit  9/11/2003 DONE
Plan assigned to (CJW)8/1/2003 9/9/2003 PASS
DetailsCarl Westfall
9/9/2003 12:44:59 CJW - activity updated through activity BLDA022 from case BLD03-01849.
Routing - FIRE9/3/2003 9/9/2003 PASS
Routing - PLAN CHECK9/9/2003 9/9/2003 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/9/2003 PASS
Inspection Record Card- Bld  9/9/2003 DONE
Print Occupancy Form  9/9/2003 DONE
Permit Ready to Issue  9/9/2003 DONE
Telephone call  9/9/2003 DONE
PERMIT READY AND FEES DUE
Routing - PLAN CHECK8/5/2003 9/3/2003 PASS
IBC plan review started Sept. 2, 2003 and finished the next day. The drawings were approved with clarifications. See the plan review report. A copy was E-mailed to the architect.
Routing - PUBLIC WORKS8/1/2003 8/5/2003 PASS
Plans ACCEPTED BY PLAN TECH  8/1/2003 DONE
Application received  7/31/2003  
Recd Pcfee & Taken To Pln CK  7/31/2003 DONE
Fee Review-notes7/31/20037/31/2003