Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/16/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/16/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10188 issued 6-16-04 to Waxi Sanitary Supply Company.
|
Print Occupancy Form | | | 6/15/2004 | | DONE |
|
|
|
|
BLD-Final | 3/18/2004 | 3/19/2004 | 3/19/2004 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 3/18/2004 at 4:22:37 PM. Contact: ###-####. Ok for a perm oc, fire has signed off. 3/18/2004 5:45:27 PM 3/18/2004 5:45:38 PM
|
Permanent Occupancy | | 3/19/2004 | 3/19/2004 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/6/2004 | 2/6/2004 | 2/6/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
Plan resubmittals received | | | 1/5/2004 | | DONE |
|
|
|
Received one copy of Hax Mat report. Routed to Ron Hill. kmm
|
BLD-Final | 11/10/2003 | 11/14/2003 | 11/14/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/10/2003 at 5:00:47 PM. Contact: ###-####. Ok for temp pending fire for perm. 11/13/2003 6:37:16 PM
|
FIRE-Final Inspection | 11/10/2003 | 11/12/2003 | 11/12/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/10/2003 at 4:59:59 PM. Contact: ###-####. Dave Miller approved temp occupancy for fire/life safety pending fire alarm submittals for required duct detectors on RTU 1 and 2; 11/12/2003 9:38:36 AM
|
BLD-Other | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/3/2003 at 7:23:38 AM. Contact: ###-####. Ok went with stand system ceiling.11/2/2003 10:11:04 PM 11/2/2003 10:11:13 PM
|
BLD-Other | 10/27/2003 | 10/28/2003 | 10/28/2003 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/27/2003 at 7:57:12 AM. Contact: ###-####. 10/28/2003 10:15:39 AM C/N provide eng for ceiling grid.....standard or floating system? (no seismic pods) 10/28/2003 10:19:17 AM
|
Plan resubmittals received | | | 10/6/2003 | | DONE |
|
|
|
Reveived letter of transmittal with two sheets of M1.0 taken to Ron H.
|
BLD-Framing/Rough-in | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | PASS |
Russ Owen
|
|
|
/2003 1:08:07 AM 9/30/2003 1:08:21 AM 9/30/2003 1:09:50 AM ok to drywall 9/30/2003 4:56:29 PM
|
BLD-Framing/Rough-in | 9/29/2003 | 9/30/2003 | 9/30/2003 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/29/2003 at 9:23:31 AM. Contact: ###-####. out of time 9/30/2003 5:20:45 PM
|
Inspection Record Card- Bld | | | 9/16/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/16/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/16/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2003 | | DONE |
|
|
|
called & left message that permit was ready & fees amount
|
Issue PAID IN FULL permit | | | 9/16/2003 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 8/7/2003 | | 9/15/2003 | | PASS |
|
|
|
9/15/2003 14:18:45 RMH - activity updated through activity BLDA022 from case BLD03-01854.
|
Routing - PLAN CHECK | 9/10/2003 | | 9/15/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2003 | | DONE |
|
|
|
|
Routing - FIRE | 9/3/2003 | | 9/10/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/11/2003 | | 9/2/2003 | | PEND |
|
|
|
No corrections required by building department review, permit pending fire departments review, routed to fire on 9/3/03
|
Routing - PUBLIC WORKS | 8/7/2003 | | 8/11/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/5/2003 | | DONE |
|
|
|
|
Application received | | | 8/1/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/1/2003 | | DONE |
|
|
|
|
Fee Review-notes | 8/1/2003 | 8/1/2003 | | | |
|
|
|
|