First Notice | | 1/28/2004 | 1/28/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/28/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 9949 issued 1-28-04 to Payless Shoe Source.
|
Permanent Occupancy | | 1/27/2004 | 1/27/2004 | | DONE |
|
|
|
|
BLD-Final | 1/26/2004 | 1/27/2004 | 1/27/2004 | A | PASS |
Russ Owen
|
|
|
Herb, ###-#### Ok perm oc, schell and core finaled. 1/27/2004 11:13:04 AM
|
(F) Reprint permit | | | 12/19/2003 | | DONE |
|
|
|
|
BLD-Final | 12/10/2003 | 12/11/2003 | 12/11/2003 | A | PART |
Russ Owen
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok temp pending schell approval for a final. perm. 12/11/2003 11:45:58 AM 12/11/2003 11:46:20 AM
|
Temporary occupancy | | | 12/11/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #5038 issued 12-11-03 to Payless Shoe Source.
|
FIRE-Final Inspection | 12/9/2003 | 12/10/2003 | 12/10/2003 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled and fire sprinklers finaled 12/10/2003 3:16:45 PM
|
BLD-Framing/Rough-in | 12/3/2003 | 12/3/2003 | 12/3/2003 | P | PASS |
Russ Owen
|
|
|
Mike -- accoustical ceiling.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Conference | 11/21/2003 | 11/24/2003 | 11/24/2003 | P | NH |
Jim Storey
|
|
|
###-#### Mike
|
(F) Reprint permit | | | 11/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/7/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/7/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/3/2003 | | |
|
|
|
|
Print Occupancy Form | | | 9/30/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/30/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/30/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLAN CHECK | 9/29/2003 | | 9/29/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2003 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 9/5/2003 | | 9/29/2003 | | PASS |
|
|
|
9/29/2003 15:06:02 RMH - activity updated through activity BLDA022 from case BLD03-02139.
|
Routing - FIRE | 9/22/2003 | | 9/29/2003 | | PASS |
|
|
|
Review comments faxed to out of state architect.
|
Case Summary (BLD) | | | 9/22/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/9/2003 | | 9/22/2003 | | PEND |
|
|
|
Permit pending fire departments review and approval, NO corrections required by building code review Routed plans to the fire department on 9/22/03.
|
Routing - PUBLIC WORKS | 9/5/2003 | | 9/9/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/5/2003 | | DONE |
|
|
|
|
Application received | | | 9/4/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/4/2003 | | |
|
|
|
|
Fee Review-notes | 9/4/2003 | 9/4/2003 | | | |
|
|
|
|