Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD03-01880
StatusExpired
Name MARK BOWEN
Site Address 1338 S ORCHARD ST
Project NameORCHARD CENTER MALL
Customer Number 
ePlanReviewNo
Description
("VANILLA FINISH" - NO TENANT / NO OCCUPANCY) To construct interior perimeter walls to create a 1,226 sq. ft. future tenant space. Work to include change out of existing exterior glazing for storefront entry door; interior tenant separation walls and electrical & HVAC rough-in to space. A "Letter of Completion / Compliance" required as a condition of tis permit for this future tenant space. NOTE: This building fire sprinklered under BLD03-01810 / FIR03-00390. Separate sprinkler permit required for modification or addition relating to this space. DRH03-00119; PC03-458/drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection5/18/20045/18/20045/18/2004 CANC
DetailsTom Arcoraci
DOC - Permit Expired5/18/20045/18/20045/18/2004APASS
DetailsTom Arcoraci
Expired by inspector at 5/18/2004 8:34:11 AM
BLD-Aging Inspection3/4/20043/4/20043/4/2004 NR
DetailsTom Arcoraci
ex 3-24 3/8/2004 8:09:21 AM
BLD-Final11/17/200311/18/200311/18/2003PPASS
DetailsTom Arcoraci
Mark --- later afternoon please. thanks.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok for perm 11/18/2003 2:09:35 PM
FIRE-Final Inspection11/17/200311/17/200311/17/2003PPASS
DetailsTroy Cobbley
fire life safety finaled
BLD-Final10/2/200310/3/200310/3/2003PCANC
DetailsTom Arcoraci
###-####
Plan assigned to (DRS)8/5/20038/5/20039/26/2003 PASS
DetailsDan Stuart
9/26/2003 11:09:03 DRS - activity updated through activity BLDA022 from case BLD03-01880.
Inspection Record Card- Bld  9/26/2003 DONE
Issue & PRINT to be Invoiced  9/26/2003 DONE
Routing - PLAN CHECK9/25/2003 9/25/2003 PASS
Approved as note on plans and all attached plan review conditions by all reviewing agencies.
PLANS/APPL TAKEN TO FRONT DESK  9/25/2003 PASS
To permit desk for issue.
Routing - FIRE9/24/2003 9/24/2003 PASS
Snake River Pool & Spa (BLD03-01739) has been removed as part of this permit package and will be issued under separate plans so that the threVanilla Finish permits can be issued. No occupancy is allowed under this permit. Separate plans for each T.I. is required;the sprinkler system shall be approved; and separate application, plan, permit & approval by inspector of an sprinkler alarm monitoring system is required before a certificate of occupancy can be issued for any space.
Routing - FIRE9/17/2003 9/18/2003 PASS
Items related to this permit are acceptable but Haz Mat info not acceptable for Snake River Pool. Since all permits are on one set of plans, approved plans cannot be issued until the Snake River Pool issues are resolved. Faxed revised review to archtect.
Routing - PLAN CHECK9/15/2003 9/17/2003 PEND
New tenant space perimeter walls created. Restroom removed from scope of permit with the future tenant to be responsible for all code upgrade requirements.Routing to fire code analyst for review.
BLD-Conference9/10/20039/10/20039/10/2003PPASS
DetailsTom Arcoraci
mark
Plan resubmittals received  9/9/2003 DONE
Received two copies of revised sheets, A1.0, A1.1, A1.2, A1.3, A1.4, A2.1, A3.1, A3.2, E1.1, M0.0, M1.0, M2.0, one copy of response letter, four copies of envelope compliance cert., two copies of struct. claculations for orcard center mall openings, four copies of United Water letter, one copy of chemicals for pools and spa and response letter regarding the external storage area. Routed to Dan S. kmm
Plan resubmittals received  9/8/2003 DONE
To Dan Stuart
Routing - FIRE8/5/2003 8/11/2003 FAIL
Plan resubmittals requested  8/5/2003 FAIL
Requested clarification for new tenant space. Several details for this space were not included in the plan submittals of 7/31/03. Copy faxed; e-mailed & mailed to the architect.
Routing - PLAN CHECK8/5/2003 8/5/2003 FAIL
PLAN RESUBMITTALS ARE INCOMPLETE. FOURTH TENANT SPACE ADDED TO PLANS; ADDITIONAL RESTROOMS, DRINKING FOUNTAINS & SERVICES SINKS TO BE ADDED TO PLAN WILL REQUIRE ROUTING BACK TO PWS; NEW OPENING IN EXTERIOR WALL FOR ADDITIONAL REQUIRED EXITS WILL REQUIRE ROUTING BACK TO PLANNING; NEED SECOND PLAN SUBMITTALS BEFORE PLANS CAN BE RE-ROUTED TO ALL PARTIES FOR REVIEW. E-MAILED, FAXED AND MAILED COPY OF PLAN REVIEW COMMENTS TO ARCHITECT.
Telephone call  8/5/2003 DONE
Call from Mark Bowen contractor concerning plan resubmittals. Told him several items were unanswered or required addressing now because of project modifications. Mark has copy of hazardous materials that will be stored and or sold at Snake River Poll & Spa.Will send through architect.
Telephone call  8/5/2003 DONE
Call from Pat Dalgleish, architect saying he had hazardous materials list from contractor to provide. wanted to know if he could fax or I needed hard copy. Told him he could fax a copy to circulate with plans while a mailed copy was being delivered. Also told him their are several clarification needed for this project and that I will have list to him today.
Additional plans submitted  7/31/2003 DONE
Resubmittal plans for BLD03-01554; BLD03-01738; & BLD03-01739 added a 4th tenant space within the building. This permit was created to provide tracking method for this "Vanilla Finish" T.I.
Application received  7/25/2003  
Routing - PLANNING Land Div7/1/2003 7/1/2003 PASS
Approved as part of original submittals with BLD03-01554.
Routing - PUBLIC WORKS8/5/2003    
Routing - PLANNING8/5/2003