Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD03-02057
StatusFinaled
Name GORDON MCDONALD
Site Address 2895 S FEDERAL WAY
Project NameStone Mountain Flooring
Customer Number 
ePlanReviewNo
Description
Stone Mountain Flooring - (Shell) To construct a new 35,675 square foot, two story, concrete tilt-up shell building and related site improvements. This is a shell building permit only. No occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. DRH03-00073/PC#514-03/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD4/26/20054/26/20054/26/2005 DONE
First Notice has not been responded to.
First Notice Sent 11/2/20044/26/2005 DONE
Letter of compliance  11/18/2004 DONE
Letter of Compliance issued 11-18-04.
DOC - Permit Finaled11/2/200411/2/200411/2/2004APASS
DetailsJim Storey
Finaled by inspector at 11/2/2004 8:24:10 AM
BLD-Aging Inspection11/2/200411/2/200411/2/2004 PASS
DetailsJim Storey
final ok 11/2/2004 8:23:47 AM
BLD-Final8/30/20048/31/20048/31/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/30/2004 at 10:08:18 AM. Contact: ###-####. final letter from engineer to justify si to be recieved at racking permit c/n insp. 8/31/2004 3:07:08 PM
FIRE-Final Inspection8/30/20048/30/20048/30/2004PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 8/30/2004 at 10:07:48 AM. Contact: ###-####.
BLD-Final8/30/20048/30/20048/30/2004PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/30/2004 at 10:08:18 AM. Contact: ###-####.
FIRE-Final Inspection8/27/20048/27/20048/27/2004PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 8/27/2004 at 8:30:47 AM. Contact: ###-####. See fire alarm permit 8/27/2004 4:16:25 PM
BLD-Final8/27/20048/27/20048/27/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/27/2004 at 8:31:35 AM. Contact: ###-####. need si final doc. 8/27/2004 3:33:29 PM
Code Occupancy Approval8/25/20048/25/20048/25/2004PPASS
DetailsWm. Michael Meloy
Compliance met. 8/25/2004 4:20:19 PM
BLD-Aging Inspection7/29/20047/29/20047/29/2004 NR
DetailsJim Storey
wip 7/29/2004 8:27:53 AM
Override - Parcel Holds1/1/19001/1/19006/15/2004  
bld isn
FIRE-Conference5/26/20045/27/20045/27/2004PDONE
DetailsTroy Cobbley
pat; Phone #: ###-#### I spoke with pat about the exhuast duct and fire/smoke damper from the elevator equipment room to the exterior wall. He wants to have it exhaust to the roof. I spoke with the plan reviewer who said if they want to change things the contractor will need to resubmit 5/27/2004 11:56:08 AM
BLD-Framing/Rough-in5/26/20045/27/20045/27/2004PPASS
DetailsJim Storey
###-#### pat ok pending ele to complet 5/27/2004 3:30:22 PM
Override - Parcel Holds1/1/19001/1/19005/26/2004  
BLD-Conference5/18/20045/19/20045/19/2004APART
DetailsJim Storey
pat; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip ok to one side gyp/ 5/19/2004 2:55:50 PM
BLD-Concrete3/24/20043/26/20043/26/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/24/2004 at 3:25:50 PM. Contact: ###-####. pending report bar appears ok. 3/26/2004 3:50:07 PM
BLD-Concrete3/1/20043/2/20043/2/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/1/2004 at 2:12:42 PM. Contact: ###-####. tilt slab walls pending report 3/2/2004 2:16:39 PM
BLD-Concrete2/25/20042/26/20042/26/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/25/2004 at 12:23:20 PM. Contact: ###-####. tilt slab wall pour placed w/sp pending report. 2/26/2004 2:02:32 PM
BLD-Aging Inspection2/23/20042/23/20042/23/2004 NR
DetailsJim Storey
wip 2/23/2004 11:05:59 AM
BLD-Concrete2/23/20042/23/20042/23/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/23/2004 at 11:10:55 AM. Contact: ###-####. wall panels reviewed with special insp. on site ok per plan pending report. 2/23/2004 2:41:37 PM
BLD-Footing12/19/200312/23/200312/23/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/19/2003 at 11:26:34 AM. Contact: ###-####.
