First Notice | | 3/12/2004 | 3/12/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/12/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10034 issued 3-12-04 to the Paper Express in the Westgate Shopping Center.
|
Letter of compliance | | | 1/7/2004 | | DONE |
|
|
|
Letter of Compliance issued 1-7-04.
|
Permanent Occupancy | | 12/29/2003 | 12/29/2003 | | DONE |
|
|
|
|
BLD-Final | 12/29/2003 | 12/29/2003 | 12/29/2003 | P | PASS |
Tom Arcoraci
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok for perm occ 12/29/2003 3:54:19 PM
|
FIRE-Final Inspection | 12/18/2003 | 12/19/2003 | 12/19/2003 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 12/19/2003 11:44:30 AM
|
BLD-Final | 12/18/2003 | 12/19/2003 | 12/19/2003 | P | FAIL |
Jim Sly
|
|
|
Matt, ###-#### : ) C/N Remove thumb turn from front door....Need Electr final.....Fire and Mech finaled (in computer). 12/18/2003 12:10:50 PM
|
BLD-Framing/Rough-in | 11/12/2003 | 11/13/2003 | 11/13/2003 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/12/2003 at 1:04:06 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 10/27/2003 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/1/2003 | | 10/24/2003 | | PASS |
Carl Westfall
|
|
|
10/24/2003 11:26:47 CJW - activity updated through activity BLDA022 from case BLD03-02360.
|
Routing - PLAN CHECK | 10/24/2003 | | 10/24/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 10/24/2003 | | 10/24/2003 | | PASS |
|
|
|
ESC waiver approved with conditions attached to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/24/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/24/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/24/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/24/2003 | | DONE |
|
|
|
Left message for Trent that permit is ready & fees
|
Telephone call | | | 10/24/2003 | | DONE |
|
|
|
Left message for Matt that permit is ready & fees
|
Routing - FIRE | 10/15/2003 | | 10/23/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/6/2003 | | 10/13/2003 | | PASS |
|
|
|
IBC plan review started October 13, 2003 and finished October 15, 2003. The drawings were approved with clarifications. See the plan review report. A copy was E-mailed to the architect.
|
Routing - PUBLIC WORKS | 10/1/2003 | | 10/6/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2003 | | DONE |
|
|
|
|
Application received | | | 9/29/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2003 | | DONE |
|
|
|
|
Fee Review-notes | 9/29/2003 | 9/29/2003 | | | |
|
|
|
|