PubWorks Occupancy Approval | 2/3/2005 | 2/3/2005 | 2/3/2005 | | DONE |
|
|
|
Project found complete 2/3/05 R.Rokovitz
|
(F) Reprint permit | | | 6/9/2004 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/13/2004 | 1/13/2004 | 1/13/2004 | | DONE |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 1/13/2004 | 1/13/2004 | 1/13/2004 | P | PASS |
Dave Hannah
|
|
|
Expired by inspector at 1/13/2004 1:02:37 PM
|
Issue PAID IN FULL permit | | | 10/14/2003 | | DONE |
|
|
|
|
Plan assigned to (KMM) | 10/3/2003 | | 10/13/2003 | | PASS |
Kathy Miller
|
|
|
10/13/2003 11:28:32 KMM - activity updated through activity BLDA022 from case BLD03-02016.
|
Routing - PUBLIC WORKS | 10/13/2003 | | 10/13/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/13/2003 | | 10/13/2003 | | DONE |
|
|
|
|
Routing - PLANNING | 10/13/2003 | | 10/13/2003 | | PASS |
|
|
|
Sidewalks widened to 6-feet, planter to 8-feet, bike rack shown, setback met with change of parking spaces to compact dimensions. Landscaping approved by Brian Jorgenson, Boise Forestry.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/13/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLAN CHECK | 10/10/2003 | | 10/13/2003 | | |
|
|
|
|
Routing - FIRE | 10/7/2003 | | 10/10/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/9/2003 | | DONE |
|
|
|
Received two copies of revised sheets A1, L1, T1.0, C1.0, C2.0, C3.0, C4.0, C5.;0, C6.0, C7.0. Put with plans. kmm
|
Routing - PLANNING | 10/7/2003 | | 10/7/2003 | | FAIL |
|
|
|
Sidewalk on east side of bldg to be 6-ft wide. WIll need site plan to match civil (2 copies of each)- both to be stamped and signed. Forestry approval is still outstanding. Applicant to work with Forestry.
|
Routing - PUBLIC WORKS | 10/2/2003 | | 10/7/2003 | | FAIL |
|
|
|
Requires three copies of street light plan. Per Bill colson
|
Routing - PLANNING | 8/28/2003 | | 9/11/2003 | | FAIL |
|
|
|
Waiting for Accorde to access approval letter and site plan. Acorde accessible 9-11-03. Site plan has not been modified to comply with CUP99-123 approval. Fax sent 9-12-03.
|
Routing - Erosion and Sediment | 8/27/2003 | | 8/28/2003 | | DONE |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 8/20/2003 | | 8/27/2003 | | FAIL |
|
|
|
Requires drainage plan revision per Brian M. kmm
|
Routing - PLANNING Land Div | 8/19/2003 | | 8/20/2003 | | DONE |
|
|
|
Approved. Consolidated under one tax parcel #.
|
Application received | | | 8/19/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/19/2003 | | DONE |
|
|
|
1. Need ESC permit application.
2. Need (2) ESC narratives.
3. Need applicants signature on "Involved parties" sheet.
4. Need Owners signature on "Design Professional" sheet.
5. Does not need Design Review per Marty Santoyo.
Called and left message for Chad Jones/B&A Engineers of document requirements. Faxed "Design Profession" and "Involved Parties" sheet to Chad Jones for signatures.
8/20/03 Received 1. Signed design professional sheet.
2. Signed involved parties sheet.
3. ESC application.
|