Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD03-01957
StatusFinaled
Name BAKER KENNETH L
Site Address 7249 N PIERCE PARK LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 2251 sq. ft. two story single family dwelling with a 262 sq. ft. covered flagstone patio and a 900 sq. ft. detached two car garage per approved plans, all engineering and attached requirement lists. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and 30 ft. defensible space shall be maintained. Unless otherwise approved by the Boise City Fire Department, this structure shall be fitted with a 13D modified sprinkler system. The sprinkler flow alarm shall be attached to the residence smoke detection system. (1st floor 1776 sq. ft.)(2nd floor 475 sq. ft.) PC #535 CZC03-125 DJO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/10/20043/11/20043/11/2004APASS
DetailsTony Young
ken; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
DOC - Permit Finaled3/11/20043/11/20043/11/2004APASS
DetailsTony Young
Finaled by inspector at 3/11/2004 9:52:06 AM
BLD-Final3/2/20043/4/20043/4/2004PNR
DetailsSteven Webb
###-#### ken Needs fire and elec sign offs prior to structural inspection. 3/4/2004 3:08:26 PM
FIRE-Final Inspection3/4/20043/4/20043/4/2004PPART
DetailsTroy Cobbley
A temporary occupancy was given on the fire sprinkler permit with dave miller's permission until the backflow can be verified and the alarms work.
BLD-Grading Inspection3/2/20043/2/20043/2/2004 PASS
DetailsRita DeYoung
Final grading and drainage approved. The engineer and the City recommend that the roof drains be piped away from the foundation as indicated on the approved plan. However, the homeowner is willing to accept the risk of letting the drains discharge out onto the ground and Jim Wyllie is willing to let him do that.
BLD-Energy code compliance12/15/200312/16/200312/16/2003PPASS
DetailsTom Arcoraci
ken; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in12/11/200312/12/200312/12/2003PPASS
DetailsTony Young
Ken --- please call first for access.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Conference11/24/200311/24/200311/24/2003PPART
DetailsTony Young
ken ###-####
frame issues, cut floor joist, etc.,,, ext shear ok 11/24/2003 4:41:23 PM
BLD-Foundation9/18/20039/19/20039/19/2003APART
DetailsTom Arcoraci
DAVE; Phone #: ###-#### Internet Inspection Request from: Marc Lileks wip ok 9/19/2003 8:57:46 AM
BLD-Footing9/16/20039/16/20039/16/2003PPART
DetailsSteven Webb
dave; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip--ok, 95% ready at time of inspection. Need to finish rebar per plan. Ok to pour. 9/16/2003 1:18:22 PM
BLD-Grading Inspection9/15/20039/15/20039/15/2003 DONE
DetailsRita DeYoung
Geotech approved footing subgrade
Plan assigned to (DJO)9/5/20039/5/20039/8/2003 PASS
DetailsDan Overy
9/8/2003 10:54:57 DJO - activity updated through activity BLDA022 from case BLD03-01957.
Routing - Erosion and Sediment9/8/2003 9/8/2003 PASS
ESC approved with attached conditions.
Plan Reviewer's activity  9/8/2003 DONE
ESC approved. ok to issue
PLANS/APPL TAKEN TO FRONT DESK  9/8/2003 DONE
Inspection Record Card- Bld  9/8/2003 DONE
Print Occupancy Form  9/8/2003 DONE
Permit Ready to Issue  9/8/2003 DONE
Issue PAID IN FULL permit  9/8/2003 DONE
Case Summary (BLD)  9/5/2003  
Plan Review Report  9/5/2003  
Plan Reviewer's activity  9/5/2003  
ESC needs to be approved before issuance of permit.
Plans ACCEPTED BY PLAN CHECK  9/5/2003  
Routing - PLANNING Land Div9/3/2003 9/3/2003 PASS
Approved. Shared driveway approved by CZC03-00125.
Routing - FIRE8/29/2003 9/3/2003 DONE
This lot requires the dwelling to be provided with a 13D fire sprinkler system and have a fully paved driveway. Hydrants are to be installed as shown on the plans we received, and all houses ae to meet the requirements of the city Foothills ordinance. All buildings are required to contain Class A roofs and a 30 feet "defensible space" on the sides of the property that border wildlands.(Horizon Hills)
Routing - Erosion and Sediment8/29/2003 8/29/2003 FAIL
ESC plan looks ok but listed RP not certified by Boise City, telephone and informed person to get Int. Certification.
Routing - PLANNING8/29/2003 8/29/2003 PASS
Per conditions of CZC03-125.
Routing - PLANNING8/20/2003 8/21/2003 FAIL
S. Riggs: Shared Drive CZC03-125 issued 8/27/2003
Routing - PLANNING Land Div8/19/2003 8/20/2003 PEND
Prior to issuance of building need approval of zoning certificate for shared driveway.
Routing - PUBLIC WORKS8/19/2003 8/19/2003 PASS
WET LINE WAIVER TO BE RETURNED TO PUBLIC WORKS PRIOR TO ISSUANCE OF BUILDING PERMIT.LOUISE
Routing - PUBLIC WORKS GRADING8/13/2003 8/18/2003 PASS
DetailsRita DeYoung
APPROVED AS CATEGORY 3 WITH CONDITIONS OF APPROVAL IN LETTER ATTACHED TO THE PLANS
Application received  8/13/2003  
Pending Assignment by DJO8/13/2003    
DetailsDan Overy
Routing - PLAN CHECK9/3/2003