Permit Information
Permit NumberBLD04-00157
StatusFinaled
Name STEED CONSTRUCTION
Site Address 2031 E HOSPITALITY CT
Project NameMODERN DENTAL BLDG
Customer Number 
ePlanReviewNo
Description
Modern Dental Building (Shell Only). To construct a new 6,455 sq.ft. two story, wood framed, nonrated, shell building for future tenant spaces. The first floor is 5,690 sq.ft and the second floor is 765 sq.ft. Work to include on site landscaping and parking lot. All construction per the approved plans and attached comment list. This is a shell only building. Separate permits must be approved prior to construction of any interior tenant spaces. NOTE: This building is located in Airport Influence Area B1 (needs NLR of 30 DB).see bld04-01473 for grading permit per mike phillips/2/25/05/mls
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  5/24/2005 DONE
Letter of Compliance issued 5-24-05.
BLD-Final5/18/20055/18/20055/18/2005PPASS
DetailsJim Storey
tim ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Code Occupancy Approval Temp5/18/20055/18/20055/18/2005AFAIL
DetailsDena Gambrel
Temporary occupancy sign off. They need updated landscape plan on file with the City. 5/18/2005 10:29:30 AM
BLD-Final5/18/20055/18/20055/18/2005PPASS
DetailsJim Storey
tim ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for l/c.
BLD-Aging Inspection5/12/20055/12/20055/15/2005 NR
DetailsJim Storey
pending others.
FIRE-Final Inspection5/13/20055/13/20055/13/2005PPART
DetailsForrest France
Pass inspection pending minor curb painting at short curb interval southeast main access roadway.
PubWorks Occupancy Approval5/13/20055/13/20055/13/2005 DONE
Drainage project complete, signed permanent occupancy 5/13/05. D.Erskine
BLD-Framing/Rough-in3/2/20053/3/20053/3/2005APASS
DetailsTroy James
tim ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in2/23/20052/24/20052/25/2005APASS
DetailsJim Storey
kim; Phone #: ###-#### call before you go out/ Internet Inspection Request from: Jan Rice
Case Summary (BLD)  2/25/2005 DONE
BLD-Framing/Rough-in1/10/20051/10/20051/10/2005PPART
DetailsJim Storey
tim- nailing insp--call 1st before insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie roof and exterior ok for cover. 1/10/2005 1:28:47 PM
(F) Reprint permit  1/10/2005 DONE
BLD-Framing/Rough-in1/7/20051/7/20051/7/2005PPART
DetailsJim Storey
tim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles exterior ok for cover/ 1/7/2005 2:41:22 PM
BLD-Framing/Rough-in11/4/200411/5/200411/5/2004APART
DetailsJim Storey
Tim-Partial Framing-Floor Joists; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner floor framing ok 11/5/2004 9:49:03 AM
Override - Parcel Holds1/1/19001/1/190011/4/2004  
BLD-Foundation10/29/200410/29/200410/29/2004PPART
DetailsJim Storey
donny; Phone #: ###-#### Internet Inspection Request from: Barbara Moore pwsi 10/29/2004 4:15:48 PM
Override - Parcel Holds1/1/19001/1/190010/29/2004  
foundation inspection
BLD-Footing10/25/200410/26/200410/26/2004PNR
DetailsDave Hannah
Donnie; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner will use spec inspection for rebar sign off 10/26/2004 5:11:27 PM
Override - Parcel Holds1/1/19001/1/190010/25/2004  
Override - Parcel Holds1/1/19001/1/190010/25/2004  
(F) Reprint permit  9/21/2004  
Override - Parcel Holds  9/20/2004  
Issue PAID IN FULL permit  9/20/2004 DONE
Override - Parcel Holds  9/17/2004  
Inspection Record Card- Bld  9/17/2004 DONE
Override - Parcel Holds  9/17/2004  
Permit Ready to Issue  9/17/2004 DONE
Telephone call  9/17/2004 DONE
spoke with Steed Construction -- permit is ready.
Routing - PLAN CHECK9/15/2004 9/16/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/16/2004 DONE
Override - Parcel Holds  9/16/2004  
Plan assigned to (M_P)2/2/2004 9/16/2004 PASS
DetailsMike Phillips
9/16/2004 09:43:09 M_P - activity updated through activity BLDA022 from case BLD04-00157.
Routing - Erosion and Sediment9/15/2004 9/15/2004 PASS
ESC approved with attached conditons.
Routing - PLAN CHECK9/14/2004 9/15/2004  
Routing to ESC for signatures.
Routing - PLANNING9/9/2004 9/14/2004 PASS
Ok per CUP03-60. KGallagher.
DRH signed off on previous date.
Routing - PLAN CHECK9/2/2004 9/9/2004  
Routing to Planning.
Routing - PLAN CHECK7/1/2004 9/2/2004  
Routed to Land Division.
Routing - PLANNING Land Div9/2/2004 9/2/2004 PASS
Vacation of easement approved by City Council on 8/31/04. Final letter of compliance on shell not to be issued until resolution is approved by City Council.--contact Dave Abo to verify if resolution is approved. (xref SOS04-00019)
Routing - PUBLIC WORKS6/29/2004 7/1/2004 PASS
Routing - PLAN CHECK5/17/2004 6/29/2004  
Routing to P.W.
Plan resubmittals received  6/28/2004 DONE
Received three copies of the recorded access easement agreement. Taken to Mike P. to put with plans.
