Permit Information
Permit NumberBLD03-01973
StatusFinaled
Name DIAMOND RIDGE CONSTRUCTION
Site Address 1816 -1818 W YALE CT
Project Name 
Customer Number 
ePlanReviewNo
Description
DEMOLITION of a existing structure on the property before constructing a 2880 sq. ft. two story DUPLEX. Each unit is a four bedroom; four bathroom 1440 sq. ft single story with (2) 18' x 20' concrete parking pads. One unit is above the other unit. Per approved plans and requirement list. THIS STRUCTURE IS BEING BUILT TO ONLY MEET DUPLEX STANDARDS AND NOT TO BE SOLD AS INDIVIDUAL UNITS. PC#494 (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/8/20047/9/20047/9/2004PPASS
DetailsJim Storey
nathan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
DOC - Permit Finaled7/9/20047/9/20047/9/2004PPASS
DetailsJim Storey
Finaled by inspector at 7/9/2004 2:51:54 PM
BLD-Framing/Rough-in3/9/20043/10/20043/10/2004ACANC
DetailsTom Arcoraci
NATHAN; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Energy code compliance3/10/20043/10/20043/10/2004APASS
DetailsTom Arcoraci
BLD-Framing/Rough-in3/5/20043/5/20043/5/2004PPASS
DetailsJim Storey
nathan; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Framing/Rough-in3/1/20043/1/20043/1/2004PNR
DetailsRuss Owen
nathan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 1 hr ceiling assembly ,with opening protection required no provisions have been made to protect openings. 2/29/2004 9:13:36 PM
Case Summary (BLD)  2/5/2004  
BLD-Foundation12/17/200312/18/200312/18/2003APART
DetailsJim Storey
Chris; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Footing12/16/200312/17/200312/17/2003APASS
DetailsJim Storey
Chris; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
Issue PAID IN FULL permit  12/16/2003 DONE
Permit Ready to Issue  10/23/2003 DONE
Inspection Record Card- Bld  9/4/2003 DONE
Telephone call  9/4/2003 DONE
left mess that permit is ready
Routing - PLAN CHECK8/27/2003 9/3/2003 DONE
Plan Review Report  9/3/2003  
PLANS/APPL TAKEN TO FRONT DESK  9/3/2003 DONE
Plan assigned to (SAM)8/19/2003 9/3/2003 PASS
DetailsSteve Munroe
9/3/2003 11:37:48 SAM - activity updated through activity BLDA022 from case BLD03-01973.
Plan Reviewer's activity  8/29/2003 PEND
8/29/03 10:10 I called and talked to Nathan Goff. I let him know that I need details showing one hour seperation / construction. He will fax me over sheets. Plans on hold till I receive them.
Routing - PLANNING8/20/2003 8/26/2003 PASS
All easements must be disclosed on site plan. AKT
Routing - PLAN CHECK8/15/2003 8/20/2003 FAIL
Sent to P & Z for parking issues. Need resubmittals if Planning passes.
Pending Assignment by DJO8/14/2003 8/19/2003 DONE
DetailsDan Overy
8/19/2003 11:04:58 SAM - activity updated through activity BLDA183 from case BLD03-01973.
Routing - PLANNING8/14/2003 8/15/2003 FAIL
Parking must be accomodated within blg. envelope.--no pking. provided
Routing - PUBLIC WORKS8/14/2003 8/15/2003 PASS
CREDIT GIVEN FOR EXISTING SFD
Routing - PLANNING Land Div8/14/2003 8/14/2003 PASS
Approved. Lot 5 of Hays Subdivision.
Application received  8/14/2003