BLD-Final | 6/8/2004 | 6/9/2004 | 6/9/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 6/8/2004 at 9:37:16 AM. Contact: ###-####.
|
DOC - Permit Finaled | 6/9/2004 | 6/9/2004 | 6/9/2004 | A | PASS |
Troy James
|
|
|
Finaled by inspector at 6/9/2004 10:41:22 AM
|
BLD-Energy code compliance | 2/12/2004 | 2/12/2004 | 2/12/2004 | A | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 2/3/2004 | 2/4/2004 | 2/4/2004 | A | PASS |
Jim Storey
|
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 2/2/2004 | 2/3/2004 | 2/3/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/2/2004 at 12:33:32 PM. Contact: ###-####. framing ok need engery sealant plk. 2/3/2004 11:24:58 AM
|
BLD-Framing/Rough-in | 1/7/2004 | 1/8/2004 | 1/8/2004 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/7/2004 at 2:36:37 PM. Contact: ###-####.
|
BLD-Foundation | 11/14/2003 | 11/18/2003 | 11/18/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 10:08:42 AM. Contact: ###-####.
|
BLD-Footing | 11/14/2003 | 11/17/2003 | 11/17/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 10:07:53 AM. Contact: ###-####.
|
BLD-Foundation | 11/12/2003 | 11/14/2003 | 11/14/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/12/2003 at 2:48:12 PM. Contact: ###-####. ft for garage and walls of dewlling ok rebar in place. 11/14/2003 10:07:56 AM
|
BLD-Footing | 11/10/2003 | 11/12/2003 | 11/12/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/10/2003 at 11:48:20 AM. Contact: ###-####. house ft ok rebar ok will phase ft on grage. setbacks ok. 11/12/2003 10:32:08 AM
|
Issue PAID IN FULL permit | | | 11/6/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 9/24/2003 | | 11/5/2003 | | PASS |
Steve Munroe
|
|
|
11/5/2003 09:51:50 SAM - activity updated through activity BLDA022 from case BLD03-02214.
|
Routing - PLANNING Land Div | 11/5/2003 | | 11/5/2003 | | PASS |
|
|
|
Approved for Lot 2, Block 1 of Barn View Subdivision. Final Plat recorded on November 3, 2003.
|
Routing - PLAN CHECK | 11/5/2003 | | 11/5/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/5/2003 | | |
|
|
|
|
Plan Review Report | | | 11/5/2003 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/5/2003 | | |
|
|
|
|
Telephone call | | | 11/5/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Inspection Record Card- Bld | | | 11/5/2003 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 9/25/2003 | | 9/29/2003 | | FAIL |
|
|
|
Do not issue building permit until Final Plat of Barn View is recorded.
|
Routing - PLAN CHECK | 9/16/2003 | | 9/25/2003 | | PEND |
|
|
|
Routed to Land Division for subdivision.
|
Pending Assignment by DJO | 9/12/2003 | | 9/24/2003 | | DONE |
Dan Overy
|
|
|
9/24/2003 11:51:54 SAM - activity updated through activity BLDA183 from case BLD03-02214.
|
Application received | | | 9/12/2003 | | |
|
|
|
|
Routing - PLANNING | 9/12/2003 | | 9/12/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2003 | | 9/12/2003 | | PASS |
|
|
|
|