(F) Reprint permit  11/21/2003  
Permit Ready to Issue  11/18/2003 DONE
Telephone call  11/18/2003 DONE
Spoke with Sandy told permit ready & fees
Issue PAID IN FULL permit  11/18/2003 DONE
Inspection Record Card- Bld  11/17/2003 DONE
Routing - FIRE11/7/2003 11/14/2003 PASS
Resubmittal acceptable
Routing - PLAN CHECK11/14/2003 11/14/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/14/2003 PASS
Plan assigned to (JCM)8/26/2003 11/14/2003 PASS
DetailsJohn Menard
11/14/2003 15:10:53 JCM - activity updated through activity BLDA022 from case BLD03-02057.
Routing - PLAN CHECK11/6/2003 11/7/2003 PASS
Plan Reviewer's activity  11/7/2003 PASS
Reviewed and approved resubmittals, including energy. JCM
Routing - PLANNING11/3/2003 11/5/2003 PASS
Approved per DRH03-73. The applicant is required to mark all compact parking stalls. The applicant placed a landscape planter in place of the cross access agreement.
Plan resubmittals received  11/5/2003 DONE
Received response letter, letter from Shilo Automatic Sprinkler, four sets of sheets A2.1,A2.2, taken to John M.
Plan resubmittals requested  10/31/2003  
Faxed the architect requesting additional resubmittals. JCM
Routing - PLAN CHECK9/23/2003 10/31/2003 FAIL
Plan resubmittals received  10/29/2003 DONE
Received response letter with four sheets of E0.0. Received response letter with four sets of sheets EN1.0,A2.1,A2.2,A4.2,A4.3,A5.1,A7.1,A9.1, Received response letter with four copies of sheets of C1,C2,C3,C4,A1.1,L1.1, taken to John M.
Plan resubmittals received  9/23/2003 DONE
Received two copies of revised sheet C2. Routed to John M. kmm
Routing - FIRE9/15/2003 9/23/2003 FAIL
Inadequate high piled storage information and failed grading permit BLD03-2015. Called architect 9/22/03 to discuss; left message to return call. 9/23/03 Review comments faxed to architect.
Plan Review Completed(1st rev)  9/23/2003 FAIL
Failed Building, Fire, Energy, Structural & Planning
Routing Off Site -Energy8/26/2003 9/18/2003 FAIL
Contacted PDQ to take plans to Eric Makela. Received an e-mailed comment list requesting revisions. JCM
Plan resubmittals requested  9/18/2003  
Faxed the architect a copy of the energy review requesting revisions. JCM
Routing Off Site - STRUCTURAL9/10/2003 9/17/2003 PASS
Contacted PDQ to take plan resubmittals of 9/9/03 to outside engineering. kmm Received a fax from the consulting structural engineer indicating that the resubmittals had been approved. JCM
Plan resubmittals requested  9/15/2003  
Mailed the architect a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK9/4/2003 9/15/2003 FAIL
Plan resubmittals received  9/9/2003 DONE
three copies of response to Structural plan review comments with three sets of S1.3, S2.1, S2.2 taken to John M.
Plan resubmittals requested  9/5/2003  
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL8/26/2003 9/5/2003 FAIL
contacted PDQ to take plans to outside engineering. kmm Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
Routing - PLANNING8/28/2003 9/4/2003 FAIL
Missing the cross access egress easement. Called Gordon McDonald 9/2/03.
Routing - PLUMBING9/4/2003 9/4/2003 PASS
Routing - Erosion and Sediment8/27/2003 8/28/2003 PASS
ESC approved with conditons attached to plans.
Routing - PUBLIC WORKS8/26/2003 8/27/2003 PASS
Routing - PLANNING Land Div8/26/2003 8/26/2003 PASS
Approved. Parcel was approved as Parcel on ROS 4004.
Plans ACCEPTED BY PLAN TECH  8/26/2003 DONE
Pending Assignment by JCM8/26/2003 8/26/2003 DONE
DetailsJohn Menard
8/26/2003 11:14:02 JCM - activity updated through activity BLDA166 from case BLD03-02057.
Plan routing begun/NEW & ADDTN  8/26/2003 DONE
Application received  8/25/2003  
Recd Pcfee & Taken To Pln CK  8/25/2003  
Fee Review-notes8/25/20038/25/2003