Permit Information
Permit NumberBLD03-02994
StatusFinaled
Name ALBERTSONS INC
Site Address 250 E PARKCENTER BLVD
Project NameALBERTSONS
Customer Number 
ePlanReviewNo
Description
(ALBERTSONS INC)(1ST & 2ND FLR) Remodel to a 6,200 sq. ft. area on the first floor and to a 288 sq. ft. area on the second floor to an existing office building per approved plans on file. Remodel on the first floor will be a series of residential type test/demonstration kitchens for grocery store food products with some work rooms and storage. One kitchen will be set up as a commercial kitchen with Type I hood and approved duct wrap system for the grease duct. The second floor remodel will be for two new small offices. Work to include some interior demolition work, some new 20 minute rated doors in existing one-hour rated exit corridor, new one-hour rated wall infill in former door opening in existing one-hour rated corridor, new interior walls, new interior doors, interior finish, suspended ceiling work, new counters/cabinets, new sinks, fire sprinkler work, fire alarm work, mechanical work, plumbing work, and electrical work. This is a Scope of Work Permit. Letter of Completion to be issued when done. NOTE: This building is fully fire sprinklered and has 60' minimum yards on all sides for unlimited area. (PC#0778-03) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection5/12/20045/12/20045/13/2004APASS
DetailsRick Jackson
air balance report okay 5/13/2004 10:54:35 AM
BLD-Final5/12/20045/12/20045/12/2004PPASS
DetailsJim Storey
bob; Phone #: ###-#### Internet Inspection Request from: Annette Moore l/c ok 5/12/2004 2:17:09 PM
Letter of compliance  5/12/2004 DONE
Letter of Compliance issued 5-12-04.
BLD-Other4/7/20044/7/20044/7/2004PPASS
DetailsJim Storey
corridor fire stopping ok ok to cover ceilling.
BLD-Framing/Rough-in4/5/20044/6/20044/6/2004APART
DetailsJim Storey
ceiling inspection to cover please//bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore all but interface with rated corridor wall south.pending ele. 4/6/2004 1:06:57 PM
BLD-Framing/Rough-in3/8/20043/9/20043/9/2004APASS
DetailsJim Storey
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Conference3/2/20043/3/20043/3/2004APART
DetailsJim Storey
Bob; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes framing ok to cover . 3/3/2004 8:56:01 AM
Issue PAID IN FULL permit  2/23/2004 DONE
Plan assigned to (JCB)12/26/2003 2/20/2004 PASS
DetailsJason Blais
2/20/2004 13:10:20 JCB - activity updated through activity BLDA022 from case BLD03-02994.
Routing - PLAN CHECK2/20/2004 2/20/2004 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  2/20/2004 PASS
Inspection Record Card- Bld  2/20/2004 DONE
Permit Ready to Issue  2/20/2004 DONE
Telephone call  2/20/2004 DONE
spoke with Bob -- permit is ready.
Routing - FIRE2/13/2004 2/19/2004 PASS
resubmittal acceptable.
Routing - PLAN CHECK1/29/2004 2/13/2004 PEND
When approved by Fire Dept. a permit can be issued. Plans to route to Fire Dept.
Plan resubmittals received  2/9/2004 DONE
Received one copy of plan review response letter, letter with a statement regarding the usage of the test kitchen area. Structural calculations and sketches. Lighting compliance certificate 81/2 x 11. UL letter reguarding surface burning characteristics classification. Two copies of revised sheets A0.00, A0.01, A1.01, A2.01, A2.02, A2.03, A4.01, A5.01, A6.01, P0.0, P0.1, P1.0, P1.1, P1.2, P2.0, P3.0, M0.0, M0.1, M1.1, M1.2, M1.3, M2.0, M2.2, M3.0, FP1.1, FP3.0, E0, E2.0P, E2.0L, E2.0F, E2.1P, E2.2P, E4.0, E4.1. Routed to Jason B. kmm
Routing - PLAN CHECK1/5/2004 1/22/2004 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
Plan resubmittals requested  1/22/2004  
Plan resubmittals and written response required for further review.
Routing - FIRE1/22/2004 1/8/2004 FAIL
REview comments faxed to architect and attached to this permit
Routing - PLUMBING12/31/2003 1/5/2004 PASS
PROVIDE THERMOL EXPANTION PRETECTION AT WATER HEATER, WASTE TO 1ST SINK MUST BE 3".
Routing - PUBLIC WORKS12/29/2003 12/31/2003 PASS
Plans ACCEPTED BY PLAN TECH  12/19/2003 DONE
Routing Off Site - C.D.H  12/18/2003 DONE
David Brodgett came in to take plans to CDH,12-18-03 Debbie signed off today.
Plans ACCEPTED BY PLAN TECH  12/17/2003 FAIL
Plans need to be taken to CDH for review per Debbie with the Health Dept. I called the Architect to let David know. rad
Application received  12/16/2003  
Recd Pcfee & Taken To Pln CK  12/16/2003  
Fee Review-notes12/16/200312/16/2003