BLD-Aging Inspection | 5/18/2005 | 5/18/2005 | 5/18/2005 | | CANC |
Tom Arcoraci
|
|
|
|
DOC - Permit Expired | 5/18/2005 | 5/18/2005 | 5/18/2005 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/22/2004 | 1/22/2004 | 1/22/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
BLD-Final | 12/30/2003 | 12/31/2003 | 12/31/2003 | A | CANC |
Russ Owen
|
|
|
Mike; Phone #: ###-#### 8174 Vanilla finish Nail Salon.Internet Inspection Request from: Aimee Hughes
|
(F) Reprint permit | | | 12/19/2003 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/30/2003 | 10/30/2003 | 10/30/2003 | P | PASS |
Russ Owen
|
|
|
Herb; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
Issue PAID IN FULL permit | | | 10/15/2003 | | |
|
|
|
|
Plan assigned to (JCB) | 8/12/2003 | | 9/19/2003 | | PASS |
Jason Blais
|
|
|
9/19/2003 11:14:38 JCB - activity updated through activity BLDA022 from case BLD03-01927.
|
Routing - FIRE | 9/11/2003 | | 9/19/2003 | | PASS |
|
|
|
Project changed to a "vanilla finish" space.
|
Routing - PLAN CHECK | 9/19/2003 | | 9/19/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2003 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/19/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 9/19/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLAN CHECK | 8/26/2003 | | 9/11/2003 | | PEND |
|
|
|
Plans need to reroute to Public Works and to Fire Department for review again. Project has changed to a "vanilla finish" project. When approved by these divisions the permit can be issued.
|
Plan Reviewer's activity | | | 9/11/2003 | | |
|
|
|
Project has changed to a "vanilla finish" permit. Plans will need to be rerouted to other divisions again.
|
Routing - PUBLIC WORKS | 9/11/2003 | | 9/11/2003 | | PASS |
|
|
|
Service sink added.
|
Plan resubmittals received | | | 9/4/2003 | | |
|
|
|
Received two copies of revised sheets A1.0, A2.0, E-1, E-2, M1.0, M2.0, M3.0 and one copy of TI application. Routed to Jason B. kmm
|
Routing - FIRE | 8/20/2003 | | 8/26/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/13/2003 | | 8/20/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 8/12/2003 | | 8/13/2003 | | PASS |
|
|
|
|
Application received | | | 8/11/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/11/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/11/2003 | | DONE |
|
|
|
Less than $25,000
|
Fee Review-notes | 8/11/2003 | 8/11/2003 | | | |
|
|
|
|