Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice Sent | | 6/16/2004 | 4/26/2005 | | DONE |
|
|
|
|
DOC - Permit Finaled | 6/16/2004 | 6/16/2004 | 6/16/2004 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 6/16/2004 3:02:12 PM
|
BLD-Final | 6/16/2004 | 6/16/2004 | 6/16/2004 | P | DONE |
Tony Young
|
|
|
|
BLD-Aging Inspection | 6/15/2004 | 6/15/2004 | 6/15/2004 | | PASS |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 3/30/2004 | 3/30/2004 | 3/30/2004 | | DONE |
|
|
|
Drainage project complete. On acceptance of engineer's letter by Brian Murphy, signed permanent occupancy 3/30/04. R.Rokovitz
|
Issue PAID IN FULL permit | | | 3/15/2004 | | DONE |
|
|
|
|
Plan assigned to (KMM) | 12/18/2003 | | 3/9/2004 | | PASS |
Kathy Miller
|
|
|
3/9/2004 10:13:09 RAD - activity updated through activity BLDA022 from case BLD03-03012.
|
Routing - PUBLIC WORKS | 2/27/2004 | | 3/9/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/9/2004 | | 3/9/2004 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/9/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/9/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/9/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/9/2004 | | DONE |
|
|
|
left a message for Bill Roscoe -- permit is ready.
|
Routing - PLAN CHECK | 2/2/2004 | | 2/27/2004 | | |
|
|
|
Plans in hold box.
|
Routing - PUBLIC WORKS | 1/29/2004 | | 2/2/2004 | | FAIL |
|
|
|
Requires Drainage Plan per Brian Murphy
|
Plan resubmittals received | | | 1/30/2004 | | DONE |
|
|
|
Received 4 copies of addendum #1 for C-1 drawings. Routed to PW. kmm
|
Routing - PLAN CHECK | 1/9/2003 | | 1/29/2004 | | |
|
|
|
Plans in my hold box waiting for PW approval. kmm
|
Routing - FIRE | 1/7/2004 | | 1/9/2004 | | PASS |
|
|
|
Approved-no review comments
|
Routing - PLANNING | 12/30/2003 | | 1/2/2004 | | PASS |
|
|
|
pending DR review (Marty) SAR
Approved per DR.
|
Routing - Erosion and Sediment | 12/29/2003 | | 12/30/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans. Prior to the start of construction a ESC Responsible person must be designated for this site. Failure to designate a RP will result in a stop work order.
|
Routing - PUBLIC WORKS | 12/18/2003 | | 12/29/2003 | | FAIL |
|
|
|
Requires drainage plan. BM
|
Routing - PLANNING Land Div | 12/18/2003 | | 12/18/2003 | | PASS |
|
|
|
Approved. Lots 1-6 have one tax parcel number.
|
Plan routing begun/TENANTS | | | 12/18/2003 | | DONE |
|
|
|
|
Application received | | | 12/18/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/18/2003 | | DONE |
|
|
|
|