BLD-Aging Inspection | 10/17/2005 | 10/17/2005 | 10/17/2005 | | PASS |
Jim Storey
|
|
|
|
First Notice | 10/17/2005 | 10/17/2005 | 10/17/2005 | | DONE |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 10/17/2005 | 10/17/2005 | 10/17/2005 | P | PASS |
Jim Storey
|
|
|
|
First Notice | | 9/19/2005 | 9/19/2005 | | DONE |
|
|
|
|
Second Notice | | 9/19/2005 | 9/19/2005 | | DONE |
|
|
|
|
Third Notice | | 9/19/2005 | 9/19/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/12/2005 | 8/15/2005 | 8/15/2005 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 8/11/2005 | 8/12/2005 | 8/12/2005 | A | FAIL |
Troy Cobbley
|
|
|
Need to repair the emergency lights in the stairwells and the exit discharge lighting. Provide NFPA 72 record of completion forms to the inspector as well.
|
BLD-Final | 8/11/2005 | 8/12/2005 | 8/11/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/11/2005 at 10:53:01 AM. Contact: ###-####.ceilling ok
|
FIRE-Final Inspection | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
repair emergency lights and provide the canopies for the sprinkler pendants. final fire alrm permit
|
Code Occupancy Approval | 8/10/2005 | 8/10/2005 | 8/10/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
BLD-Aging Inspection | 6/20/2005 | 6/20/2005 | 6/20/2005 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Framing/Rough-in | 4/19/2005 | 4/19/2005 | 4/19/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/19/2005 at 9:17:31 AM. Contact: ###-####.east stair framing ok.
|
BLD-Framing/Rough-in | 4/7/2005 | 4/8/2005 | 4/8/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 12:40:16 PM.
|
BLD-Framing/Rough-in | 3/22/2005 | 3/23/2005 | 3/23/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 5:00:24 PM. Contact: ###-####. p/l wall ok /insulation ok. 3/23/2005 2:59:12 PM
|
BLD-Other | 3/15/2005 | 3/15/2005 | 3/15/2005 | P | PASS |
Jim Storey
|
|
|
first floor to 2nd ok 2hr wall joint fire stopping
|
PubWorks Occupancy Approval | 1/26/2005 | 1/26/2005 | 1/26/2005 | | DONE |
|
|
|
Final approval of drainage by B.Murphy 01/26/05
|
BLD-Aging Inspection | 9/10/2004 | 9/10/2004 | 9/10/2004 | | PASS |
Jim Storey
|
|
|
wip 9/13/2004 11:39:18 AM
|
BLD-Aging Inspection | 6/22/2004 | 6/22/2004 | 6/22/2004 | | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 4/16/2004 | 4/16/2004 | 4/16/2004 | P | PASS |
Jim Storey
|
|
|
nick grouting; Phone #: ###-#### Internet Inspection Request from: Darla Downs special insp. onsite. 4/16/2004 3:49:36 PM
|
BLD-Aging Inspection | 3/15/2004 | 3/15/2004 | 3/15/2004 | | PASS |
Jim Storey
|
|
|
wip 3/15/2004 8:18:22 AM
|
Plan resubmittals received | | | 2/24/2004 | | DONE |
|
|
|
Received three requested changes to the Bown shell and core projects. Routed to Mike P. kmm
|
BLD-Foundation | 1/9/2004 | 1/12/2004 | 1/12/2004 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 1/9/2004 at 2:35:08 PM. Contact: ###-####. Subject to special inspection. 1/12/2004 10:52:27 AM
|
BLD-Footing | 12/30/2003 | 12/31/2003 | 12/31/2003 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/30/2003 at 8:59:26 AM. Contact: ###-####.
|
Plan resubmittals received | | | 12/24/2003 | | DONE |
|
|
|
Received response letter to previous plan review, 16 soils reports, and 2 sets of sheets C1-A, a2.11a, a4.11a, a5.00, a5.11, S2.11a, s3.11a, S4.11, S6.11, S7.11 and m1.01a and forwarded to Mike Phillips.
|
(F) Reprint permit | | | 12/9/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/8/2003 | | DONE |
|
|
|
|
Telephone call | | | 12/8/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Permit Ready to Issue | | | 12/8/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/8/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/3/2003 | | 12/5/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2003 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/16/2003 | | 12/5/2003 | | PASS |
Mike Phillips
|
|
|
12/5/2003 16:49:01 M_P - activity updated through activity BLDA022 from case BLD03-02236.
