Agreement of Future work | 10/16/2003 | 2/2/2005 | 6/19/2007 | | DONE |
Jason Blais
|
|
|
Owner to submit plans for a permit for the second required accessible restroom, mop sink, and either a drinking fountain or water cooler. It was the owners intent to delay because he wanted to provide core restrooms usable by multiple tenants in the building.
10/27/2004 Extension to Upgrade Agreement approved by Jenifer Gilliland to be completed by 2/2/05.
1/28/05 owner came in stating he was still working on a plan and that a few tenants had backed out of lease deals. Owner indicated he would not meet deadline and was going to contact Jenifer Gilliland.
9/6/05 Sent letter to Richard Schultz concerning this issue to respond by the date of 9/16/05 and how it will be resolved. 9/16/05 Mr. Richard Schultz came in to discuss the agreement and had a preliminary plan for the core restrooms and a core janitor closet with a service sink. He stated he would be submitting for a building permit within a couple of weeks.
12/27/05 Building permit obtained to complete the upgrade work under permit BLD05-03253.
(JCB)
6/19/07 Permit finaled. Upgrade Agreement work complete.
|
Telephone call | | | 9/22/2004 | | |
|
|
|
Called Randy Schultz concerning upgrade agreement and he indicated that plans were being designed now and would be submitted by the October 16, 2004 agreement date. If a delay arises, they would submit a request for additional time.
|
(F) Reprint permit | | | 1/22/2004 | | DONE |
|
|
|
|
First Notice | | 1/16/2004 | 1/16/2004 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 1/16/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 9937 issued 1-16-04 to R.A. Schultz Company.
|
Permanent Occupancy | | 12/17/2003 | 12/17/2003 | | DONE |
|
|
|
|
BLD-Final | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PASS |
Dave Hannah
|
|
|
Richard; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Final | 12/16/2003 | 12/16/2003 | 12/16/2003 | P | FAIL |
Dave Hannah
|
|
|
Richard; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes needs plumbing final and landing out single door 12/16/2003 5:12:17 PM
|
FIRE-Final Inspection | 12/15/2003 | 12/16/2003 | 12/16/2003 | A | PASS |
Rick Jackson
|
|
|
Richard; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Framing/Rough-in | 12/11/2003 | 12/12/2003 | 12/12/2003 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/11/2003 at 3:38:19 PM. Contact: ###-####. ok to cover int infill walls 12/12/2003 4:50:57 PM
|
BLD-Conference | 12/11/2003 | 12/11/2003 | 12/11/2003 | P | DONE |
Troy James
|
|
|
Richard; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
okayed relocation of 1 hour wall. 12/11/2003 2:41:54 PM
|
BLD-Framing/Rough-in | 11/25/2003 | 11/26/2003 | 11/26/2003 | A | PASS |
Dave Hannah
|
|
|
re-bar inspection//dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to grout 11/26/2003 8:27:22 AM
|
BLD-Footing | 11/24/2003 | 11/24/2003 | 11/24/2003 | P | NR |
Jim Storey
|
|
|
Dave; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes need epoxy special insp of #5 bar verts 48 oc recall when ready to place grout. 11/24/2003 2:52:25 PM
|
Print Occupancy Form | | | 10/29/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/29/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/27/2003 | | DONE |
|
|
|
Spoke with Richard told permit is ready & fees
|
Permit Ready to Issue | | | 10/27/2003 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 9/22/2003 | | 10/27/2003 | | PASS |
Jason Blais
|
|
|
10/27/2003 08:27:09 JCB - activity updated through activity BLDA022 from case BLD03-02283.
|
Routing - PLAN CHECK | 10/23/2003 | | 10/27/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan resubmittals received | | | 10/24/2003 | | |
|
|
|
Received one page of a detail and cover letter. Routed to Jason
|
Telephone call | | | 10/23/2003 | | |
|
|
|
Called architect to request another detail for the new parapet wall extension addressing required vertical and horizontal reinforcement and grouting. Also the Alternate Approval letter concerning number of restrooms needs to be addressed to Tim Hogland, the Building Director, for approval.
|
Routing - PLAN CHECK | 10/13/2003 | | 10/23/2003 | | FAIL |
|
|
|
Need new parapet detail to address required vertical and horizontal reinforcement and grouting. Also need alternate approval letter concerning number of restrooms to be addressed to Tim Hogland the Building Director for approval.
|
Plan resubmittals received | | | 10/21/2003 | | DONE |
|
|
|
Received two copies of revised sheet A1.0, one copy of response letter, one copy of ADA compliant bathroom letter. Routed to Jason Blais. kmm
|
Routing - FIRE | 10/9/2003 | | 10/13/2003 | | PASS |
|
|
|
Approved subject to satisfactory insepction by PDS Fire; no written review comments.
|
Plan resubmittals requested | | | 10/9/2003 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 10/8/2003 | | 10/9/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review.
|
Routing - PUBLIC WORKS | 10/6/2003 | | 10/8/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/6/2003 | | DONE |
|
|
|
Received plans back from Pat McKeegan. Prepared for routing. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 9/24/2003 | | DONE |
|
|
|
Pat Mckeegan took plans back to his office to change title page to reflect the name change.
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2003 | | DONE |
|
|
|
|
Application received | | | 9/19/2003 | | |
|
|
|
|
Fee Review-notes | 9/19/2003 | 9/19/2003 | | | |
|
|
|
|