BLD-Final | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | PASS |
Jim Sly
|
|
|
Cameron, ###-#### - please call 1st so he can meet you there. All others have finaled project. Thanks : ) C/C issued. 1/31/2005 4:14:25 PM
|
DOC - Permit Finaled | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 1/31/2005 4:14:32 PM
|
FIRE-Final Inspection | 1/21/2005 | 1/21/2005 | 1/21/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled.
|
BLD-Wall cover | 11/2/2004 | 11/3/2004 | 11/3/2004 | A | PASS |
Tom Arcoraci
|
|
|
Kameron-call before you go out...this is ceiling cover; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok to cover and grid ok 11/3/2004 9:51:03 AM
|
BLD-Conference | 6/7/2004 | 6/8/2004 | 6/8/2004 | A | PASS |
Jim Sly
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Annette Moore Frame and Energy OK. 6/8/2004 11:12:37 AM
|
BLD-Conference | 4/13/2004 | 4/14/2004 | 4/14/2004 | A | PASS |
Jim Sly
|
|
|
MEET DIXIE AT 8:30 FOR A CONF
|
Issue PAID IN FULL permit | | | 4/2/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/10/2004 | | 3/19/2004 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2004 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/19/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/19/2004 | | |
|
|
|
|
Telephone call | | | 3/19/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (JCB) | 11/28/2003 | | 3/19/2004 | | PASS |
Jason Blais
|
|
|
3/19/2004 10:32:38 JCB - activity updated through activity BLDA022 from case BLD03-02866.
|
Routing - FIRE | 3/5/2004 | | 3/9/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/16/2003 | | 3/5/2004 | | PEND |
|
|
|
Plan review attached to plans. An active permit for the classroom areas under BLD03-01393 needs to be finaled. Fire Dept. approval required. Plans to route to Fire Dept. for review.
|
Routing - PLUMBING | 3/5/2004 | | 3/5/2004 | | PASS |
|
|
|
minor fixture relocation, flop restrooms and deleate 2 showers.
|
Plan resubmittals received | | | 3/4/2004 | | DONE |
|
|
|
Received two copies of revised sheets TI-1.0, M1.0 and kitchen/restroom plan and energy. Routed to Jason B. kmm
|
Routing - PLAN CHECK | 12/10/2003 | | 12/16/2003 | | FAIL |
|
|
|
Cursory review of project indicates several issues needing to be addressed. Contacted applicant to set up a meeting with him and the architect rep. Resubmittal drawings will be required prior to a full review and routing of plans to Fire Dept.
|
Telephone call | | | 12/15/2003 | | |
|
|
|
Called applicant to set up a meeting with him and the architect rep. He said he would get back to me. Several issues need to be addressed concerning the plans on this project. Resubmittal drawings will be required.
|
Routing - PLUMBING | 12/10/2003 | | 12/10/2003 | | PASS |
|
|
|
existing plumbing shall have thermal expansion protection and the water heater may require a pan with a drain.
|
Routing - PUBLIC WORKS | 12/5/2003 | | 12/9/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/4/2003 | | 12/5/2003 | | FAIL |
|
|
|
Plans to reroute to Public Works and Plumbing.
|
Plan resubmittals received | | | 12/4/2003 | | DONE |
|
|
|
Received three sets of sheets P1.0,M1.0, taken to Jason B.
|
Routing - PLUMBING | 12/1/2003 | | 12/3/2003 | | FAIL |
|
|
|
the plumbing plans submitted with these plans does not include the extent of work described in the building permit. please submit a complete set of plumbing drawings for the work to be preformed.
|
Routing - PUBLIC WORKS | 12/1/2003 | | 12/1/2003 | | FAIL |
|
|
|
To supply current plumbing plan showing all kitchen equipment and plumbing fixtures. Per Louise Waldorf. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 11/28/2003 | | DONE |
|
|
|
|
Application received | | | 11/26/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/26/2003 | | |
|
|
|
|
Fee Review-notes | 11/26/2003 | 11/26/2003 | | | |
|
|
|
|