BLD-Final | 12/23/2003 | 12/23/2003 | 12/23/2003 | P | PASS |
Jim Sly
|
|
|
Harvey ###-#### OK for Perm Occ. :) 12/23/2003 2:12:43 PM
|
FIRE-Final Inspection | 12/23/2003 | 12/23/2003 | 12/23/2003 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 12/23/2003 1:24:21 PM
|
First Notice | | 12/23/2003 | 12/23/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/23/2003 | 12/23/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/23/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9910 issued 12-23-03 to GMAC.
|
BLD-Wall cover | 12/11/2003 | 12/12/2003 | 12/12/2003 | A | PASS |
Jim Sly
|
|
|
###-#### Grid OK. 12/12/2003 9:15:39 AM
|
Issue & PRINT permit | | | 12/11/2003 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 11/3/2003 | 11/4/2003 | 11/4/2003 | P | PASS |
Jim Sly
|
|
|
harvey--call 1st before insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Issue PAID IN FULL permit | | | 10/22/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/16/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/16/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/16/2003 | | DONE |
|
|
|
called left a voice message for dick ,permit ready & fee given///dld 10-16-03 9:22
|
CHANGE STATUS TO (R) | | | 10/16/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/13/2003 | | 10/15/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan resubmittals received | | | 10/15/2003 | | DONE |
|
|
|
Received one copy of sheets S1, S2, S3, S4, S5, S6, S7. Three copies of revised sheet A1.0 and one copy of memo from Stapley engineering. Routed to Jason B. kmm
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2003 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 9/22/2003 | | 10/15/2003 | | PASS |
Jason Blais
|
|
|
10/15/2003 15:11:13 JCB - activity updated through activity BLDA022 from case BLD03-02261.
|
Routing - PLAN CHECK | 10/10/2003 | | 10/13/2003 | | FAIL |
|
|
|
Resubmittal plan sheets need architect stamp and signature. Also structural engineer to verify if wall with new opening is a bearing wall.
|
Plan resubmittals received | | | 10/13/2003 | | DONE |
|
|
|
Received three copies of revised sheet A-1 one copy of BRS Architects Memo and one copy of Stapley Engineering Memo. Routed to Jason B.
|
Routing - FIRE | 10/6/2003 | | 10/10/2003 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 10/6/2003 | | |
|
|
|
Two items in plan review report need to be addressed and additional information to be provided.
|
Routing - PLAN CHECK | 9/25/2003 | | 10/6/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architec. Response required for two items. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 9/24/2003 | | 9/25/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/22/2003 | | DONE |
|
|
|
|
Application received | | | 9/17/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/17/2003 | | |
|
|
|
|
Fee Review-notes | 9/17/2003 | 9/17/2003 | | | |
|
|
|
|