Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/11/2005 | 4/26/2005 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/11/2005 | 3/11/2005 | | DONE |
|
|
|
|
BLD-Final | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PASS |
Jim Sly
|
|
|
kerry ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Perm Occ. :) 3/11/2005 8:53:57 AM
|
Override - Parcel Holds | | | 3/11/2005 | | |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/11/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10470 issued 3-11-05 to the King of Glory Lutheran Church classroom addn.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 3/10/2005 | | |
|
|
|
need insp
|
BLD-Conference | 3/7/2005 | 3/8/2005 | 3/8/2005 | A | CANC |
Jim Sly
|
|
|
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 3/7/2005 | | |
|
|
|
this is for landscaping
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 3/7/2005 | | |
|
|
|
per terry has paperwork ready at site
|
FIRE-Final Inspection | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 2/11/2005 8:43:36 AM
|
BLD-Final | 2/10/2005 | 2/11/2005 | 2/11/2005 | P | NR |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore OK for Perm Occ. when Code Enforce sign off for Perm. 2/11/2005 4:17:24 PM
|
PubWorks Occupancy Approval | 2/9/2005 | 2/9/2005 | 2/9/2005 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 2/9/05 D.Erskine
|
FIRE-Final Inspection | 2/4/2005 | 2/4/2005 | 2/4/2005 | A | FAIL |
Troy Cobbley
|
|
|
Paint curgbing for fire dept access as discussed and marked on approved drawings. Repair the two existing exit signs in the assembly hall. Provide occupant load signs for both assembly areas.
|
Agreement of Future work | 11/19/2004 | 1/14/2005 | 2/4/2005 | | DONE |
|
|
|
Fire Alarm Work Finaled 2/4/2005
|
BLD-Framing/Rough-in | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PASS |
Jim Sly
|
|
|
ceiling grid-- terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 1/24/2005 | 1/25/2005 | 1/25/2005 | A | PASS |
Jim Sly
|
|
|
cieling grid inspection please///terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 1/20/2005 | 1/21/2005 | 1/21/2005 | P | NR |
Jim Sly
|
|
|
Terry-ceiling grid; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Framing/Rough-in | 1/7/2005 | 1/10/2005 | 1/10/2005 | A | PART |
Jim Sly
|
|
|
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice Library and ajacent rooms. 1/10/2005 9:37:00 AM
|
BLD-Framing/Rough-in | 12/10/2004 | 12/13/2004 | 12/13/2004 | A | PART |
Jim Sly
|
|
|
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice Soffits/ceiling framing at main hallway OK. Sprinkler inspection...OK. 12/13/2004 10:54:20 AM
|
Plan resubmittals received | | | 12/2/2004 | | |
|
|
|
|
BLD-Framing/Rough-in | 11/18/2004 | 11/19/2004 | 11/19/2004 | A | PART |
Jim Sly
|
|
|
ceiling grid inspection please////terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 4 conditional use rooms OK for grid. 11/19/2004 11:44:29 AM
|
BLD-Conference | 10/27/2004 | 10/28/2004 | 10/28/2004 | A | PASS |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Need Fire Guru blessing for partial Occ. on new and old areas befor finals. 10/28/2004 3:44:15 PM
|
FIRE-Conference | 10/28/2004 | 10/28/2004 | 10/28/2004 | P | DONE |
Troy Cobbley
|
|
|
Contractor wants to move people out of four existing offices into four new offices. Per Dave Miller Benchmark Construction needs to submit a letter to him stating what they want to do, why they can't get fire alarm and fire sprinkler systems operational at the time they do this and a time line on when work will be completed or else they will need to vacate. 10/28/2004 4:14:10 PM
|
BLD-Energy code compliance | 9/20/2004 | 9/20/2004 | 9/20/2004 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/20/2004 at 7:05:09 AM. Contact: ###-####. Frame pass. 9/20/2004 12:15:30 PM
|
BLD-Framing/Rough-in | 9/13/2004 | 9/14/2004 | 9/14/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/13/2004 at 2:24:42 PM. Contact: ###-####. All OK except Need to check shear wall W of restrooms at energy code insp. 9/14/2004 1:53:33 PM
|
BLD-Framing/Rough-in | 9/8/2004 | 9/10/2004 | 9/10/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/8/2004 at 7:40:43 AM. Need straps at micros to wall, complete shear wall W.of restrms. OK to insulate.
