Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD04-00116
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project Name 
Customer NumberPCS#7012
ePlanReviewNo
Description
Micron Building #1 - Remodel Plenum 6 (PCS #01-20047012) - To demolish and excavate below approximately 200 square feet (13.5'x15') of existing concrete slab floor and to pour a new concrete slab floor at 42 inches below existing floor and perimeter concrete retaining walls. To install new access floor system, remodel ceiling above this area and reconstruct 17 lineal feet of clean room wall. To relocate existing lights, electrical outlets and HVAC duct work to accomodate ceiling and wall modifications. This work is being done on the first floor of Building #1 between grid lines C&D and 3&4. All construction per the approved plans. #04-037/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  4/13/2004 DONE
Letter of Compliance issued 4-13-04.
FIRE-Final Inspection4/9/20044/9/20044/9/2004APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 4/9/2004 at 6:45:16 AM. Contact: ###-####. No fire alarm work or sprinkler work was required; the horn/strobe and heat detector were just replaced after the floor was replaced 4/9/2004 9:22:47 AM
BLD-Final4/9/20044/9/20044/9/2004PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/9/2004 at 6:45:56 AM. Contact: ###-####.
Inspection Record Card- Bld  3/8/2004 DONE
BLD-Footing2/23/20042/26/20042/26/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/23/2004 at 2:41:17 PM. Contact: ###-####.
(F) Reprint permit  2/26/2004  
BLD-Footing2/23/20042/25/20042/25/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/23/2004 at 2:40:59 PM. Contact: ###-####.
BLD-Conference2/23/20042/24/20042/24/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/23/2004 at 4:17:48 PM. Contact: ###-####.
BLD-Footing2/23/20042/24/20042/24/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/23/2004 at 2:40:35 PM. Contact: ###-####.
Plan assigned to (JCM)1/23/2004 2/20/2004 PASS
DetailsJohn Menard
2/20/2004 13:13:23 JCM - activity updated through activity BLDA022 from case BLD04-00116.
Routing - Erosion and Sediment2/13/2004 2/20/2004 PASS
ESC approved with conditions attached to plans.
Routing - PLAN CHECK2/20/2004 2/20/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  2/20/2004 PASS
Permit Ready to Issue  2/20/2004 DONE
Inspection Record Card- Bld  2/20/2004 DONE
Print Occupancy Form  2/20/2004 DONE
Issue & PRINT to be Invoiced  2/20/2004 DONE
(F) Reprint permit  2/20/2004 DONE
Routing - PLAN CHECK2/13/2004 2/13/2004  
Routing - FIRE2/5/2004 2/12/2004 PASS
Plan resubmittals received  2/10/2004 DONE
Received a 2 page letter to Jim Rogers, ESC application, Warranty deed taken to John M. I will create ESC permit.
Routing - PLAN CHECK1/28/2004 2/5/2004 PASS
Plan Reviewer's activity  2/5/2004 PASS
Plans reviewed and approved as submitted. JCM
Routing - Erosion and Sediment1/28/2004 1/28/2004 FAIL
Contacted Paul Marcolina for an ESC application. rad
No ESC application or request for Waiver attached.
Routing - PUBLIC WORKS1/23/2004 1/27/2004 PASS
Plan routing begun/NEW & ADDTN  1/23/2004  
Application received  1/22/2004  
Recd Pcfee & Taken To Pln CK  1/22/2004  
Fee Review-notes1/22/20041/22/2004