Case Summary (BLD) | | | 5/10/2016 | | DONE |
|
|
|
|
DOC-Permit Expired | 4/13/2004 | 4/13/2004 | 4/13/2004 | | DONE |
Jim Storey
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 2/12/2004 | 2/12/2004 | 2/12/2004 | | NR |
Jim Storey
|
|
|
waiting for better weather to finsh work. 2/12/2004 8:08:01 AM
|
Issue PAID IN FULL permit | | | 11/13/2003 | | |
|
|
|
|
(F) Reprint permit | | | 11/13/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/4/2003 | | 11/12/2003 | | |
|
|
|
Plans in hold box waiting for Planning approval.
|
Routing - PLANNING | 11/7/2003 | | 11/7/2003 | | PASS |
|
|
|
Approved per CZC01-54 and per letter from Rocky Towle, dated November 6, 2003 (original in file).
|
CHANGE STATUS TO (PND) | | | 11/4/2003 | | DONE |
|
|
|
Changed per Kathy Miller as she took the plans with her//11/04/03 BAM
Marty needs to sign off on plans. kmm
|
Plan assigned to (KMM) | 9/11/2003 | | 10/13/2003 | | PASS |
Kathy Miller
|
|
|
10/13/2003 11:18:49 KMM - activity updated through activity BLDA022 from case BLD03-02202.
|
Routing - PUBLIC WORKS | 10/9/2003 | | 10/13/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 10/13/2003 | | 10/13/2003 | | FAIL |
|
|
|
Need agreements from adjacent property owners to the south to utilize cross-access, as well as adding 2'0" of cross-access for the handicap parking space (total of 8 ft. for the loading aisle).
|
Routing - PLAN CHECK | 10/13/2003 | | 10/13/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/13/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/13/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLAN CHECK | 10/7/2003 | | 10/9/2003 | | |
|
|
|
Plans in hold box waiting PW and Planning approval. kmm
|
Plan resubmittals received | | | 10/9/2003 | | DONE |
|
|
|
Received two copies of revised sheet C1.1. Put with plans. kmm
|
Routing - Erosion and Sediment | 10/6/2003 | | 10/6/2003 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 10/3/2003 | | 10/6/2003 | | |
|
|
|
Plans in hold box waiting for PW, Planning and ESC approval. kmm
|
Routing - FIRE | 9/25/2003 | | 10/3/2003 | | PASS |
|
|
|
No impact on FD access.
|
Routing - Erosion and Sediment | 9/17/2003 | | 9/18/2003 | | FAIL |
|
|
|
Individual listed as RP is not certified by Boise City.
|
Routing - PUBLIC WORKS | 9/12/2003 | | 9/16/2003 | | FAIL |
|
|
|
Requires drainage plan per Brian M. kmm
|
Routing - PLANNING Land Div | 9/11/2003 | | 9/11/2003 | | PASS |
|
|
|
Approved, ROS 5299.
|
Plan routing begun/TENANTS | | | 9/11/2003 | | DONE |
|
|
|
|
Application received | | | 9/11/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2003 | | DONE |
|
|
|
|
Routing - PLANNING | 9/18/2003 | | 2/25/2003 | | FAIL |
|
|
|
Need agreements from adjacent property owners to the south to utilize cross-access, as well as adding 2'0" of paving for the handicap parking space (total of 8 ft. for the loading aisle).
|