First Notice | | 2/9/2004 | 2/9/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/9/2004 | | DONE |
|
|
|
Perm. Occ. Cert. #9982 issued 2-9-04 to the Cash Store in the Venture Development Building.
|
FIRE-Final Inspection | 1/21/2004 | 1/22/2004 | 1/22/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety OK 1/22/2004 11:02:18 AM
|
BLD-Final | 1/21/2004 | 1/22/2004 | 1/22/2004 | P | PASS |
Russ Owen
|
|
|
lancester ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Ok perm oc. 1/22/2004 2:21:38 PM
|
Permanent Occupancy | | 1/22/2004 | 1/22/2004 | | DONE |
|
|
|
|
BLD-Final | 1/20/2004 | 1/21/2004 | 1/21/2004 | A | FAIL |
Russ Owen
|
|
|
trot; Phone #: ###-#### Internet Inspection Request from: Annette Moore Needs fire life safety. also went over restroom finish requirements. 1/21/2004 1:37:00 PM
|
BLD-Framing/Rough-in | 1/5/2004 | 1/5/2004 | 1/5/2004 | P | PASS |
Russ Owen
|
|
|
ok tied top of walls. 1/5/2004 3:11:52 PM
|
BLD-Framing/Rough-in | 12/30/2003 | 12/31/2003 | 12/31/2003 | A | PART |
Russ Owen
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore walls ok need to verify tie wires have been completed at top of the 2 new walls work in progress for this now contractor notified. 12/31/2003 11:30:29 AM
|
Print Pending Permit.LaserJet4 | | | 12/19/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/18/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/18/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 12/18/2003 | | DONE |
|
|
|
Spoke with Troy and told him permit is ready & fees
|
Plan assigned to (JCB) | 12/10/2003 | | 12/17/2003 | | PASS |
Jason Blais
|
|
|
12/17/2003 08:03:42 JCB - activity updated through activity BLDA022 from case BLD03-02931.
|
Routing - PLAN CHECK | 12/17/2003 | | 12/17/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2003 | | PASS |
|
|
|
|
Routing - FIRE | 12/12/2003 | | 12/15/2003 | | PASS |
|
|
|
review faxed to architect due to possible need for AS modifications/permit.
|
Routing - PLAN CHECK | 12/11/2003 | | 12/12/2003 | | PEND |
|
|
|
Plan review report faxed to applicant. No response required. When approved by Fire Dept. a permit can be issued. Plans to route to Fire Dept.
|
Routing - PUBLIC WORKS | 12/10/2003 | | 12/11/2003 | | PASS |
|
|
|
|
Telephone call | | | 12/10/2003 | | DONE |
|
|
|
left mess for troy lanchaster that partial permit is ready
|
Issue & Print w/o conditions | | | 12/10/2003 | | DONE |
|
|
|
|
CHANGE STATUS TO (PND) | | | 12/10/2003 | | DONE |
|
|
|
I PUT THIS TO ISSUE, OOPS ! SO I PUT IT BACK TO PEND ///DLD 12-10-03
|
Plan Reviewer's activity | | | 12/10/2003 | | DONE |
|
|
|
PARTIAL PERMIT ISSUED at the request of the contractor on this date.
|
CHANGE ISSUED DATE | | | 12/10/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/8/2003 | | DONE |
|
|
|
|
Application received | | | 12/8/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/8/2003 | | DONE |
|
|
|
|
Fee Review-notes | 12/8/2003 | 12/8/2003 | | | |
|
|
|
|