Letter of compliance | | | 9/13/2004 | | DONE |
|
|
|
Letter of Compliance issued 9-13-04.
|
FIRE-Final Inspection | 9/1/2004 | 9/2/2004 | 9/2/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. Overspacing of the smoke heat vents was approved by Dave Miller on 9-1-04 as long as the approved smoke heat vents had been installed. Per the data sheets the smoke heat vents are approved. 9/2/2004 9:45:54 AM
|
BLD-Final | 9/1/2004 | 9/2/2004 | 9/2/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/1/2004 at 4:55:00 PM. Contact: ###-####. ok for perm 9/2/2004 3:13:58 PM
|
BLD-Final | 8/30/2004 | 8/31/2004 | 8/31/2004 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 8:19:48 PM. Contact: ###-####. needs fire ok 8/31/2004 3:32:43 PM
|
FIRE-Final Inspection | 8/30/2004 | 8/31/2004 | 8/31/2004 | A | FAIL |
Troy Cobbley
|
|
|
Space heat vents are overspaced. See review note "C". Provide data sheet for revised smoke heat vents. Manual type, as approved, was not installed. 8/31/2004 5:15:43 PM
|
BLD-Final | 8/30/2004 | 8/31/2004 | 8/30/2004 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 5:14:16 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 30 2004 8:18PM.
|
BLD-Final | 8/26/2004 | 8/27/2004 | 8/27/2004 | P | NR |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 8/26/2004 at 3:27:09 PM. Contact: ###-####.
fire insp. has correction issues, and additional final insp. to do before bldg. dept. final 8/27/2004 3:22:24 PM
|
BLD-Footing | 8/20/2004 | 8/20/2004 | 8/20/2004 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/20/2004 at 7:57:30 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/20/2004 | 8/20/2004 | 8/20/2004 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/20/2004 at 7:58:14 AM. Contact: ###-####.
|
BLD-Final | 8/20/2004 | 8/20/2004 | 8/20/2004 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/20/2004 at 7:58:59 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 7/7/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/1/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/1/2004 | | |
|
|
|
|
Telephone call | | | 7/1/2004 | | DONE |
|
|
|
left mess for trent koci at ###-#### that permit is ready
|
Routing - PLAN CHECK | 6/30/2004 | | 6/30/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2004 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 2/23/2004 | | 6/30/2004 | | PASS |
Mike Otto
|
|
|
6/30/2004 09:39:20 MLO - activity updated through activity BLDA022 from case BLD04-00279.
|
Routing - FIRE | 6/28/2004 | | 6/29/2004 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 6/10/2004 | | 6/15/2004 | | FAIL |
Bill Alexander
|
|
|
1. Lack "manual" part of the requirement for smoke heat venting.
2. Lack commodity type with maximum storage height requesting.
Called Trent Koci 10:25am, regarding "Tank Storage" access and he indicated that the "Tank Storage" is going away so end containmnet wall (for required back access door) is being demolished. Plan is redline corrected.
Faxed letter of requirements (attached).
|
Plan resubmittals received | | | 6/7/2004 | | DONE |
|
|
|
Received Transmittal Letter, 1 Set R-1 Taken to Mike Otto..
|
Routing - PLAN CHECK | 4/12/2004 | | 4/12/2004 | | NR |
|
|
|
|
Routing - FIRE | 4/7/2004 | | 4/9/2004 | | FAIL |
Bill Alexander
|
|
|
1. Not met. The (warehouse) facility will require building access meeting the requirements of IFC Table 2306.6 or otherwise approval from the Fire Chief.
2. Did not provide manufacturer documentation on operations and listings of smoke heat vents.
3. Did not address maximum storage height of commodities.
4. Need updated HAZMAT inventory statement/analysis review due to added storage system.
|
Routing - PLAN CHECK | 4/7/2004 | | 4/7/2004 | | PEND |
|
|
|
need FD approval
|
Plan resubmittals received | | | 4/6/2004 | | DONE |
|
|
|
Received letter of transmittal with two cover letter, two copies of calculations for skylights, two copies of sheets R-1,R-2 taken to Mike O.
|
Routing - PLAN CHECK | 3/4/2004 | | 3/5/2004 | | FAIL |
|
|
|
IBC corrections in accordance with IFC review. Corrections faxed to applicant. MLO
|
Routing - FIRE | 3/3/2004 | | 3/4/2004 | | FAIL |
Bill Alexander
|
|
|
A. Provide on the plan/s a standard and identifiable scale for dimensioning. (IFC 105.4.2)
B. This (warehouse) facility will require building access meeting the requirements of IFC Table 2306.6, which must be shown and associated with this building racking permit plans. Plans must include the whole unseperated warehouse along with outside building fire apparatus access. (IFC 105.4.2, 2301.3)
C. This (warehouse) facility will require smoke and heat removal meeting the requirements of IFC Table 2306.7, which must be shown and associated with this building racking permit plans. (IFC 105.4.2, 2301.3)
D. Provide on the plans the maximum storage height intending to incorporate in each or all racking (if similar) by identification. Fire sprinkler deflector's distance incorporating in this facility allow for a minimum 18" from top of any storage to deflector spacing. No storage shall be allowed above this minimum requirement. (NFPA 13:5-11.4.1).
E. Provide location of required fire extinguishers meeting requirements of IFC 2306.10 and 3403.2.1. Handle shall be mounted at 48" AFF. Extinguisher shall be conspicuously located where they will be readily accessible and immediately available in the event of fire or provided with identifiable signage which specifically identifies the extinguisher location.
F. Under delayed submittal and prior to installation, obtain a fire permit and approval after providing fire sprinkler plans, calculations and manufacturer data submittals meeting, but not limited too, the minimum requirements of IFC 2306.4, 2308. Submittals shall include, but may not be limited too the minimum requirements of NFPA 13 Chapter 14.
|
Plan Review Completed(1st rev) | | | 3/4/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/23/2004 | | 3/3/2004 | | PEND |
|
|
|
Pending Fire Code Review
|
Plans ACCEPTED BY PLAN TECH | | | 2/23/2004 | | DONE |
|
|
|
faxed over the certificate of value to get it signed.
|
Fee Review-notes | 2/20/2004 | 2/20/2004 | 2/20/2004 | | DONE |
|
|
|
|
Application received | | | 2/20/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/20/2004 | | DONE |
|
|
|
|