BLD-Final | 1/6/2004 | 1/7/2004 | 1/7/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/6/2004 at 3:08:14 PM. Contact: ###-####.
|
First Notice | | 1/7/2004 | 1/7/2004 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/7/2004 | 1/7/2004 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 1/7/2004 | | DONE |
|
|
|
Perm. Occ. Cert. #9921 issued 1-7-04 to Express Cash in Columbia Market A.
|
FIRE-Final Inspection | 1/6/2004 | 1/6/2004 | 1/6/2004 | P | PASS |
Rick Jackson
|
|
|
|
BLD-Other | 12/30/2003 | 12/30/2003 | 12/30/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/30/2003 at 9:05:12 AM. Contact: ###-####. ceilling ok 12/30/2003 3:30:31 PM
|
BLD-Wall cover | 12/4/2003 | 12/9/2003 | 12/9/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/4/2003 at 3:12:23 PM. Contact: ###-####. fire stopping to be verified above ceilling in common area. ele box less than 24 inch septration by back door of common area need spudy pad or moved/ ceilling steel rafters need top flange screwed to ledger/info on insulation for store front soffit area to be submited . ok to cover upon mech aproval of fire damper instaltion. 12/9/2003 9:30:29 AM
|
Issue PAID IN FULL permit | | | 11/24/2003 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 11/14/2003 | | 11/20/2003 | | PASS |
John Menard
|
|
|
11/20/2003 11:17:46 JCM - activity updated through activity BLDA022 from case BLD03-02569.
|
Routing - PLAN CHECK | 11/20/2003 | | 11/20/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/20/2003 | | DONE |
|
|
|
|
CHANGE STATUS TO (R) | | | 11/20/2003 | | DONE |
|
|
|
|
Telephone call | | | 11/20/2003 | | DONE |
|
|
|
CALLED LEFT VOICE MESSAGE FOR VICK PERMIT READY & FEE GIVEN 11-20-03 1:04 ///DLD
|
Routing - FIRE | 11/17/2003 | | 11/20/2003 | | PASS |
|
|
|
Approved with conditions. Review faxed to architect.
|
Plan assigned to (CJW) | 10/22/2003 | | 11/14/2003 | | |
Carl Westfall
|
|
|
Energy review by Carl. Drawings received October 20, 2003. 2 weeks (Nov. 3). 4 weeks (Nov. 17).
|
Plan Reviewer's activity | | | 11/14/2003 | | PASS |
|
|
|
Plans approved as submitted with attached comment list. JCM
|
Routing - PLUMBING | 11/14/2003 | | 11/14/2003 | | PASS |
|
|
|
per plans and 2000 upc
|
Routing - PLAN CHECK | 11/4/2003 | | 11/14/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/3/2003 | | 11/4/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/23/2003 | | 11/3/2003 | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/22/2003 | | 10/23/2003 | | FAIL |
|
|
|
Need to figure out addressing sequence, per April Miller. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 10/21/2003 | | DONE |
|
|
|
|
Application received | | | 10/20/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/20/2003 | | DONE |
|
|
|
|
Fee Review-notes | 10/20/2003 | 10/20/2003 | | | |
|
|
|
|