9/10/2004 3:37:17 PM 9/10/2004 3:37:42 PM
|
BLD-Framing/Rough-in | 8/30/2004 | 8/31/2004 | 8/31/2004 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 1:39:09 PM. Contact: ###-####. C/N mRemove all kraft facing from existing insul....OR protect. Framing OK. 8/31/2004 10:15:07 AM
|
BLD-Framing/Rough-in | 8/26/2004 | 8/27/2004 | 8/27/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/26/2004 at 10:40:39 AM. Contact: ###-####. Framing in existing Bldg at daycare area...OK Note: Need to remove kraft paper on existing ceiling insulation. Foot and wall OK at front entry columns....N. wall. 8/27/2004 3:44:14 PM
|
BLD-Other | 8/24/2004 | 8/25/2004 | 8/25/2004 | P | PART |
Jim Sly
|
|
|
terry - plywood inspect for new roof job; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 8/25/2004 3:03:12 PM Roof OK. 8/25/2004 3:49:58 PM
|
BLD-Framing/Rough-in | 8/16/2004 | 8/18/2004 | 8/18/2004 | A | PART |
Lane Manuel
|
|
|
TERRY SHEAR WALL; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Exter. shear nailing ok. LM 8/18/2004 11:05:22 AM
|
BLD-Foundation | 7/19/2004 | 7/20/2004 | 7/20/2004 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/19/2004 at 1:19:28 PM. Contact: ###-####.
c/n posted on changes and fix for rebar,, ok to pour if needed 7/20/2004 11:05:25 AM
|
BLD-Footing | 7/14/2004 | 7/15/2004 | 7/15/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 7/14/2004 at 3:53:15 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 6/15/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/15/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/28/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/28/2004 | | |
|
|
|
|
Telephone call | | | 5/28/2004 | | DONE |
|
|
|
permit ready and fee due
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2004 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 12/22/2003 | | 5/27/2004 | | PASS |
Mike Otto
|
|
|
5/27/2004 13:49:31 MLO - activity updated through activity BLDA022 from case BLD03-03027.
|
Routing - FIRE | 5/21/2004 | | 5/26/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - Erosion and Sediment | 5/26/2004 | | 5/26/2004 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PLAN CHECK | 5/17/2004 | | 5/21/2004 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/17/2004 | | 5/20/2004 | | PASS |
|
|
|
|
Routing Off Site -Energy | 12/23/2003 | | 5/20/2004 | | PASS |
|
|
|
Contacted Eric M for outside energy review. kmm corrections sent to architect
|
Plan resubmittals received | | | 5/14/2004 | | DONE |
|
|
|
Received Transmittal Letter , 3 Sets G-1,SD-1,S0.1,A-1,A-7,E2.1F, E2.1L,E2.1P,ES.1S, E2.1S,E3.0, Taken to Mike Otto...
|
Routing - FIRE | 1/21/2004 | | 1/28/2004 | | FAIL |
|
|
|
REview comments faxed to architect and attached to this permit.
|
Plan Review Completed(1st rev) | | | 1/28/2004 | | FAIL |
|
|
|
Failed Structural, Public Works, ESC, Plan Check and Fire.
|
Routing Off Site - STRUCTURAL | 12/23/2003 | | 1/21/2004 | | FAIL |
|
|
|
Contacted PDQ for outside engineering review. corrections sent to architect
|
Routing - PLAN CHECK | 1/15/2004 | | 1/21/2004 | | FAIL |
|
|
|
corrections sent to architect. MLO
|
Plan resubmittals requested | | | 1/21/2004 | | DONE |
|
|
|
IBC, Struc. and energy corrections
|
Routing - PUBLIC WORKS | 1/13/2004 | | 1/15/2004 | | PASS |
|
|
|
|
Routing - PLUMBING | 1/8/2004 | | 1/9/2004 | | PASS |
|
|
|
Approved per plan and as noted to provide water heater detail and thermal expansion on drawings prior to construction. Called engineer on 1/9/2004.
|
Plan resubmittals received | | | 1/8/2004 | | DONE |
|
|
|
Received to two L1sheets and put with plans.
|
Routing - PUBLIC WORKS | 12/23/2003 | | 1/6/2004 | | FAIL |
|
|
|
Requires drainage plan revision.
|
Routing - PLANNING | 1/6/2004 | | 1/6/2004 | | PASS |
|
|
|
Susan Riggs CUP03-00098
DRH03-00089 is not a part of this application
|
Routing - Erosion and Sediment | 1/6/2004 | | 1/6/2004 | | FAIL |
|
|
|
Individual listed as RP not certified by Boise City.
|
Routing - PLANNING Land Div | 12/23/2003 | | 12/23/2003 | | PASS |
|
|
|
Lot 1, Block 1 of King of Glory Lutheran Church Survey Subdivision.
|
Plans ACCEPTED BY PLAN TECH | | | 12/23/2003 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 12/23/2003 | | DONE |
|
|
|
|
Application received | | | 12/22/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/22/2003 | | |
|
|
|
|
Fee Review-notes | 12/22/2003 | 12/22/2003 | | | |
|
|
|
|