Permit Information
Permit NumberBLD03-01851
StatusFinaled
Name PETER H ROCKWELL
Site Address 8921 W HACKAMORE DR
Project NameAUDROC MORTGAGE BLDG
Customer Number 
ePlanReviewNo
Description
(Audroc Mortgage Building) * To construct a 5,479 one story , type VB office building. Other work includes all site improvements, paving and landscaping per approved plans and attachments, DRH03-00065. A "Letter of Compliance" is required as a condition of final approval for this permit, 'Shell & Core'.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD4/26/20054/26/20054/26/2005 DONE
First Notice has not been responded to.
First Notice 7/21/20044/26/2005 DONE
Permanent occupancy  7/21/2004 DONE
Perm. Occ. Cert. # 10239 issued 7-21-04 to the Audroc Mortgage Bldg.
Permanent Occupancy 7/20/20047/20/2004 DONE
Details
PubWorks Occupancy Approval5/26/20045/26/20045/26/2004 DONE
Drainage inspection complete, Cathy told to sign off for permanent occupancy 5/26/04. G.Fitts
BLD-Final4/29/20044/30/20044/30/2004AFAIL
DetailsRuss Owen
###-#### Craig. c/n posted. 4/30/2004 12:14:34 AM
BLD-Final4/29/20044/30/20044/30/2004ACANC
DetailsRuss Owen
craig; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Final4/29/20044/30/20044/30/2004PPART
DetailsRuss Owen
ok, for a temp oc, needs all signatures and the c/n ite###-#### Craig. c/n posted.ms completed for a perm oc. 4/30/2004 12:18:12 AM
Temporary occupancy  4/30/2004 DONE
Temp. Occ. # 5106 issued 4-30-04 to Audroc Mortgage Building.
FIRE-Final Inspection4/28/20044/29/20044/29/2004ANR
DetailsTroy Cobbley
Contractor is not ready. Inspection to be rescheduled for afternoon 4/29/2004 10:34:53 AM
FIRE-Final Inspection4/29/20044/29/20044/29/2004PPASS
DetailsTroy Cobbley
Fire life safety for the shell/core finaled 4/29/2004 2:49:52 PM
Code Occupancy Approval Temp  4/29/2004 DONE
BOND IN PLACE SO I SIGNED OFF TEMP. OCCUPANCY.
FIRE-Final Inspection4/27/20044/28/20044/28/2004AFAIL
DetailsTroy Cobbley
Relocate emergency light at the south entry. Add an emergency light in the long corridor. Paint fire dept. access as discussed. Provide correct sticker at the main entry exits. Provide approved door hardware on doors 130-1 and 130-2 per plan review note #48. Provide additional permits for the tenants. 4/28/2004 1:54:20 PM
FIRE-Final Inspection4/27/20044/27/20044/27/2004PFAIL
DetailsTroy Cobbley
Relocate the emergency light as discussed away one fixture at the south exit. Add one emergency light in the middle of the long corridor. Paint curbing for fire dept. access per drawing sheet A.1 as discussed. Provide building address. Provide correct sticker at the main entry/exit. Resubmitt plans to the city for clarification on number of tenants for the building.
Code Occupancy Approval Temp4/27/20044/27/20044/27/2004PPART
DetailsScott M.Brown
TO BOND FOR $15246 INCOMPLETE LANDSCAPE, I WAS TOLD THE REST WOULD BE IN PLACE? WHEN BOND POSTED WITH CATHY I CAN SIGN TEMP OCCUPANCY4/27/2004 3:48:00 PM 4/27/2004 3:48:45 PM
BLD-Other4/14/20044/15/20044/15/2004APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 4/14/2004 at 11:30:35 AM. Contact: ###-####. need perimeter wires in hall rest ok. 4/14/2004 11:23:18 PM
BLD-Energy code compliance3/10/20043/11/20043/11/2004APASS
DetailsRuss Owen
BLD-Energy code compliance3/10/20043/10/20043/10/2004PCANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/10/2004 at 8:45:10 AM. Contact: ###-####. out off time. 3/10/2004 6:13:23 PM
BLD-Framing/Rough-in3/5/20043/5/20043/5/2004PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/5/2004 at 9:04:16 AM. Contact: ###-####. needs king studs added, ok to insulate other items ok. 3/5/2004 12:12:23 AM
BLD-Framing/Rough-in3/2/20043/2/20043/2/2004PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/2/2004 at 9:48:25 AM. Contact: ###-####. c/n posted ok to insulate. 3/2/2004 12:02:29 AM
BLD-Framing/Rough-in2/20/20042/23/20042/23/2004APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 2/20/2004 at 11:46:20 AM. Contact: ###-####.ok to side. 2/22/2004 11:21:54 PM
