PostCard Mailed | | | 8/4/2004 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
(F) Reprint permit | | | 3/11/2004 | | DONE |
|
|
|
|
BLD-Final | 1/27/2004 | 1/28/2004 | 1/28/2004 | P | PASS |
Tom Arcoraci
|
|
|
Bob; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes per plan lc issued 1/28/2004 2:49:28 PM
|
BLD-Energy code compliance | 12/15/2003 | 12/17/2003 | 12/17/2003 | A | PASS |
Tom Arcoraci
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 12/14/2003 | 12/15/2003 | 12/15/2003 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/14/2003 at 12:51:58 PM. Contact: ###-####. no plans on site no insp made 12/15/2003 9:10:07 AM
|
BLD-Framing/Rough-in | 12/15/2003 | 12/15/2003 | 12/15/2003 | P | PASS |
Tom Arcoraci
|
|
|
Bob; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Foundation | 11/24/2003 | 11/24/2003 | 11/24/2003 | P | NR |
Tom Arcoraci
|
|
|
Bob --- sheer; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok to side per policy dated 7-03 11/24/2003 2:47:26 PM
|
BLD-Foundation | 10/15/2003 | 10/15/2003 | 10/15/2003 | P | PART |
Tom Arcoraci
|
|
|
Jack; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip ok 10/15/2003 2:09:51 PM
|
BLD-Foundation | 10/14/2003 | 10/14/2003 | 10/14/2003 | P | PART |
Tom Arcoraci
|
|
|
jack; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip ok 10/14/2003 1:47:02 PM
|
Issue PAID IN FULL permit | | | 9/24/2003 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 9/11/2003 | 9/11/2003 | 9/12/2003 | | PASS |
Dan Overy
|
|
|
9/12/2003 09:56:01 DJO - activity updated through activity BLDA022 from case BLD03-02032.
|
Plan Reviewer's activity | | | 9/12/2003 | | DONE |
|
|
|
red-lined plans to indicate additional bearing. re-calculated res-check.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/12/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/12/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/12/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Case Summary (BLD) | | | 9/11/2003 | | |
|
|
|
|
Plan Review Report | | | 9/11/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 9/11/2003 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/11/2003 | | |
|
|
|
need to verify brg. before issuing.
|
Plan Reviewer's activity | | | 8/29/2003 | | PEND |
|
|
|
plans routed to zoning. parking indicated in setbacks. designer also required to modify plans or provide engineering for lateral design.
|
Routing - PLANNING | 8/21/2003 | | 8/22/2003 | | PASS |
|
|
|
Need 20' deep garage. Attempted to call but "memory full" continues on ans.machine. Will call for 2 revised sets + 3 site plans 8/25/2003. AKT; Builder revised floor and site plans to provide approved garage depth of 20'. PMC
|
Routing - PUBLIC WORKS | 8/21/2003 | | 8/21/2003 | | PASS |
|
|
|
BENCH SEWER DISTRICT
|
Routing - PLANNING Land Div | 8/20/2003 | | 8/21/2003 | | PASS |
|
|
|
Approved. Parcel is two lots that have been combined into one tax parcel #.
|
Application received | | | 8/20/2003 | | |
|
|
|
|
Pending Assignment by DJO | 8/20/2003 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 8/21/2003 | | | | |
|
|
|
|