Case Summary (BLD) | | | 9/2/2010 | | |
|
|
|
|
Case Summary (BLD) | | | 3/21/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 1/6/2005 | | |
|
|
|
|
Expired/Cancelled | 11/3/2004 | 11/3/2004 | 11/3/2004 | | DONE |
|
|
|
expired by limitation 10/10/04. No activity.
|
DOC - Permit Expired | | | 11/3/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/21/2004 | | |
|
|
|
|
MISC ACTIONS | | | 9/20/2004 | | PART |
Bob Archibald
|
|
|
Site visit on 9/17/04 structure has been secured per code enforcements notice. Lock placed on work door. Temporary bracing still in place.
|
BLD-Other | 9/3/2004 | 9/3/2004 | 9/3/2004 | A | FAIL |
Bob Archibald
|
|
|
Site investigation with code enforcement. Report of fire response. No structural damage caused by fire, strucure open and accessible no work has been performed on this permit. Code enforcement issued notice of violation seeking exterior cleanup of weeds and building materials also securing of structure against entry. COD04-01397
|
BLD-Other | 6/23/2004 | 6/23/2004 | 6/23/2004 | P | |
Bob Archibald
|
|
|
No new construction activity in progress.
|
Issue PAID IN FULL permit | | | 4/13/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2004 | | DONE |
|
|
|
customer will pickup permit april 15th
|
MISC ACTIONS | | | 3/26/2004 | | PART |
Bob Archibald
|
|
|
Larry Sundell informed me that permit would be obtained within 2 weeks.
|
Case Summary (BLD) | | | 3/24/2004 | | |
|
|
|
|
Case Summary (BLD) | | | 3/24/2004 | | |
|
|
|
|
Telephone call | | | 2/26/2004 | | DONE |
|
|
|
per larry sundell will pickup around march 1st
|
Telephone call | | | 1/29/2004 | | DONE |
|
|
|
talked to larry swindell that permit is ready to pickup
|
Inspection Record Card- Bld | | | 1/2/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/2/2004 | | DONE |
|
|
|
|
Telephone call | | | 1/2/2004 | | DONE |
|
|
|
called resource management permit ready for pick up
|
Routing - PLAN CHECK | 12/26/2003 | | 12/30/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/30/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/30/2003 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 8/19/2003 | | 12/30/2003 | | PASS |
Mike Phillips
|
|
|
12/30/2003 09:24:19 M_P - activity updated through activity BLDA022 from case BLD03-01962.
|
Routing - FIRE | 12/19/2003 | | 12/24/2003 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - PLAN CHECK | 12/3/2003 | | 12/19/2003 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 12/17/2003 | | DONE |
|
|
|
Received a letter from United Water, taken to Mike P.
|
Plan resubmittals received | | | 12/15/2003 | | DONE |
|
|
|
Received three copies of reivsed sheets one, three, four, five, six, seven, and one copy of responce letter. Routed to Mike P. kmm
|
Routing - PLANNING | 12/1/2003 | | 12/3/2003 | | PASS |
|
|
|
Changing location of exterior stairs and removing windows in basement.
|
Routing - FIRE | 11/28/2003 | | 12/1/2003 | | FAIL |
Bill Alexander
|
|
|
Found no response to hydrant location/s or water flow requirements.
|
Routing - PLAN CHECK | 12/1/2003 | | 12/1/2003 | | |
|
|
|
Routing to planning.
|
Routing - PLAN CHECK | 10/13/2003 | | 11/28/2003 | | FAIL |
|
|
|
Second review failed, sent correction report to architect requesting additional informaiton be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 10/22/2003 | | DONE |
|
|
|
Received two copies of response letter and calculations. Four copies of revised sheets one thru seven S0, S1, S2, S3, S4, S5, S6, S7, S8. Routed to Mike P. kmm
|
Routing - PUBLIC WORKS | 10/6/2003 | | 10/13/2003 | | PASS |
|
|
|
Clarification for renovation & remodel of existing building.
|
Routing - FIRE | 9/29/2003 | | 10/6/2003 | | FAIL |
|
|
|
review comments faxed to architect and attached; issues related to H occupancy.
|
Routing Off Site - STRUCTURAL | 8/19/2003 | | 9/29/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside engineering. kmm
Second review completed by City's plan reviewer.
|
Routing - PLAN CHECK | 8/27/2003 | | 9/29/2003 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be resubmitted for further review prior to issuing permit.
|
Routing Off Site -Energy | 8/19/2003 | | 9/22/2003 | | PASS |
|
|
|
Contacted Eric M for energy review.
No energy review required. Historic building as declaired by Jeff Neberman.
|
Routing - PLUMBING | 8/25/2003 | | 8/27/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/22/2003 | | 8/25/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 8/20/2003 | | 8/22/2003 | | FAIL |
|
|
|
STATUS UNKNOWN: NEW BUILDING? DEMO? CONFLICTING INFO.
|
Routing - PLANNING | 8/22/2003 | | 8/22/2003 | | PASS |
|
|
|
Complies with Conditions on DRH02-00224
|
Plans ACCEPTED BY PLAN TECH | | | 8/21/2003 | | DONE |
|
|
|
Received four copies of P-1 sheet. put with plans. kmm
|
Routing - PLANNING Land Div | 8/19/2003 | | 8/20/2003 | | PASS |
|
|
|
Approved. Parcel is consolidated under one tax parcel # and parcel was created prior to October 30, 1965.
|
Plans ACCEPTED BY PLAN TECH | | | 8/19/2003 | | DONE |
|
|
|
1. Still waiting on plumbing sheets.
|
Plans ACCEPTED BY PLAN TECH | | | 8/15/2003 | | |
|
|
|
1. No energy compliance sheets.
2. No plumbing, mechanical, and electrical plans.
3. Need "New commercial, Additions..." application. (Adding a basement)
4. Need one more ESC narrative.
5. Called Larry Sundell (left message) that these documents are required before routing can start. Placed on "hold" until received.
8/15/03 1545 Received (1) extra ESC narrative.
Received "New Commercial..." application
Plumbing sheets will be submitted next week. No Mech or Elect will be done at this time since there are no tenants. Energy compliance not required per Dan Stuart.
|
Application received | | | 8/13/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/13/2003 | | DONE |
|
|
|
|
Fee Review-notes | 8/13/2003 | 8/13/2003 | | | |
|
|
|
|