BLD-Framing/Rough-in2/17/20042/18/20042/18/2004AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 2/17/2004 at 4:06:04 PM. Contact: ###-####.a few areas need nailing and some clairification on anchor bolts contractor on site with c/n. 2/18/2004 12:33:58 AM
BLD-Framing/Rough-in2/12/20042/13/20042/13/2004APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 2/12/2004 at 10:10:55 AM. Contact: ###-####. roof ok for cover 2/13/2004 11:06:36 AM
BLD-Framing/Rough-in2/6/20042/9/20042/9/2004PFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 2/6/2004 at 4:57:51 PM. Contact: ###-####. Roof needs additional nailing ,2 hold downs need installation, 1 is hd 8 needs to be hd 10. Went over areas with contractor will need to recall. 2/9/2004 5:49:57 PM
BLD-Framing/Rough-in2/2/20042/2/20042/2/2004PFAIL
DetailsTroy James
Craig; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
Shear wall inspection not complete too many areas not nailed off. Informed contractor not to install anymore felt on roof without naiing inspection complete. 2/2/2004 4:08:20 PM
BLD-Foundation12/9/200312/10/200312/10/2003ANR
DetailsRuss Owen
Alan; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Foundation12/10/200312/10/200312/10/2003PPART
DetailsRuss Owen
Ok special inspecion performed. 12/10/2003 3:25:03 PM
BLD-Footing12/5/200312/8/200312/8/2003APART
DetailsRuss Owen
Alan; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes OK BY SPECIAL INSP. 12/8/2003 2:32:48 PM
(F) Reprint permit  12/2/2003  
Issue PAID IN FULL permit  12/1/2003 DONE
Routing - PUBLIC WORKS11/4/2003 11/6/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/6/2003 DONE
Inspection Record Card- Bld  11/6/2003 DONE
Print Occupancy Form  11/6/2003 DONE
Permit Ready to Issue  11/6/2003 DONE
Telephone call  11/6/2003 DONE
Spoke with Justin told permit ready & fees and that we need info from ACHD
Plan assigned to (MLO)8/4/2003 11/6/2003 PASS
DetailsMike Otto
11/6/2003 14:13:57 MLO - activity updated through activity BLDA022 from case BLD03-01851.
Routing Off Site -Energy9/19/2003 9/30/2003 PASS
called Eric for pickup
Routing - PLAN CHECK9/18/2003 9/19/2003 PASS
Plan resubmittals received  9/18/2003 DONE
Received a letter of transmittal, letter to Mike O., two copies of resistered design professional in responsible charge.,two copies of a memo from Stapley Engineering,. 3 sheets of CVR, 2 E1 sheets, 2 A-1.3 sheets, 2 A-4.1 sheets, 2 A-5.1 sheets, taken to Mike Otto.
Routing - FIRE9/10/2003 9/10/2003 PASS
resubmittal acceptable.
Routing - PUBLIC WORKS9/9/2003 9/10/2003 FAIL
April Miller failed.
Plan resubmittals received  9/9/2003 DONE
Received one copy of United Water letter. Routed to Mike O. kmm
Routing - FIRE9/2/2003 9/8/2003 FAIL
United Water verification of water supply required.
Routing Off Site -Energy8/5/2003 9/2/2003 FAIL
Contacted Eric M for energy review. Corrections sent to architect
Plan resubmittals requested  9/2/2003 DONE
IBC and energy corrections
Routing - PLAN CHECK8/25/2003 9/2/2003 FAIL
corrections faxed and mailed to architect
Routing - PLUMBING8/19/2003 8/22/2003 PASS
Sewer is sleeved under seepage well.
Routing - PLANNING8/14/2003 8/19/2003 PASS
Approved per DRH03-65.
Routing - Erosion and Sediment8/13/2003 8/14/2003 PASS
ESC approved with conditions attached to plans. Individual listed as RP has not been certified by Boise City.
Routing - PUBLIC WORKS8/5/2003 8/13/2003 FAIL
Need to show correct easement lines on property. Per April Miller. Reuires drainage plan revision per Brian M. kmm
Routing - PLANNING Land Div8/1/2003 8/5/2003 PASS
Approved as Parcel 2A on ROS 3815 approved by City Engineer on March 14, 1997.
Pending Assignment by JCM8/1/2003 8/4/2003 DONE
DetailsJohn Menard
8/4/2003 09:22:49 JCM - activity updated through activity BLDA174 from case BLD03-01851.
Plan resubmittals received  8/4/2003 DONE
received fax transmittal sheet with registered design professional in responseible charge sheet taken to Mike O.
Plans ACCEPTED BY PLAN TECH  8/1/2003 DONE
Waiting for signed responible party sheet. Needs to have envelope compliance cert. signed. kmm
Plan routing begun/NEW & ADDTN  8/1/2003 DONE
Application received  8/1/2003  
Recd Pcfee & Taken To Pln CK  8/1/2003 DONE
Fee Review-notes8/1/20038/1/2003