Permit Information
Permit NumberBLD03-02191
StatusFinaled
Name BOWN CROSSING MARKET PLACE BLDG C
Site Address 3082 S BOWN WAY
Project NameBown Crossing Market Place
Customer Number 
ePlanReviewNo
Description
(Bown Crossing Market Place-Bldg C) To construct a new 5,550 s.f. two story, multi-tenant, shell only building. The first floor is 2,878 s.f. and the second floor is 2,672 s.f. NOTE: This building is fully fire sprinklered for Code reduction and fire flow. Separate permits, plans and Certificate of Occupancies must be obtained and approved for each tenant space to be occupied. Alll construction per the approved plans and attached comment list. PC#549-03 DRH03-00034
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 9/19/20059/19/2005 DONE
Second Notice 9/19/20059/19/2005 DONE
Third Notice 9/19/20059/19/2005 DONE
Letter of compliance  1/28/2005 DONE
Letter of Compliance issued 1-28-05.
PubWorks Occupancy Approval1/26/20051/26/20051/26/2005 DONE
Drainage final approval by B.Murphy 1/26/05
Code Occupancy Approval  1/25/2005 PASS
Compliance met.
BLD-Final12/13/200412/13/200412/13/2004PPART
DetailsJim Storey
Nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice final pending achd/pw/p&z/si final si 12/13/2004 3:43:58 PM
FIRE-Final Inspection12/10/200412/10/200412/10/2004APASS
DetailsRick Jackson
Final okay 12/10/2004 9:03:19 AM
BLD-Final12/8/200412/9/200412/9/2004ANR
DetailsJim Storey
nick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Aging Inspection11/3/200411/3/200411/3/2004 NR
DetailsJim Storey
BLD-Other9/2/20049/3/20049/3/2004ANR
DetailsDave Hannah
stairway fire inspection//nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Other8/30/20048/31/20048/31/2004APART
DetailsDave Hannah
nick; Phone #: ###-#### Internet Inspection Request from: Annette Moorec 8/31/2004 10:24:27 AM ok to use sheet rock behind columns st sec floor needs to make sure rockwool is secured under foor also inslation in walls at floor in nat per plans 8/31/2004 10:27:29 AM
BLD-Aging Inspection7/12/20047/12/20047/12/2004 PASS
DetailsJim Storey
wip 7/12/2004 8:06:08 AM
BLD-Aging Inspection5/10/20045/10/20045/10/2004 PASS
DetailsJim Storey
wip 5/10/2004 8:12:59 AM
BLD-Foundation3/8/20043/9/20043/9/2004PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/8/2004 at 9:48:03 AM. Contact: ###-####. form alinement in progess/ rebar ok pending special insp. reports. 3/9/2004 2:20:52 PM
BLD-Footing3/3/20043/3/20043/3/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/3/2004 at 8:54:50 AM. Contact: ###-####. placed with special insp. pending report. 3/3/2004 3:05:08 PM
Plan resubmittals received  2/24/2004 DONE
Received three requested changes to the Bown shell and core projects. Routed to Mike P. kmm
Plan resubmittals received  12/30/2003 DONE
Received two additional copies of revised sheets C2, A1.11, A2.12, A5.00 A5.11, S2.12, S3.12, S4.11, S5.12, S6.12, S7.11 M1.02. One copy of cover letter. Routed to Marlene. kmm
(F) Reprint permit  12/9/2003  
Inspection Record Card- Bld  12/8/2003 DONE
Telephone call  12/8/2003 DONE
left mess that permit is ready
Permit Ready to Issue  12/8/2003 DONE
Issue PAID IN FULL permit  12/8/2003 DONE
Routing - PLAN CHECK12/2/2003 12/5/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/5/2003 DONE
Plan assigned to (M_P)9/15/2003 12/5/2003 PASS
DetailsMike Phillips
12/5/2003 14:44:15 M_P - activity updated through activity BLDA022 from case BLD03-02191.
Plan resubmittals received  12/2/2003 DONE
Received two copies of revised ESC plans and narrative. Routed to Mike P. kmm
Routing - Erosion and Sediment12/2/2003 12/2/2003 PASS
Routing - PLANNING Land Div11/26/2003 11/26/2003 PASS
Riverwalk Subdivision No. 1 recorded 11-25-03. Lot 6 of Block 2.
Routing - Erosion and Sediment11/26/2003 11/26/2003 FAIL
See comments on ESC permit.
Routing - PLANNING11/26/2003 11/26/2003 PASS
Routing - FIRE11/21/2003 11/25/2003 PASS
resubmittal acceptable.
Routing - PUBLIC WORKS11/14/2003 11/21/2003 PASS
Plan resubmittals received  11/18/2003 DONE
Received one transmittals with one plan review response letters,1 letters to Marty regarding landscape, Guide specifications, four structural calcs. two sets of sheets A1.11, 4 sets of sheets C2,A2.12,A3.12,A4.12,,A5.00,A5.11,A6.12,S1.11,S2.12,S3.12,S4.11,S5.11,S5.12,S6.12,S7.11,M1.02,M1.02,E2.21
Plan resubmittals received  11/17/2003 DONE
Received two copies of revised sheets a1.11, one copy of plan review response letter, one copy of fire flow package from United Water, one copy of letter from Dave Miller. Routed to Mike P. kmm
Plan resubmittals received  11/17/2003 DONE
Received two copies of ESC control report. Routed to Mike P.
Plan resubmittals received  11/14/2003 DONE
Received transmittal letter from Toothman orton engineering & ESC narrative. Taken to Mike P.
Routing - FIRE11/5/2003 11/13/2003 FAIL
Fire hydrant and sprinkler flow required. Review faxed to architect.
Routing Off Site -Energy9/15/2003 11/5/2003 FAIL
Contacted Ron O. for energy review.
Routing - PLAN CHECK10/2/2003 11/5/2003 FAIL
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
Routing - PLUMBING9/26/2003 10/2/2003 PASS
per plans and 2000 upc
Routing - PLANNING9/26/2003 9/26/2003 FAIL
Landscape plan does not comply with Design Review DRH03-34.
Plan resubmittals received  9/26/2003 DONE
Received transmittal sheet with Erosion & sediment control design report. taken to Mike P.
Routing - Erosion and Sediment9/23/2003 9/25/2003 FAIL
No ESC narrative attached to plans.
Routing - PUBLIC WORKS9/16/2003 9/23/2003 FAIL
Requires site plans showing meets and bounds with utilities and easements being shown and building. Per April Miller Requires O&M manual and geotech report. Per Brian Murphy. Sanitary sewer is considered public and needs to be reviewed and approved separately by PW. Per John Johnson. kmm
Plans ACCEPTED BY PLAN TECH  9/15/2003 DONE
RP out to bid. kmm
Routing - PLANNING Land Div9/15/2003 9/15/2003 FAIL
Prior to issuance of building permit, plat of Riverwalk Subdivision must be recorded.
Plan routing begun/NEW & ADDTN  9/15/2003 DONE
Application received  9/11/2003  
Recd Pcfee & Taken To Pln CK  9/11/2003  
Fee Review-notes9/11/20039/11/2003