Third Notice BLD | 5/20/2005 | 5/20/2005 | 12/9/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Over a year old No final values
|
Second Notice BLD | 4/26/2005 | 4/26/2005 | 5/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/3/2005 | 4/26/2005 | | DONE |
|
|
|
|
BLD-Aging Inspection | 8/18/2004 | 8/18/2004 | 8/18/2004 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 6/16/2004 | 6/17/2004 | 6/17/2004 | P | PASS |
Dave Hannah
|
|
|
rick-- ###-#### ok for perm occ 6/17/2004 3:19:51 PM
|
Permanent Occupancy | | 6/17/2004 | 6/17/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/17/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10191 issued 6-17-04 to The Melting Pot.
|
FIRE-Final Inspection | 5/27/2004 | 5/28/2004 | 5/28/2004 | A | PASS |
Rick Jackson
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 5/27/2004 | 5/28/2004 | 5/28/2004 | P | PART |
Tom Arcoraci
|
|
|
rick ###-#### ok for temp check tp holders in baths and exit sign in bar area 5/28/2004 2:57:46 PM
|
Temporary occupancy | | | 5/28/2004 | | DONE |
|
|
|
Temp. Occ. cert. # 5116 issued 5-28-04 tothe Melting Pot.
|
BLD-Conference | 5/25/2004 | 5/26/2004 | 5/26/2004 | A | PART |
Russ Owen
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Annette Moore Contractor wanted some info on 2 doors, access issues, on the plan review comments there is a note that they are to comply with building code 1/4" min slope etc. 5/26/2004 1:49:59 PM
|
BLD-Framing/Rough-in | 5/21/2004 | 5/24/2004 | 5/24/2004 | P | PASS |
Tom Arcoraci
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie grid ok 5/24/2004 4:24:27 PM
|
FIRE-Conference | 5/24/2004 | 5/24/2004 | 5/24/2004 | P | PART |
Rick Jackson
|
|
|
Met with Rick about items for final: need to test all emergency/exit signs for battery back-up; remove deadbolts from exit doors; provide occupant load sign; install fire extinguishers 5/24/2004 4:35:25 PM
|
BLD-Framing/Rough-in | 5/18/2004 | 5/19/2004 | 5/19/2004 | P | PART |
Dave Hannah
|
|
|
rick ceiling inspect in kitchen; Phone #: ###-#### Internet Inspection Request from: Annette Moore ceiling in kitchen ok 5/19/2004 3:55:08 PM
|
BLD-Framing/Rough-in | 5/6/2004 | 5/6/2004 | 5/6/2004 | P | PART |
Dave Hannah
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Annette Moore new roof framing for air handler ok 5/6/2004 3:01:14 PM
|
BLD-Wall cover | 4/9/2004 | 4/12/2004 | 4/12/2004 | A | PART |
Troy James
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Provide 48" clearance at hallway between restrooms. Ok to cover walls other areas. 4/12/2004 10:08:15 AM
|
Inspection Record Card- Bld | | | 3/15/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2004 | | DONE |
|
|
|
permit ready and fee due
|
Permit Ready to Issue | | | 3/10/2004 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2004 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/12/2004 | | 3/10/2004 | | PASS |
Carl Westfall
|
|
|
3/10/2004 16:02:01 CJW - activity updated through activity BLDA022 from case BLD04-00031.
|
Routing - FIRE | 3/6/2004 | | 3/9/2004 | | PASS |
|
|
|
acceptble per resubmittal
|
Routing - PLAN CHECK | 2/18/2004 | | 3/6/2004 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 3/1/2004 | | DONE |
|
|
|
Received response letter, Plan review report with project information, two sets of sheets A1.1,A1.2,A4.2,M-1,M-2,M-3, taken to Carl W.
|
Plan resubmittals received | | | 2/23/2004 | | DONE |
|
|
|
Received additional information regarding cooking operations relative to grease emissions; replied to by letter faxed to submitter Jay Walden.
|
Plan resubmittals received | | | 2/19/2004 | | DONE |
|
|
|
Received via fax, one copy of plan review response to Carl W., one copy of fire alarm system installation memo and one memo reguarding handicap access to the patio dining. Routed to Carl W. kmm
|
Routing - PLUMBING | 2/18/2004 | | 2/18/2004 | | PASS |
|
|
|
backflow preventors must be within 5' of the floor, rout waste from hand sink at the bar to a floor sink, all indirect waste receptors must be kept out from under cabinets and equipment, pipe grease trap to a floor sink, cooler hub drain trap must be with in 5' of its vent, additional cross connection protection may be required, if an automatic soap dispensor is installed at the mop sink, provide a water supply for it.
|
Routing - PLAN CHECK | 2/17/2004 | | 2/17/2004 | | |
|
|
|
|
Routing - FIRE | 2/6/2004 | | 2/14/2004 | | |
|
|
|
Failed first IFC code. Sprinkler valving and water information required; review comments faxed to architect and attached.
|
Routing - PLAN CHECK | 1/20/2004 | | 2/6/2004 | | |
|
|
|
Failed first IBC plan reveiw. IBC plan review started February 2, 2004 and was finished February 6, 2004. A response from the archtiect was required. See the plan review report. A copy was E-mailed to the architect.
|
Plan resubmittals received | | | 1/30/2004 | | DONE |
|
|
|
Received four sets of sheets P-1,P2,P3,P4 taken to Carl W.
|
Plan resubmittals received | | | 1/28/2004 | | DONE |
|
|
|
Received via fax the details on plumbing routed to Ron G. Ron G wanted these details to go with the plans. Routed to Carl W on 2/10/04. kmm
|
Routing - PLUMBING | 1/20/2004 | | 1/20/2004 | | |
|
|
|
Failed first UPC review. drawings must meet the 2000 uniform plumbing code
|
Routing - PUBLIC WORKS | 1/12/2004 | | 1/16/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/13/2004 | | DONE |
|
|
|
Received five copies of sheet E5.0 for energy lighting compliance. Routed to Carl W. kmm Per Jim Rogers, plans are to have ESC permit with waiver letter for the interior demo work, due to downtown proximity. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 1/12/2004 | | PEND |
|
|
|
Called David Hiatt to let him know we needed energy compliance. Received fax letting us know that the energy sheets are to follow this fax.
No Planning review required per Marty Santoyo.
|
Application received | | | 1/9/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2004 | | |
|
|
|
|
Fee Review-notes | 1/9/2004 | 1/9/2004 | | | |
|
|
|
|
Routing - PLAN CHECK | 3/10/2004 | | | | |
|
|
|
|