Routing - PLAN CHECK5/12/2004 5/17/2004 PEND
Waiting for others to approve prior to issuing permit.
Routing - PLANNING Land Div5/12/2004 5/12/2004 FAIL
Need to vacate easement.
Routing - PUBLIC WORKS4/23/2004 5/12/2004 FAIL
per April Miller site plan doesn"t match ROS 6121 or easements.
Plan resubmittals received  4/30/2004 DONE
Received Transmittal Letter/ Memorandum. 1 set 2 sheets S4.0 Routed to Mike Phillips..
Routing - PLANNING4/16/2004 4/23/2004 FAIL
Routing - FIRE4/19/2004 4/23/2004 PASS
4/23-Okayed by DM. 4/21/04 resubmittal pending review/decision by DM re new DE roadway in excess of 700'
Plan resubmittals received  4/21/2004 DONE
Received two copies of revised stamped and signed structural calculations and sketch. Routed to Mike Phillips.
Routing - PLANNING4/16/2004 4/19/2004 FAIL
Need new easement. Need conceptual plan showing how sidewalk at southwest side of service drive will connect to future expansion on abutting parcel to the south.
Plan resubmittals received  4/19/2004 DONE
Received two copies of revised sheets A1.
Plan resubmittals received  4/19/2004 DONE
Received one copy of revised stamped and signed structural calculations and sketch. Routed to Mike P. kmm
Routing - PLAN CHECK4/12/2004 4/16/2004  
Routing to other departments.
Plan resubmittals received  4/13/2004 DONE
Received two response letters to Mike P, and Karen G. with one set of sheets S1.0,S1.1,S2.0,S3.0,S3.1 (2of S4.0),S4.1,S4.2 and three sheets of A1.0,taken to Mike P.
Routing Off Site - STRUCTURAL4/8/2004 4/13/2004 FAIL
Called PDQ for pickup.
Second review failed, faxed comments to architect requesting written responce. City plan reviewer will review written responce from architect.
Routing - PLANNING4/8/2004 4/9/2004 FAIL
Need two sidewalk revisions and easement per CUP03-60. KG
Plan resubmittals received  4/9/2004 DONE
Received response letter with, five sheets of Envelope Compliance, two M0.1 sheets taken to Mike P.
Routing - PLAN CHECK3/12/2004 4/8/2004 FAIL
Called architect requesting additional informtion be submitted for further review, also waiting for outside structural comments to be returned.
Plan resubmittals received  4/1/2004 DONE
Received a two response letters, one copy of structural response & calculations, Soil & foundation report, two sets of sheets T1.0,A1.0,A3.0,A3.1,A4.0,A5.0,A5.1,A6.0,A6.1,A7.0,A7.1,S1.0,S1.1,S2.0,S3.0,S3.1,S4.0,S4.1,S4.2,M0.1,E2.0, also received a response letter to Sam Rogers, United Water letter with two sets of sheets A1.0,C-1,C-2,C-3,C-5,taken to Mike P.
Routing - PLANNING3/30/2004 3/30/2004 PEND
Approved per DRH03-131. Please note that although the proposed quantity of parking spaces requires two additional handicap parking spaces, the two additional parking spaces may be constructed at the time the future building is constructed in order to coordinate with the entry of the future building. Also need CUP03-60 approval by KG.
Routing - Erosion and Sediment3/8/2004 3/10/2004 FAIL
ESC permit application does not list RP. Contacted Pat. Mck.
Routing - PLAN CHECK3/8/2004 3/8/2004  
Routing to ESC
Routing - FIRE3/4/2004 3/5/2004 FAIL
Hydrant location and FD access issues; no water flow info; review faxed to architect.
Plan resubmittals received  3/5/2004 DONE
Received three copies of Stormwater Pollution Prevention Plan with two copies of a transmittal letter taken to Mike P.
Routing - PLUMBING3/2/2004 3/4/2004 PASS
per plans and 2000 upc
Routing - PLAN CHECK2/19/2004 3/2/2004 FAIL
Plan review compoleted, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
Routing - PLANNING2/12/2004 2/19/2004 FAIL
Failed by KGallagher 2/12/04 * Airport Influence Area B1. Plans do not comply with CUP03-60 Conditions 1.A., 3, 10, possibly 11.
Routed to Marty Santoyo on 2/12/04 * Plans do not comply with DRH03-131conditions; please note the handicap accessible parking.
Routing - Erosion and Sediment2/10/2004 2/12/2004 FAIL
ESC incomplete. See ESC permit activity. Contacted Plan Designer.
Routing Off Site - STRUCTURAL2/2/2004 2/10/2004 FAIL
contacted PDQ for outside engineering.
Plan review completed, second review required by our outside engineerig fir.
Routing - PUBLIC WORKS2/3/2004 2/10/2004 FAIL
Site plan does not match ROS 6121 or easements per April Miller. Requires drainage plan three copies and O&M manual per Brian M. kmm
Routing - PLANNING Land Div2/2/2004 2/3/2004 FAIL
Need to vacate easement.
Plan routing begun/NEW & ADDTN  2/2/2004 DONE
Plans ACCEPTED BY PLAN TECH  2/2/2004 DONE
Envelope not signed I called Pat to let him know.
Application received  1/30/2004  
Recd Pcfee & Taken To Pln CK  1/30/2004  
Fee Review-notes1/30/20041/30/2004