Letter of compliance | | | 3/5/2004 | | DONE |
|
|
|
Letter of Compliance issued 3-5-04.
|
FIRE-Final Inspection | 2/13/2004 | 2/13/2004 | 2/13/2004 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 2/13/2004 at 11:00:17 AM. Contact: ###-####.
|
BLD-Final | 2/13/2004 | 2/13/2004 | 2/13/2004 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/13/2004 at 11:00:45 AM. Contact: ###-####.
|
FIRE-Final Inspection | 2/9/2004 | 2/9/2004 | 2/9/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 2/9/2004 at 6:22:52 AM. Contact: ###-####. removing the office wall has overspaced the 15 cd strobe from the wall with the new sink; a 110 cd strobe will be needed where the 15 cd strobe is currently located to meet NFPA 72 Table 7.5.4.1.1 (a) 2/9/2004 8:38:54 AM
|
BLD-Final | 2/9/2004 | 2/9/2004 | 2/9/2004 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/9/2004 at 6:23:31 AM. Contact: ###-####.
need f/l saftey 1st 2/9/2004 2:19:49 PM
|
Issue PAID IN FULL permit | | | 1/20/2004 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 12/19/2003 | | 1/16/2004 | | PASS |
|
|
|
1/16/2004 09:30:51 RMH - activity updated through activity BLDA022 from case BLD03-02969.
|
Routing - PLAN CHECK | 12/19/2003 | | 1/16/2004 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/16/2004 | | DONE |
|
|
|
Minor remodel of existing tenant space, Fire department to field inspect.
|
Case Summary (BLD) | | | 1/16/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/16/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/16/2004 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2004 | | DONE |
|
|
|
spoke with Eric -- permit is ready.
|
Application received | | | 12/12/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/12/2003 | | DONE |
|
|
|
|