Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/27/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent Occupancy | | 7/1/2004 | 7/1/2004 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 7/1/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10214 issued 7-1-04 to Dave Humphries.
|
BLD-Final | 6/24/2004 | 6/24/2004 | 6/24/2004 | P | PASS |
Jim Storey
|
|
|
###-#### rick
|
FIRE-Final Inspection | 6/21/2004 | 6/21/2004 | 6/21/2004 | P | PASS |
Rick Jackson
|
|
|
|
BLD-Aging Inspection | 6/9/2004 | 6/9/2004 | 6/9/2004 | | PASS |
Jim Storey
|
|
|
wip 6/9/2004 8:28:13 AM
|
BLD-Foundation | 3/17/2004 | 3/18/2004 | 3/18/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/17/2004 at 3:59:54 PM. Contact: ###-####. recieved engineering for grade bust and extention of specific colm. requring epoxy rebar in turn needs special insp of this part of project. 3/18/2004 9:56:02 AM
|
BLD-Footing | 3/11/2004 | 3/12/2004 | 3/12/2004 | A | PASS |
Jim Storey
|
|
|
re-bar inspection///ryan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
(F) Reprint permit | | | 3/10/2004 | | |
|
|
|
|
Plan resubmittals received | | | 3/9/2004 | | DONE |
|
|
|
Received three copies of revised sheetA4.0. Routed to Marty Santoyo. kmm
|
Issue PAID IN FULL permit | | | 3/9/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/8/2004 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/8/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2004 | | DONE |
|
|
|
permit ready and fee due
|
Plan assigned to (MLO) | 10/15/2003 | | 3/8/2004 | | PASS |
Mike Otto
|
|
|
3/8/2004 10:18:40 MLO - activity updated through activity BLDA022 from case BLD03-02517.
|
Routing - PLANNING | 3/1/2004 | | 3/5/2004 | | PASS |
|
|
|
Approved per DRH03-96 and as noted on sheet A4.0.
|
Plan resubmittals received | | | 3/1/2004 | | DONE |
|
|
|
Received letter of transmittal with three A4.0 sheets. Taken to Mike O.
|
Routing - PLAN CHECK | 2/26/2004 | | 2/26/2004 | | NR |
|
|
|
|
Routing - Erosion and Sediment | 2/26/2004 | | 2/26/2004 | | PASS |
|
|
|
|
Routing - PLUMBING | 2/25/2004 | | 2/25/2004 | | PASS |
|
|
|
Mike O. says the architect says he is deleting all the plumbing from this project so this approval is based on that information i.e. there is no plumbing approved under this permit. Architect would not return a call to plumbing plan reviewer Ron Ginner to verify.
|
Routing - PLUMBING | 2/20/2004 | | 2/20/2004 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/20/2004 | | 2/20/2004 | | NR |
|
|
|
|
Routing - PLUMBING | 2/20/2004 | | 2/20/2004 | | FAIL |
|
|
|
|
Routing - FIRE | 2/13/2004 | | 2/19/2004 | | PASS |
|
|
|
Approved per additional resubmittal information received 2/17/04.
|
Plan resubmittals received | | | 2/17/2004 | | DONE |
|
|
|
Received three copies of fire hydrant clearance (81/2 x 11) and one copy of revised sheet A1.0, signed fire chief plan. Routed to Mike O. kmm
|
Routing - PLAN CHECK | 2/4/2004 | | 2/4/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 2/2/2004 | | 2/3/2004 | | PASS |
|
|
|
Parcel created in Ada County prior to 1985. Legal parcel at time of annexation into Boise City.
|
Routing - PLAN CHECK | 1/28/2004 | | 2/2/2004 | | PEND |
|
|
|
only one set of metal building plans. 2/2
|
Plan resubmittals received | | | 1/27/2004 | | DONE |
|
|
|
Received transmittal letter with one set of calculations, design calculations, one set of C1,A1,A2,A3,A4,CS1,CS2,CS3,RF1,RF2,S1,S2,S3,E1,E2 taken to Mike O.
|
Routing - PUBLIC WORKS | 1/8/2004 | | 1/20/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 12/23/2003 | | DONE |
|
|
|
Received two copies of revised sheets A1, A5 and A6 with one copy of description of changes. One copy of water flows. Routed to Mike O. kmm
|
Plan Review Completed(1st rev) | | | 12/2/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/2/2003 | | 12/2/2003 | | NR |
|
|
|
|
Routing - FIRE | 12/2/2003 | | 12/2/2003 | | FAIL |
Bill Alexander
|
|
|
Lack water supply information for hydrant flows. Lack emergency vehicle access verification.
|
Routing - PLAN CHECK | 11/10/2003 | | 11/14/2003 | | FAIL |
|
|
|
Plans are incomplete and unacceptable for review. MLO
|
Routing - PLUMBING | 11/5/2003 | | 11/7/2003 | | FAIL |
|
|
|
see bld03-02554 for comments
|
Routing - PLANNING | 10/30/2003 | | 11/5/2003 | | FAIL |
|
|
|
Landscape plans do not indicate planting notes as required per DRH03-96.
|
Plan resubmittals received | | | 10/31/2003 | | DONE |
|
|
|
Received two copies of ESC narrative. Routed to Mike O.
|
Routing - Erosion and Sediment | 10/29/2003 | | 10/30/2003 | | FAIL |
|
|
|
ESC does not meet conditions of BCC 8-17 or Appendix A&C of Plan Designer Manual
|
Routing - PUBLIC WORKS | 10/20/2003 | | 10/29/2003 | | FAIL |
|
|
|
Requires Drainage Plan Geotech report.
|
Routing - PLANNING Land Div | 10/17/2003 | | 10/20/2003 | | FAIL |
|
|
|
Prior to issuance of building permit, need proof of legal land division. Called Hutchinson Smith Architects on 10/20/03.
|
Plans ACCEPTED BY PLAN TECH | | | 10/17/2003 | | PEND |
|
|
|
Waiting for pre-engineered plans and calcs.
|
Plan routing begun/NEW & ADDTN | | | 10/17/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/15/2003 | | DONE |
|
|
|
Requires permit to be seperated into three permits. Waiting for pre-engineered plans for the RV ports. Contacted David Humphries.
|
Application received | | | 10/15/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 10/15/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/15/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 10/15/2003 | | |
|
|
|
|
Routing - FIRE | 1/21/2004 | | 1/28/2003 | | FAIL |
|
|
|
Required resubmittal info not provided. Revised review faxed to architect.
|
Fee Review-notes | 10/15/2003 | 10/15/2003 | | | |
|
|
|
|