First Notice | | 3/23/2004 | 3/23/2004 | | DONE |
|
|
|
|
First Notice | | 3/23/2004 | 3/23/2004 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/23/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10046 issued 3-19-04 to the Erland Medical Office.
|
Permanent Occupancy | | 3/19/2004 | 3/19/2004 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/17/2004 | 3/18/2004 | 3/18/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled. Hvac unit did not require automatic shutdown 3/18/2004 11:07:08 AM
|
BLD-Final | 3/17/2004 | 3/18/2004 | 3/18/2004 | P | PART |
Tony Young
|
|
|
BOB; Phone #: ###-#### Internet Inspection Request from: Darla Downs
perm. c of o ok after trades 3/18/2004 4:41:35 PM
|
Case Summary (BLD) | | | 2/18/2004 | | |
|
|
|
|
BLD-Framing/Rough-in | 1/16/2004 | 1/16/2004 | 1/16/2004 | P | PASS |
Tony Young
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
energy ok also 1/16/2004 4:35:43 PM
|
BLD-Framing/Rough-in | 1/14/2004 | 1/14/2004 | 1/14/2004 | P | PART |
Tony Young
|
|
|
bob ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
c/n on truss fixes 1/14/2004 4:25:00 PM
|
(F) Reprint permit | | | 11/21/2003 | | |
|
|
|
|
BLD-Foundation | 11/18/2003 | 11/19/2003 | 11/19/2003 | A | PART |
Tony Young
|
|
|
Jason; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Footing | 11/18/2003 | 11/18/2003 | 11/18/2003 | P | PART |
Tony Young
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Issue PAID IN FULL permit | | | 11/17/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/17/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/13/2003 | | |
|
|
|
|
Permit Ready to Issue | | | 11/13/2003 | | DONE |
|
|
|
|
Telephone call | | | 11/13/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 11/10/2003 | | 11/12/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2003 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 9/18/2003 | | 11/12/2003 | | PASS |
John Menard
|
|
|
11/12/2003 09:44:08 JCM - activity updated through activity BLDA022 from case BLD03-02216.
|
Routing - FIRE | 11/6/2003 | | 11/10/2003 | | PASS |
|
|
|
resubmittal acceptable
|
Routing - PLANNING | 11/3/2003 | | 11/6/2003 | | PASS |
|
|
|
Approved per DRH03-184.
|
Routing - PLAN CHECK | 11/6/2003 | | 11/6/2003 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 11/6/2003 | | PASS |
|
|
|
Plans reviewed and approved with attached comment list and redlined notes. JCM
|
Routing - PLAN CHECK | 10/27/2003 | | 11/3/2003 | | |
|
|
|
|
Plan resubmittals received | | | 11/3/2003 | | DONE |
|
|
|
Received one copy of plan review response letter, one copy of letter from Fred Ramey attorney at law, two copies of envelope compliance certificate and four copies of revised sheets 1 thru 6. Routed to John M. kmm
|
Routing - PUBLIC WORKS | 10/24/2003 | | 10/27/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 10/23/2003 | | 10/24/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 10/17/2003 | | 10/23/2003 | | FAIL |
|
|
|
Requies geotech plan per Brian Murphy. kmm
|
Routing - PLAN CHECK | 10/13/2003 | | 10/17/2003 | | |
|
|
|
|
Routing - FIRE | 10/8/2003 | | 10/13/2003 | | FAIL |
|
|
|
No fire flow info, no hydrants, no FD access shown. REview faxed to architect.
|
Plan resubmittals requested | | | 10/8/2003 | | |
|
|
|
Mailed the architect a copy of plan review report and energy report requesting revisions. JCM
|
Routing - PLAN CHECK | 10/2/2003 | | 10/8/2003 | | FAIL |
|
|
|
|
Routing - PLUMBING | 10/1/2003 | | 10/1/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 9/25/2003 | | 10/1/2003 | | FAIL |
|
|
|
Needs Design Review approval. Phone James Gipson and informed him of the status. He stated that he will contact Bob Erland.
|
Plan resubmittals received | | | 9/26/2003 | | DONE |
|
|
|
Received two copies of revised ESC plans and Narrative. Put with plans. kmm
|
Routing - Erosion and Sediment | 9/24/2003 | | 9/24/2003 | | FAIL |
|
|
|
RP listed is not certified and plan not specific to project.
|
Routing - PUBLIC WORKS | 9/19/2003 | | 9/22/2003 | | FAIL |
|
|
|
Requires drainage plan and geotech report.
|
Plan resubmittals received | | | 9/22/2003 | | DONE |
|
|
|
Received signed ESC plans. kmm
|
Plan resubmittals received | | | 9/22/2003 | | DONE |
|
|
|
Received six sheets of C1 put with plans
|
Routing - PLANNING Land Div | 9/18/2003 | | 9/19/2003 | | PASS |
|
|
|
Approved, Lot 2 of Pyrmont Subdivision.
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2003 | | DONE |
|
|
|
Have asked for two signed ESC plans. The ones submitted were not signed. Contacted Bob Erland. kmm
|
Plan routing begun/NEW & ADDTN | | | 9/18/2003 | | DONE |
|
|
|
|
Application received | | | 9/12/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/12/2003 | | |
|
|
|
|
Fee Review-notes | 9/12/2003 | 9/12/2003 | | | |
|
|
|
|
Routing Off Site -Energy | 9/18/2003 | | | | |
|
|
|
Contacted Ron O to pick up plans. kmm
|