Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice Sent | | 11/2/2004 | 4/26/2005 | | DONE |
|
|
|
|
Letter of compliance | | | 11/18/2004 | | DONE |
|
|
|
Letter of Compliance issued 11-18-04.
|
DOC - Permit Finaled | 11/2/2004 | 11/2/2004 | 11/2/2004 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 11/2/2004 8:24:10 AM
|
BLD-Aging Inspection | 11/2/2004 | 11/2/2004 | 11/2/2004 | | PASS |
Jim Storey
|
|
|
final ok 11/2/2004 8:23:47 AM
|
BLD-Final | 8/30/2004 | 8/31/2004 | 8/31/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 10:08:18 AM. Contact: ###-####. final letter from engineer to justify si to be recieved at racking permit c/n insp. 8/31/2004 3:07:08 PM
|
FIRE-Final Inspection | 8/30/2004 | 8/30/2004 | 8/30/2004 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 10:07:48 AM. Contact: ###-####.
|
BLD-Final | 8/30/2004 | 8/30/2004 | 8/30/2004 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 10:08:18 AM. Contact: ###-####.
|
FIRE-Final Inspection | 8/27/2004 | 8/27/2004 | 8/27/2004 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 8/27/2004 at 8:30:47 AM. Contact: ###-####. See fire alarm permit 8/27/2004 4:16:25 PM
|
BLD-Final | 8/27/2004 | 8/27/2004 | 8/27/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/27/2004 at 8:31:35 AM. Contact: ###-####. need si final doc. 8/27/2004 3:33:29 PM
|
Code Occupancy Approval | 8/25/2004 | 8/25/2004 | 8/25/2004 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 8/25/2004 4:20:19 PM
|
BLD-Aging Inspection | 7/29/2004 | 7/29/2004 | 7/29/2004 | | NR |
Jim Storey
|
|
|
wip 7/29/2004 8:27:53 AM
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 6/15/2004 | | |
|
|
|
bld isn
|
FIRE-Conference | 5/26/2004 | 5/27/2004 | 5/27/2004 | P | DONE |
Troy Cobbley
|
|
|
pat; Phone #: ###-#### I spoke with pat about the exhuast duct and fire/smoke damper from the elevator equipment room to the exterior wall. He wants to have it exhaust to the roof. I spoke with the plan reviewer who said if they want to change things the contractor will need to resubmit 5/27/2004 11:56:08 AM
|
BLD-Framing/Rough-in | 5/26/2004 | 5/27/2004 | 5/27/2004 | P | PASS |
Jim Storey
|
|
|
###-#### pat ok pending ele to complet 5/27/2004 3:30:22 PM
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 5/26/2004 | | |
|
|
|
|
BLD-Conference | 5/18/2004 | 5/19/2004 | 5/19/2004 | A | PART |
Jim Storey
|
|
|
pat; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip ok to one side gyp/ 5/19/2004 2:55:50 PM
|
BLD-Concrete | 3/24/2004 | 3/26/2004 | 3/26/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/24/2004 at 3:25:50 PM. Contact: ###-####. pending report bar appears ok. 3/26/2004 3:50:07 PM
|
BLD-Concrete | 3/1/2004 | 3/2/2004 | 3/2/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/1/2004 at 2:12:42 PM. Contact: ###-####. tilt slab walls pending report 3/2/2004 2:16:39 PM
|
BLD-Concrete | 2/25/2004 | 2/26/2004 | 2/26/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/25/2004 at 12:23:20 PM. Contact: ###-####. tilt slab wall pour placed w/sp pending report. 2/26/2004 2:02:32 PM
|
BLD-Aging Inspection | 2/23/2004 | 2/23/2004 | 2/23/2004 | | NR |
Jim Storey
|
|
|
wip 2/23/2004 11:05:59 AM
|
BLD-Concrete | 2/23/2004 | 2/23/2004 | 2/23/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/23/2004 at 11:10:55 AM. Contact: ###-####. wall panels reviewed with special insp. on site ok per plan pending report. 2/23/2004 2:41:37 PM
|
BLD-Footing | 12/19/2003 | 12/23/2003 | 12/23/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/19/2003 at 11:26:34 AM. Contact: ###-####.
