BLD-Conference | 6/1/2004 | 6/1/2004 | 6/1/2004 | P | PASS |
Tom Arcoraci
|
|
|
Les -- please call. thanks.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Energy code compliance | 6/1/2004 | 6/1/2004 | 6/1/2004 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/24/2004 | 5/24/2004 | 5/24/2004 | P | PASS |
Jim Sly
|
|
|
Les; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes 5/24/2004 2:03:09 PM Frame OK.....OK to insulate. 5/24/2004 4:27:32 PM
|
BLD-Conference | 3/5/2004 | 3/5/2004 | 3/5/2004 | P | PASS |
Jim Sly
|
|
|
###-#### les
|
BLD-Conference | 11/19/2003 | 11/19/2003 | 11/19/2003 | P | PASS |
Jim Sly
|
|
|
les; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Went through plans with owner. 11/19/2003 3:26:29 PM
|
BLD-Foundation | 10/31/2003 | 10/31/2003 | 10/31/2003 | P | PASS |
Jim Sly
|
|
|
LES; Phone #: ###-#### Internet Inspection Request from: Annette Moore Ustick...W of Maple gr....S. on Kim...... Letter from MTI for compaction test on fill.....OK. 10/31/2003 4:02:03 PM
|
BLD-Foundation | 10/29/2003 | 10/29/2003 | 10/29/2003 | P | FAIL |
Russ Owen
|
|
|
les; Phone #: ###-#### Internet Inspection Request from: Annette Moore Posted c/n for compaction etc as prior reqested10/28/2003 11:17:06 PM 10/28/2003 11:17:18 PM
|
BLD-Footing | 10/21/2003 | 10/22/2003 | 10/22/2003 | A | PART |
Jim Sly
|
|
|
ft insp les-- ###-#### setbacks appear OK....Not 24" frost....but owner says he will backfill to comply.....Had wrong letter for soil report.....Need at wall insp. Advised owner. 10/22/2003 8:33:22 AM 10/22/2003 8:33:56 AM
|
BLD-Conference | 10/8/2003 | 10/8/2003 | 10/8/2003 | P | DONE |
Jim Sly
|
|
|
LES ###-#### OR ###-#### Maple GR.... W cory (by Northview)...R Kimball. 1/4 blk on R. 10/8/2003 1:06:29 PM
|
(F) Reprint permit | | | 9/23/2003 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/22/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/22/2003 | | |
|
|
|
|
Telephone call | | | 9/22/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 9/22/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 9/3/2003 | | 9/22/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 9/5/2003 | | 9/22/2003 | | PASS |
Steve Munroe
|
|
|
9/22/2003 09:57:23 SAM - activity updated through activity BLDA022 from case BLD03-02031.
|
Case Summary (BLD) | | | 9/5/2003 | | |
|
|
|
|
Plan Review Report | | | 9/5/2003 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/5/2003 | | DONE |
|
|
|
9/5/03 11:45 I called and talked to the builder. I let him know that I have the plan review done and will issue the permit after the demo permit is pulled.
|
Pending Assignment by DJO | 8/20/2003 | | 9/5/2003 | | DONE |
Dan Overy
|
|
|
9/5/2003 07:35:27 SAM - activity updated through activity BLDA183 from case BLD03-02031.
|
Routing - PLANNING | 9/2/2003 | | 9/2/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/2/2003 | | 9/2/2003 | | PASS |
|
|
|
EXISTING HOUSE TO BE DEMOLISHED PRIOR TO CONSTRUCTION OF NEW SFD PER LES HAZEN, ###-####; ###-####: IF EXISTING SFD NOT DEM0LISHED THEY WILL OWE ADDITIONAL FEES, LW
|
Routing - PLANNING Land Div | 8/21/2003 | | 8/21/2003 | | PASS |
|
|
|
Approved, site is Lot 16 of Block 3 of Home Acres 18.
|
Routing - PLANNING | 8/20/2003 | | 8/21/2003 | | FAIL |
|
|
|
Called Les 8/21: Need updated/complete site plan--impermeable surfaces, scaled, scale notated, etc. AKT
|
Application received | | | 8/20/2003 | | |
|
|
|
|