Permit Information
Permit NumberBLD03-02195
StatusExpired
Name BEKINS MOVING & STORAGE CO
Site Address 631 S 9TH ST
Project NameIdaho Self Storage
Customer Number 
ePlanReviewNo
Description
(Idaho Self Storage)(Building C)* To install new non-bearing interior panel walls to create storage units with open ceilings within an existing warehouse. New windows and doors will be installed along with new lighting and hvac. This permit covers work on Building C only and any related site improvements as shown on the approved plans for Building C. DRH03-00009 Mod 1 Fire Sprinklers are to comply with NFPA 13 as regulated by the Fire Dept.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/2/20058/2/20058/3/2005 PASS
DetailsDave Hannah
DOC - Permit Expired8/3/20058/3/20058/3/2005PPASS
DetailsDave Hannah
BLD-Aging Inspection8/2/20048/2/20048/2/2004 PASS
DetailsDave Hannah
BLD-Aging Inspection8/2/20048/2/20048/2/2004 PASS
DetailsDave Hannah
Routing - Erosion and Sediment7/14/2004 7/14/2004 PASS
ESC plan approved with attached conditions. Misc. additional work.
BLD-Final4/29/20044/30/20044/30/2004PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/29/2004 at 10:56:04 AM. Contact: ###-####. ok for perm occ 4/30/2004 3:03:12 PM
FIRE-Final Inspection4/30/20044/30/20044/30/2004PPASS
DetailsRick Jackson
Code Occupancy Approval4/27/20044/27/20044/27/2004PPASS
DetailsWm. Michael Meloy
Compliancae met. 4/27/2004 1:33:14 PM
BLD-Conference4/14/20044/14/20044/14/2004PDONE
DetailsDave Hannah
devin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
FIRE-Conference4/14/20044/14/20044/14/2004PPART
DetailsRick Jackson
Met with GC about Knox box location and timing of moving storage from area B to area A; the sprinkler rough-in and hydro not ready on new system in area A 4/14/2004 2:23:18 PM
BLD-Wall cover2/17/20042/17/20042/17/2004PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/17/2004 at 8:17:04 AM. Contact: ###-####. ok to cover infill on ext walls and rock ceiling 2/17/2004 3:59:03 PM
Telephone call  1/29/2004 DONE
talked to robert thornton to verify plans are ready
Issue PAID IN FULL permit  1/29/2004 DONE
Inspection Record Card- Bld  1/6/2004 DONE
Print Occupancy Form  1/6/2004 DONE
Telephone call  1/6/2004 DONE
Left message with Devin -- permit is ready.
Permit Ready to Issue  1/6/2004 DONE
Routing - PLAN CHECK12/26/2003 1/5/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/5/2004 DONE
Plan assigned to (MLO)9/17/2003 1/5/2004 PASS
DetailsMike Otto
1/5/2004 14:28:09 MLO - activity updated through activity BLDA022 from case BLD03-02195.
Plan resubmittals received  12/24/2003 DONE
2 sheets of a2.12 received and forwarded to Mike Otto.
Plan resubmittals received  11/25/2003 DONE
Received transmittal letter with two sheets of A1.11 taken to Mike O.
Routing - FIRE11/20/2003 11/25/2003 PASS
Revised site plans and hydrant flow info were not included with the resubmittal package for this permit. Plans are approved subject to the same information received under bldg permit BLD03-02196 for Bldg A/B but do not issue these plans or permit until the architect brings in 2 copies of revised Sheet a1.11 and United water flow information to be attached to these two sets of plans.
Plan resubmittals received  11/20/2003 DONE
Received transmittal letter, response letter, copy of fax transmittal, two A2.12 sheets taken to Mike O.
Plan resubmittals requested  11/20/2003 DONE
details and engineering for interior wall systems
Routing - PLAN CHECK11/5/2003 11/19/2003 FAIL
corrections sent to architect
Plan resubmittals received  11/6/2003 DONE
Received transmittal letter, Response letter for plan review, Response letter to Fire, three sets of sheets A2.12,A3.12 taken to Mike Otto.
Routing - Erosion and Sediment11/4/2003 11/5/2003 PASS
Cert. RP is Devin Wiggett. kmm ESC approved with conditions attached to plans.
Routing - FIRE10/27/2003 11/3/2003 FAIL
FD access, hydrant, and sprinkler flow info required. Review to faxed to architect and attached.
Reroute to ESC after fire. kmm
Routing Off Site - STRUCTURAL9/17/2003 10/27/2003 PASS
Contacted PDQ to take to outside engineering. corrections sent to architect
Plan resubmittals requested  10/27/2003 DONE
IBC Struc and Non-struc corrections
Routing - PLAN CHECK10/14/2003 10/27/2003 FAIL
corrections sent to architect
Routing - Erosion and Sediment10/13/2003 10/14/2003 FAIL
route to erosion after planning 10/9/2003 MLO. Individual list as RP not certified by Boise City. Contacted Rob Thornton.
Routing - PLANNING10/9/2003 10/13/2003 PASS
Approved as per DRH03-9 Mod. #1 and as noted on sheet L1.1.
Routing - PLAN CHECK10/7/2003 10/9/2003 NR
Routing - PLUMBING10/6/2003 10/6/2003 PASS
fixture removal, per plans and 2000 upc.
Routing - PLANNING10/6/2003 10/6/2003 FAIL
Needs revised landscape plans inserted.
Plan resubmittals received  10/6/2003 DONE
Received two landscape plans and taken to Mike O.
Routing - Erosion and Sediment9/29/2003 10/3/2003 FAIL
Individual listed as RP is not certified by Boise City.
Routing - PUBLIC WORKS9/18/2003 9/29/2003 PASS
Pending grading and drainage (bld03-01953) approval per Brian Murphy. kmm
Routing - PLANNING Land Div9/17/2003 9/17/2003 PASS
Approved.
Plan routing begun/TENANTS  9/17/2003 DONE
Application received  9/11/2003  
Override - Parcel Holds  9/11/2003  
Recd Pcfee & Taken To Pln CK  9/11/2003 DONE
Fee Review-notes9/11/20039/11/2003