|
(F) Reprint permit | | | 11/21/2003 | | |
|
|
|
|
Permit Ready to Issue | | | 11/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 11/18/2003 | | DONE |
|
|
|
Spoke with Sandy told permit ready & fees
|
Issue PAID IN FULL permit | | | 11/18/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2003 | | DONE |
|
|
|
|
Routing - FIRE | 11/7/2003 | | 11/14/2003 | | PASS |
|
|
|
Resubmittal acceptable
|
Routing - PLAN CHECK | 11/14/2003 | | 11/14/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2003 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 8/26/2003 | | 11/14/2003 | | PASS |
John Menard
|
|
|
11/14/2003 15:10:53 JCM - activity updated through activity BLDA022 from case BLD03-02057.
|
Routing - PLAN CHECK | 11/6/2003 | | 11/7/2003 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 11/7/2003 | | PASS |
|
|
|
Reviewed and approved resubmittals, including energy. JCM
|
Routing - PLANNING | 11/3/2003 | | 11/5/2003 | | PASS |
|
|
|
Approved per DRH03-73. The applicant is required to mark all compact parking stalls. The applicant placed a landscape planter in place of the cross access agreement.
|
Plan resubmittals received | | | 11/5/2003 | | DONE |
|
|
|
Received response letter, letter from Shilo Automatic Sprinkler, four sets of sheets A2.1,A2.2, taken to John M.
|
Plan resubmittals requested | | | 10/31/2003 | | |
|
|
|
Faxed the architect requesting additional resubmittals. JCM
|
Routing - PLAN CHECK | 9/23/2003 | | 10/31/2003 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 10/29/2003 | | DONE |
|
|
|
Received response letter with four sheets of E0.0. Received response letter with four sets of sheets EN1.0,A2.1,A2.2,A4.2,A4.3,A5.1,A7.1,A9.1, Received response letter with four copies of sheets of C1,C2,C3,C4,A1.1,L1.1, taken to John M.
|
Plan resubmittals received | | | 9/23/2003 | | DONE |
|
|
|
Received two copies of revised sheet C2. Routed to John M. kmm
|
Routing - FIRE | 9/15/2003 | | 9/23/2003 | | FAIL |
|
|
|
Inadequate high piled storage information and failed grading permit BLD03-2015. Called architect 9/22/03 to discuss; left message to return call. 9/23/03 Review comments faxed to architect.
|
Plan Review Completed(1st rev) | | | 9/23/2003 | | FAIL |
|
|
|
Failed Building, Fire, Energy, Structural & Planning
|
Routing Off Site -Energy | 8/26/2003 | | 9/18/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to Eric Makela. Received an e-mailed comment list requesting revisions. JCM
|
Plan resubmittals requested | | | 9/18/2003 | | |
|
|
|
Faxed the architect a copy of the energy review requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/10/2003 | | 9/17/2003 | | PASS |
|
|
|
Contacted PDQ to take plan resubmittals of 9/9/03 to outside engineering. kmm Received a fax from the consulting structural engineer indicating that the resubmittals had been approved. JCM
|
Plan resubmittals requested | | | 9/15/2003 | | |
|
|
|
Mailed the architect a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 9/4/2003 | | 9/15/2003 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 9/9/2003 | | DONE |
|
|
|
three copies of response to Structural plan review comments with three sets of S1.3, S2.1, S2.2 taken to John M.
|
Plan resubmittals requested | | | 9/5/2003 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 8/26/2003 | | 9/5/2003 | | FAIL |
|
|
|
contacted PDQ to take plans to outside engineering. kmm Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING | 8/28/2003 | | 9/4/2003 | | FAIL |
|
|
|
Missing the cross access egress easement. Called Gordon McDonald 9/2/03.
|
Routing - PLUMBING | 9/4/2003 | | 9/4/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/27/2003 | | 8/28/2003 | | PASS |
|
|
|
ESC approved with conditons attached to plans.
|
Routing - PUBLIC WORKS | 8/26/2003 | | 8/27/2003 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 8/26/2003 | | 8/26/2003 | | PASS |
|
|
|
Approved. Parcel was approved as Parcel on ROS 4004.
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/2003 | | DONE |
|
|
|
|
Pending Assignment by JCM | 8/26/2003 | | 8/26/2003 | | DONE |
John Menard
|
|
|
8/26/2003 11:14:02 JCM - activity updated through activity BLDA166 from case BLD03-02057.
|
Plan routing begun/NEW & ADDTN | | | 8/26/2003 | | DONE |
|
|
|
|
Application received | | | 8/25/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2003 | | |
|
|
|
|
Fee Review-notes | 8/25/2003 | 8/25/2003 | | | |
|
|
|
|