|
Routing - PLAN CHECK | 12/2/2003 | | 12/3/2003 | | FAIL |
|
|
|
Second review failed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - Erosion and Sediment | 12/2/2003 | | 12/2/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/26/2003 | | 12/2/2003 | | |
|
|
|
Routed to ESC.
|
Plan resubmittals received | | | 12/2/2003 | | DONE |
|
|
|
Received two copies of revised ESC and narrative. Routed to Mike P. kmm
|
Routing - PLANNING | 11/26/2003 | | 11/26/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/26/2003 | | 11/26/2003 | | FAIL |
|
|
|
See comments under Erosion Control Permit.
|
Routing - PLANNING Land Div | 11/26/2003 | | 11/26/2003 | | PASS |
|
|
|
Riverwalk Subdivision No. 1 recorded 11-25-03. Lot 2 of Block 3.
|
Routing - FIRE | 11/21/2003 | | 11/25/2003 | | PASS |
|
|
|
REsubmittal acceptable.
|
Routing - PUBLIC WORKS | 11/14/2003 | | 11/21/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/17/2003 | | DONE |
|
|
|
Received two copies of ESC report. Routed to Mike P. kmm
|
Plan resubmittals received | | | 11/14/2003 | | DONE |
|
|
|
Received a transmittal letter to Mike P. & transmittal letter to Marty S. two A1.11 sheets. Taken to Mike P.
|
Plan resubmittals received | | | 11/14/2003 | | DONE |
|
|
|
Received transmittal letter from Toothman orton engineering & ESC narrative. Taken to Mike P.
|
Routing - PLAN CHECK | 11/5/2003 | | 11/14/2003 | | |
|
|
|
|
Plan resubmittals received | | | 11/12/2003 | | DONE |
|
|
|
Received two copies of revised sheets a1.11 and C1-A, one copy of fire flow package from United Water, letter from Dave miller and one copy of plan review response letter. routed to Mike P. kmm
|
Plan resubmittals received | | | 11/10/2003 | | DONE |
|
|
|
Received transmittal letter, response letter,two copies of supplemental structural calculations,two sets of sheets A1.11,A2.11A,A3.11A,A4.11A,A5.00,A5.11,A6.11A,S1.11,S2.11A,S3.11A,S4.11,S5.11,S5.12,S6.11,S7.11,C1.A,E2.1I,M1.01A taken to Mike P.
|
Routing - FIRE | 10/28/2003 | | 11/5/2003 | | FAIL |
|
|
|
FD access, fire water flow and AS valving issues; review faxed to architect and attached.
|
Routing Off Site -Energy | 9/16/2003 | | 10/28/2003 | | FAIL |
|
|
|
Contacted Ron O for outside enregy review.
|
Routing - PLAN CHECK | 10/2/2003 | | 10/28/2003 | | FAIL |
|
|
|
Plan review completed, sent correction report to archtitect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 9/26/2003 | | 10/2/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 9/25/2003 | | 9/26/2003 | | FAIL |
|
|
|
Landscape plan does not comply with Design Review DRH03-34.
|
Plan resubmittals received | | | 9/26/2003 | | DONE |
|
|
|
Received transmittal sheet with Erosion & sediment control design report. taken to Mike P.
|
Routing - Erosion and Sediment | 9/22/2003 | | 9/25/2003 | | FAIL |
|
|
|
No ESC narrative attached to plans.
|
Routing - PUBLIC WORKS | 9/16/2003 | | 9/22/2003 | | FAIL |
|
|
|
Requires site plans showing meets and bounds with utilities and easements being shown and building. Per April Miller Requires O&M manual and geotech report. Per Brian Murphy. Sanitary sewer is considered public and needs to be reviewed and approved separately by PW. Per John Johnson. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 9/16/2003 | | DONE |
|
|
|
Requires ESC RP and energy compliance cert. needs to be signed. kmm
|
Routing - PLANNING Land Div | 9/16/2003 | | 9/16/2003 | | FAIL |
|
|
|
Do not issue building permit until plat of Riverwalk Subdivision is recorded.
|
Plan routing begun/NEW & ADDTN | | | 9/16/2003 | | |
|
|
|
|
Application received | | | 9/15/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/15/2003 | | |
|
|
|
|
Fee Review-notes | 9/15/2003 | 9/15/2003 | | | |
|
|
|
|