Letter of compliance | | | 6/10/2004 | | DONE |
|
|
|
Letter of Compliance issued 6-10-04.
|
BLD-Final | 6/7/2004 | 6/8/2004 | 6/8/2004 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Wayne Berry
|
FIRE-Final Inspection | 5/13/2004 | 5/14/2004 | 5/14/2004 | A | PASS |
Rick Jackson
|
|
|
Internet Inspection Request from: Wayne Berry
|
FIRE-Final Inspection | 5/6/2004 | 5/6/2004 | 5/6/2004 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 5/6/2004 at 6:52:31 AM. Contact: ###-####. Alarms not ready so this will be inspected at alarm final 5/6/2004 8:48:34 AM
|
BLD-Conference | 4/23/2004 | 4/23/2004 | 4/23/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/23/2004 at 7:29:31 AM. Contact: ###-####. strucral steel ok 4/23/2004 2:49:34 PM
|
BLD-Footing | 4/20/2004 | 4/22/2004 | 4/22/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/20/2004 at 8:08:31 AM. Contact: ###-####. placed with special insp. 4/22/2004 8:17:34 AM
|
BLD-Footing | 4/20/2004 | 4/22/2004 | 4/22/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/20/2004 at 8:09:35 AM. Contact: ###-####. placed with special insp. 4/22/2004 3:55:21 PM
|
BLD-Conference | 4/20/2004 | 4/21/2004 | 4/21/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/20/2004 at 8:07:54 AM. Contact: ###-####. reviewed handrail requriments. 4/21/2004 9:19:29 AM
|
BLD-Footing | 4/20/2004 | 4/20/2004 | 4/20/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/20/2004 at 8:07:54 AM. Contact: ###-####. placed w/si 4/20/2004 2:33:08 PM
|
BLD-Conference | 4/16/2004 | 4/16/2004 | 4/16/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/16/2004 at 9:26:26 AM. Contact: ###-####.
|
Plan resubmittals received | | | 4/13/2004 | | DONE |
|
|
|
Received two copies of revised sheets A2.2A.2. Routed to Jim Storey. kmm
|
Print Occupancy Form | | | 3/26/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/26/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2004 | | DONE |
|
|
|
email to Paul and Darla permit ready and fee due
|
Issue & PRINT to be Invoiced | | | 3/26/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/12/2004 | | 3/25/2004 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/25/2004 | | PASS |
|
|
|
Plan resubmittals reviewed and approved with the undrstanding that a second exit from the exterior balcony, for electrical room #200C, will be submitted for review and approval as a deferred submittal. After approval, the second exit must be installed per the approved plans before occupancy. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2004 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 12/18/2003 | | 3/25/2004 | | PASS |
John Menard
|
|
|
3/25/2004 14:09:44 JCM - activity updated through activity BLDA022 from case BLD03-02947.
|
Plan resubmittals requested | | | 2/18/2004 | | |
|
|
|
E-mailed the architect requesting clarification on the exiting system from the second floor. JCM
|
Plan resubmittals received | | | 2/11/2004 | | DONE |
|
|
|
Received three copies of revised sheets A2.1A.1, A6.0.1, A7.0.2, and one copy of response letter. Routed to John M. kmm
|
Routing - FIRE | 2/11/2004 | | 2/11/2004 | | PASS |
|
|
|
Plans approved per additioanl information provided by Micron employees via teleconference 2/10/04
|
Routing - FIRE | 1/15/2004 | | 1/21/2004 | | HOLD |
|
|
|
Initial review begun. Hold for further study, review with MF and disc'n with Micron for clarification of terms, scope, and details verifying H occupancy requirements.
|
Plan Review Completed(1st rev) | | | 1/21/2004 | | FAIL |
|
|
|
Failed Building, Structural & Fire
|
Routing - PLAN CHECK | 12/11/2003 | | 1/15/2004 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 1/15/2004 | | |
|
|
|
E-mailed the architect a copy of the plan review comment list requesting revisions. JCM
|
Plan resubmittals requested | | | 1/15/2004 | | |
|
|
|
Faxed a copy of the consulting structural engineer's comment list requesting resubmittals. JCM
|
Routing Off Site - STRUCTURAL | 1/12/2004 | | 1/14/2004 | | PASS |
|
|
|
sending out resubmitted calcs. Received comment list from consulting structural engineer requesting additional revisions. JCM
|
Plan resubmittals received | | | 1/9/2004 | | DONE |
|
|
|
One copy of response letter and three copies of additional structual calcs. Routed to John M. kmm
|
Plan resubmittals requested | | | 12/22/2003 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 12/10/2003 | | 12/19/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside engineering. kmm Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing - PLUMBING | 12/11/2003 | | 12/11/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 12/10/2003 | | 12/11/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/10/2003 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 12/10/2003 | | DONE |
|
|
|
|
Application received | | | 12/9/2003 | | |
|
|
|
|
Fee Review-notes | 12/9/2003 | 12/9/2003 | | | |
|
|
|
|